City of Toronto Storm Water Work Yonge & The Esplanade – October 11 – 13

Posted October 11

Please Note: 

    We have been advised that City of Toronto contractor OJCR will be working at Yonge Street and The Esplanade starting Friday night, October 11 through to Sunday, October 13, on storm water connections. We anticipate that there may be disruptions to traffic flow and possibly pedestrian access to The Esplanade from Yonge Street. 

The Esplanade reopens to vehicles btwn Yonge & Scott

Yesterday’s closure of the eastbound vehicle lane on The Esplanade between Yonge & Scott Street will end this afternoon with the reopening of the vehicle lane. Pedestrian access has been maintained throughout the day. 

The Backstage & L Tower Parking construction schedule for July 8 – 12 was unaffected by the storm and remains on track. Please click here to view it.

The Esplanade closed from Yonge to Scott

Please note that due to a water-main break earlier today on Front Street, east of Scott Street there are two temporary road closures:

  1. Front Street is closed from Scott Street to Church Street.
  2. Toronto Police Services and the City of Toronto Works Department have also asked for The Esplanade to be closed from Younge Street to Scott Street to minimize traffic in the area.

There is no information on the duration of this closure at this time. Once we have more information we will post it here.

Recap on Dec 5 Long Reach Back-hoe delivery

UPDATE: The Long Reach Back-hoe that was scheduled to arrive Wednesday, December 5, under police escort between 6:20 am and 7:00 am. It actually arrived at 5:30 am as the City of Toronto permit stipulated that the semi-trailer float (truck) had to be out of the downtown core prior to 6:00 am. Unfortunately we did not receive accurate information on the timing of the delivery.

On December 4 we were advised by subcontractor GFL Excavating that the back-hoe was coming early in the morning, instead of the originally and preferred plan to deliver it at midday. GFL could not get a permit for midday because City of Toronto staff considered the impact on daytime traffic would be too onerous. The permit was issued for 5 am to 6 am delivery and GFL was instructed by the City and the Police to have their large delivery truck off the site an out of the downtown by 6:00 am.

In this case the regulations for large deliveries trumped the regulations for construction noise; the regulating bodies determined that the traffic regulations trumped the standard construction noise regulations.  

Please click here for a revised Backstage – 1 The Esplanade construction schedule.

 
Please click here for a revised Backstage – 1 The Esplanade construction schedule.

L Tower Construction Schedule June 18 – 22

This is the current construction schedule for 8 The Esplanade – L Tower – for   June 18 – 22, 2012

Posted June 15, 2012

NOTE:

  • The L Tower is scheduled to reach 46 floors this week.

Monday, June 18

  • A rebar (steel) delivery starting at 7:00 am.
    • Please note that eastbound vehicular traffic may be interrupted during these deliveries.
    • Pedestrian traffic will remain open

Tuesday, June 19

  • A 220M (cubic metre) slab concrete pour, at level 46, starting at 9:00 am, which is not expected to extend beyond 7:00 pm.
  • A rebar (steel) delivery starting at 10:00 am.
    • Please note that eastbound vehicular traffic may be interrupted during these deliveries.
    • Pedestrian traffic will remain open

Wednesday, June 20

  • A 122M (cubic metre) part 1, wall and column concrete pour, levels 46 – 47, starting at 1 pm, which is not expected to extend beyond 7:00 pm.

Thursday, June 21

  • A 70M (cubic metre) part 2, wall and column concrete pour, levels 46 – 47, starting at 1 pm, which is not expected to extend beyond 7:00 pm.

Friday, June 22

  • A rebar (steel) delivery starting at 7:00 am.
    • Please note that eastbound vehicular traffic may be interrupted during these deliveries.
    • Pedestrian traffic will remain open

* * *

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage June 18 – 22 summary highlights: L Tower & Backstage Construction June 18-22

L Tower Construction Schedule June 11 – 15

This is the current construction schedule for 8 The Esplanade – L Tower – for   June 11 – 15, 2012

Posted June 8, 2012

NOTE:

  • The L Tower is scheduled to reach 45 floors this week.

Monday, June 11

  • A 101M (cubic metre) part 2, wall and column concrete pour, levels 44 – 45, starting at 1 pm, which is not expected to extend beyond 7:00 pm.
  • The hoist will be climbed (raised) three floors. 

Tuesday, June 12

  • A rebar (steel) delivery starting at 7:00 am.
    • Please note that eastbound vehicular traffic may be interrupted during these deliveries.
    • Pedestrian traffic will remain open

Wednesday, June 13

  • A rebar (steel) delivery starting at 7:00 am.
    • Please note that eastbound vehicular traffic may be interrupted during these deliveries.
    • Pedestrian traffic will remain open
  • A 220M (cubic metre) slab concrete pour, at level 45, starting at 10:00 am, which is not expected to extend beyond 7:00 pm.

Thursday, June 14

  • A 101M (cubic metre) part 1, wall and column concrete pour, levels 45 – 46, starting at 1 pm, which is not expected to extend beyond 7:00 pm.

Friday, June 15

  • A 101M (cubic metre) part 2, wall and column concrete pour, levels 45 – 46, starting at 1 pm, which is not expected to extend beyond 7:00 pm.

* * *

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage June 11 – 15 summary highlights: L Tower & Backstage Construction June 11-15

L Tower Concrete & Rebar, June 5, 2012

Concrete truck backing into the site at the L Tower, June 5, 2012

 

Concrete truck at the L Tower, June 5, 2012

 

Rebar delivery at the L Tower, June 5, 2012

 

Rebar delivery at the L Tower, looking east from Yonge Street, June 5, 2012

L Tower Construction Schedule May 22 – 26

This is the current construction schedule for 8 The Esplanade – L Tower – for  May  22 – 26, 2012

Posted May 18, 2012

Note: The L Tower is scheduled to reach 42 floors this week.

Monday, May 21 – Victoria Day Holiday 

Tuesday, May 22

  • Heat Pump delivery starting at 7:30 am, with the estimated completion of the delivery at 11:00 am. 
    • Please note there may be some short-term disruptions to eastbound vehicular traffic.
    • Pedestrian traffic will remain open.
  • A 92M (part 1) wall and column concrete pour, levels 41 – 42 starting at Noon, which is not expected to extend beyond 7:00 pm.

Wednesday, May 23

  • A 96M (part 2) wall and column concrete pour, levels 41 – 42 starting at Noon, which is not expected to extend beyond 7:00 pm.

Thursday, May 24

Friday, May 25

  • A 215M slab concrete pour, level 42, starting 10:00 am, which is not expected to extend beyond 7:00 pm.

Saturday, May 26

  • Hoist maintenance will commence at 9:00 am and the estimated completion time for this work is 1:00 pm.

* * *

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Tuesday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage May 22 – 26 summary highlights: L Tower & Backstage Construction May 22 – 26

L Tower Construction Schedule April 23 – 27

This is the current construction schedule for 8 The Esplanade – L Tower for April 23 – 27, 2012

Posted April 20, 2012

Note: The L Tower is scheduled to reach 38 floors this week.

Monday, April 23

  • Window delivery starting at 7:00 am.
  • Rebar delivery starting at 10:00 am.
  • A 190M slab concrete pour, level 37, starting 10:00 am, which is not expected to extend beyond 7:00 pm.

Tuesday, April 24

  • Window delivery starting at 7:00 am.
  • A 99M (part 1) wall and column concrete pour, levels 37 – 38 starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Wednesday, April 25

  • Rebar delivery starting at 12:30 pm. 
  • A 108M (part 2) wall and column concrete pour, levels 36 – 37, starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Thursday, April 26

  • Rebar delivery starting at 7:00 am.
  • Rebar delivery starting at 12:30 pm.

Friday, April 27

  • Rebar delivery starting at 7:00 am.
  • A 190M slab concrete pour, level 38, starting 10:00 am, which is not expected to extend beyond 7:00 pm.

* * *

NOTES:

Construction schedules are dependent on weather conditions.

A Paid Duty Police Officer is on-site daily Monday to Thursday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 23 – 27 summary highlights:  L Tower & Backstage Construction April 23-27

L Tower Construction Schedule April 9 – 13

This is the current construction schedule for 8 The Esplanade – L Tower for April 9 – 12, 2012

Posted April 7, 2012

Note: The L Tower is scheduled to reach 35 floors this week.

Monday, April 9

  • Heat Pump (for individual condo suites) delivery starting at 7:30 am.
  • A 108M (part 2) wall and column concrete pour, levels 34 – 35, starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

Tuesday, April 10

  • Rebar delivery starting at 7:00 am.
  • Window delivery starting at 7:00 am.
  • Rebar delivery starting at 12:30 pm

Wednesday, April 11

  • Rebar delivery starting at 7:00 am.
  • Rebar delivery starting at 10:00 am.
  • A 190M slab concrete pour, level 35, starting 10:00 am, which is not expected to extend beyond 7:00 pm.

Thursday, April 12

  • A 99M (part 1) wall and column concrete pour, levels 35 – 36 starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

  Friday, April 13

  • Rebar delivery starting at 12:30 pm.
  • A 108M (part 2) wall and column concrete pour, levels 35 – 36, starting 1:00 pm, which is not expected to extend beyond 7:00 pm.

* * *

NOTES:

Construction schedules are dependent on weather conditions.

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 9 – 13 summary update: 1+8 The Esplanade – Construction Notice-April-9-13

%d bloggers like this: