Backstage & L Tower Construction Schedule for March 8

This is the construction schedule for 1 The Esplanade – Backstage condominium & 8 The Esplanade – L Tower  for  March 8, 2014.

Please click here for general information on concrete pours.

Backstage 

Saturday, March 8

  • Small carpenter crew from the Forming company will be working on crash wall from 9:00 am.
  • A Dominus crew  will be on-site doing house keeping tasks, working from 9:00 am to 1:00 pm.

 L Tower

Saturday, March 8

  •  Staff will be at work inside the tower from 7:00 am.
  • Crane, bobcat and hoist work will begin after 9:00 am.

Please Note: Any work involving construction noise will be scheduled to begin at or after 9:00 am.

Backstage & L Tower Construction Schedule for March 1

This is the construction schedule for 1 The Esplanade – Backstage condominium & 8 The Esplanade – L Tower  for  March 1, 2014.

Please click here for general information on concrete pours.

Backstage 

Saturday, March 1

  • Fourth floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 9:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. 
  • Concrete Finishing to 10:30 pm.

 L Tower

Saturday, March 1

  •  Weather Permitting the Hoist will be raised and Window Work will be undertaken. 

Please Note: Any work involving construction noise will be scheduled to begin at or after 9:00 am.

L Tower quick facts

Some quick facts about the construction of the L Tower

    rr

  • The  L Tower reached 28 floors as of the week ending February 24th 2012.
    rr

  • Since construction began 16,230M of concrete have been poured to-date.
    rr

  • The L Tower’s glazing system is part curtain wall and part window wall system.
      rr

    • Windows are brought up into the building through the means of our material hoist.
    • These windows are then distributed on the appropriate floors and then installed from inside the building.

rr