L Tower Update October 25 – 31

This is the current construction schedule for 8 The Esplanade – L Tower  October 25 – 31, 2014

NOTE: New residents are continuing to move into the L Tower When moves occur they are loading in on Yonge Street. As external construction comes closer to completion, the dimensions of the future sidewalk area on the north side of The Esplanade is beginning to emerge.  

Saturday, October 25

  • Interior work on site.
  • Move-ins through the Yonge Street entrance.

Monday, October 27

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Tuesday, October 28

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Wednesday, October 29

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Thursday, October 30

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Friday, October 31

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

L Tower Update October 18 – 24

This is the current construction schedule for 8 The Esplanade – L Tower  October 18 – 24, 2014

NOTE: New residents are continuing to move into the L Tower When moves occur they are loading in on Yonge Street. As external construction comes closer to completion, the dimensions of the future sidewalk area on the north side of The Esplanade is beginning to emerge.  

L Tower at 8 The Eslpanade

L Tower at 8 The Esplanade

Saturday, October 18

  • Interior work on site.
  • Move-ins through the Yonge Street entrance.

Monday, October 20

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Tuesday, October 21

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Wednesday, October 22

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Thursday, October 23

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Friday, October 24

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

L Tower Update October 14 – 17

This is the current construction schedule for 8 The Esplanade – L Tower  October 14 – 17, 2014

NOTE: Initial occupants continue to move-in to the L Tower. Move-ins are loading in on Yonge Street. With the building close to being substantially completed, work continue on the sidewalks on Yonge Street and The Esplanade. 

Tuesday, October 14

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Wednesday, October 15

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Thursday, October 16

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Friday, October 17

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

L Tower Update October 11 – 13

This is the current construction schedule for 8 The Esplanade – L Tower  October 11 – 13, 2014

NOTE: Initial occupants have begun to move-in to the L Tower. Moves are loading in on Yonge Street. With the building close to being substantially completed, work will begin in the coming weeks on the sidewalks on Yonge Street and The Esplanade. 

L Tower October 10

L Tower & CN Tower October 10, 2014

Saturday, October 11

  • Some interior work on site.

Monday, October 13 – Site Closed for the Thanksgiving Holiday! 

NOTE: The construction update for Tuesday, October 14 – Friday, October 17, will be posted by Tuesday morning, October 14. 

L Tower Update October 4 – 10

This is the current construction schedule for 8 The Esplanade – L Tower  October 4 – 10, 2014

NOTE: Initial occupants are beginning to move-in to the L Tower. When moves occur they are loading in on Yonge Street. With the building close to being substantially completed, work will begin in the coming weeks on the sidewalks on Yonge Street and The Esplanade. 

L Tower and Crane

L Tower crane October 2, 2014

Saturday, October 4

  • Interior work on site.

Monday, October 6

  • There will be general construction work inside the L Tower.
  •  Move-ins continue through the Yonge Street entrance.

Tuesday, October 7

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Wednesday, October 8

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Thursday, October 9

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

Friday, October 10

  • There will be general construction work inside the L Tower.
  • Move-ins continue through the Yonge Street entrance.

L Tower Construction Schedule September 27 – October 3

This is the current construction schedule for 8 The Esplanade – L Tower  – September 27 – October 3, 2014

NOTE: Initial occupants are beginning to arrange their move-ins to the L Tower. When moves occur they will be loading in on Yonge Street, with no expected impacts on The Esplanade. With the building close to being substantially completed, work will begin in the coming weeks on the sidewalks, starting on the Yonge Street side of the project. 

 

L Tower on The Esplanade

L Tower on The Esplanade

Saturday, September 27

  • Interior work on site.

Monday, September 29

  • There will be general construction work inside the L Tower.
  •  Window wall installation.

Tuesday, September 30

  • There will be general construction work inside the L Tower.
  • Window wall installation.

Wednesday, October 1

  • There will be general construction work inside the L Tower.
  • Window wall installation.

Thursday, October 2

  • There will be general construction work inside the L Tower.
  • Window wall installation.

Friday, October 3

  • There will be general construction work inside the L Tower.
  • Window wall installation.

L Tower Construction Schedule September 20 – 26

This is the current construction schedule for 8 The Esplanade – L Tower  – September 20 – 16, 2014

As we noted in an earlier post, move-ins to the L Tower may begin this week; more information will be posted when relevant and available. 
L Tower B x W

 

Saturday, September 20

  • Some interior work on site.
  • Window wall installation.

Monday, September 22

  • There will be general construction work inside the L Tower.
  •  Window wall installation.

Tuesday, September 23

  • There will be general construction work inside the L Tower.
  • Window wall installation.

Wednesday, September 24

  • There will be general construction work inside the L Tower.
  • Window wall installation.

Thursday, September 25

  • There will be general construction work inside the L Tower.
  • Window wall installation.

Friday, September 26

  • There will be general construction work inside the L Tower.
  • Window wall installation.

L Tower Construction Schedule September 13 – 19

This is the current construction schedule for 8 The Esplanade – L Tower  – September 13 – 19, 2014

L Tower September 12, 2014

L Tower September 12, 2014

Saturday, September 13

  • Some interior work on site.
  • Window wall installation.

Monday, September 15

  • There will be general construction work inside the L Tower.
  •  Window wall installation.

Tuesday, September 16

  • There will be general construction work inside the L Tower.
  • Window wall installation.

Wednesday, September 17

  • There will be general construction work inside the L Tower.
  • Window wall installation.

Thursday, September 18

  • There will be general construction work inside the L Tower.
  • Window wall installation.

Friday, September 19

  • There will be general construction work inside the L Tower.
  • Window wall installation.
%d bloggers like this: