Backstage Construction Schedule April 20 – 24, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for April 20 – 24, 2015. 

Work on the podium deck outdoor swimming pool and interior suite drywall work are the main construction activities this week. 

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Apr-20-24-2015

Backstage swimming pool on the podium deck

Backstage swimming pool on the podium deck

 Monday, April 20

  • Drywall delivery from 8:00 am to 1:00 pm.
  • Waterproofing 5th floor podium.
  • Interior suite drywall and finishing.

Tuesday, April 21

  • Concrete pour for the podium deck swimming pool starting at 11:00am, concrete finishing till 9:00pm
  • Interior suite drywall and finishing.
  • Waterproofing 5th floor podium.

Wednesday, April 22

  • Working on 5th floor swimming pool.
  • Waterproofing main roof.
  • Interior suite drywall and finishing.

Thursday, April 23

  • Working on 5th floor swimming pool.
  • Waterproofing main roof.
  • Interior suite drywall and finishing.

Friday, April 24

  • Working on 5th floor swimming pool.
  • Waterproofing main roof.
  • Interior suite drywall and finishing.
Yonge Street Railway Bridge - future PATH connection to Union Station.

Yonge Street Railway Bridge – future PATH connection to Union Station.

 NOTES:

    • All rebar deliveries are now complete.
    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete or delivery trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule April 13 – 17, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for April 13 – 17, 2015. 

Last concrete pour for the tower and work on the podium deck outdoor swimming pool are the main construction activities this week. 

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Apr-13-17-2015

Backstage Swimming Pool on the Podium Deck looking east from the tower.

Backstage Swimming Pool on the Podium Deck looking east from the tower.

 Monday, April 13

  • Last concrete pour for the tower, elevator curbs on the roof (8 meters of concrete), starting at 12:00 pm. 
  • Interior suite drywall and finishing.

Tuesday, April 14

  • Subcontractor Italform demobilizing their equipment and materials.
  • Working on 5th floor swimming pool.
  • Waterproofing 5th floor podium.
  • Interior suite drywall and finishing.
  • 35th floor Window delivery occupying north curb lane of the Esplanade, starting at 2:00 pm to approximately 4:00 pm.

Wednesday, April 15

  • Subcontractor Italform demobilizing their equipment and materials.
  • Working on 5th floor swimming pool.
  • Waterproofing 5th floor podium.
  • Interior suite drywall and finishing.

Thursday, April 16

  • Subcontractor Italform demobilizing their equipment and materials.
  • Working on 5th floor swimming pool.
  • Waterproofing 5th floor podium.
  • Interior suite drywall and finishing.

Friday, April 17

  • Subcontractor Italform demobilizing their equipment and materials.
  • Working on 5th floor swimming pool.
  • Waterproofing 5th floor podium.
  • Interior suite drywall and finishing.
Backstage tower south west elevation

Backstage tower south west elevation

 NOTES:

    • All rebar deliveries are now complete.
    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete or delivery trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Backstage Saturday, February 14, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for Saturday, February 14, 2015.  

Note: Extreme cold weather continues to cause delays and rescheduling of concrete pours and deliveries. 

The current Backstage "construction streetscape" will be replaced by a broad sidwalk, trees, animated by retail and the entrance to the new public exhibit space on the second floor of the building.

The current Backstage “construction streetscape” will be replaced by a broad sidewalk, trees, animated by retail and the entrance to the new public exhibit space on the 2nd floor.

Saturday, February 14

  • Weather permitting, a window delivery is scheduled to bring window and glazing for 2 floors, starting at 9:00am.

The construction schedule for Monday, February 16 – Friday, February 20 was not available at post time. We will post that information by Tuesday morning. Please check back. 

Backstage Construction Schedule November 22 – 28

UPDATED November 25–This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for November 22 – 28, 2014.

Backstage, south west corner, November 21, 2014

Backstage, south west corner, November 21, 2014

Saturday, November 22

  • Subcontractor, Italform doing high elevation rescue training off the crane.
    Please Note: During the training a dummy will be dropped and “rescued.”
  • Dominus construction crew doing housekeeping work on-site, from 9:00 am. 
  • Electrical and plumbing subcontractors working in the building from 9:00 am.

Monday, November 24

  • CANCELLED – 28thFloor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:30 am.
  • After slab, wall concrete pour (45 metres of concrete). 
  • Concrete Finishing until to 10:30 pm.

Tuesday, November 25

  • Rebar delivery, scheduled to begin at 7:00 am.
  • Rescheduled from Monday: 28thFloor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:30 am.
  • After slab, wall concrete pour (45 metres of concrete). 
  • Concrete Finishing until to 10:30 pm.

Wednesday, November 26

  • 28th Floor slab concrete pour 3, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (42 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

ThursdayNovember 27

  • Rebar delivery from 7:00 am.
  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Friday, November 28

  • 29th Floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (42 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

 NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule November 17 – 21

UPDATED – November 19

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for November 17 – 21, 2014.

Backstage parking entrance interior

Backstage parking entrance interior

Monday, November 17

  • The Esplanade will be closed during the day to eastbound vehicle traffic by contractor Distinct Tech. They will be installing conduits for fibre-optic cable for Beanfield Metroconnect.
    • Please note: Beanfield Metroconnect schedules their own work and is responsible for relevant permits and did not advise on-site construction managers of the scheduling of this work prior to late Friday, November 14. 
  • CANCELLED – 27thFloor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 10:30 am.
  • Cancelled – Concrete Finishing until to 10:30 pm.

Tuesday, November 18

  • Rebar delivery, scheduled to begin at 7:00 am.
  • CANCELLED – A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Wednesday, November 19

  • 27th Floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (33 metres of concrete) to begin following the main slab pour till 8:30 pm.
  • Concrete Finishing until to 10:30 pm.

ThursdayNovember 20

  • Rebar delivery from 7:00 am.
  • 28thFloor slab concrete pour 1, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (42 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

Friday, November 21

  • 28th Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (42 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

 NOTES:

    • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule November 8 – 14

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for November 8 – 14, 2014.

Please note: there will be a road closure of The Esplanade from Yonge Street to Scott Street from 9:00 am to 7:00 pm Monday, November 10 and Tuesday November 12. A copy of the ROAD CLOSURE PERMIT for November 10 – 11 is provided here: SBACKSTAGE 14110715270. Pedestrian access will be provided, as safety permits, on the north side The Esplanade adjacent the L Tower. 

The crane at Backstage seen from the 36th floor of the L Tower

The crane at Backstage seen from the 36th floor of the L Tower

Saturday, November 8

  • Subcontractor, Italform doing high elevation rescue training off the crane.
  • Dominus construction crew doing housekeeping work on-site, from 9:00 am. 
  • Electrical and plumbing subcontractors working in the building from 9:00 am.

Monday, November 10

  • Rebar delivery from 7:00 am.
  • ROAD CLOSURE OF THE ESPLANADE – 9:00 am – 7:00 pm to permit relocation of the hoardings and concrete barriers.
  • Pedestrians will be permitted access to Yonge Street on the north side of The Esplanade adjacent to the L Tower.
  • 2 Paid Duty Police Officers will be on site.
  • Please click on the link to the right to view or download the Road Closure Permit: SBACKSTAGE 14110715270
  • 26thFloor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (42 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

Tuesday, November 11

  • ROAD CLOSURE OF THE ESPLANADE – 9:00 am – 7:00 pm to permit relocation of the hoardings and concrete barriers.
  • Pedestrians will be permitted access to Yonge Street on the north side of The Esplanade adjacent to the L Tower.
  • 2 Paid Duty Police Officers will be on site.
  • Please click on the link to the right to view or download the Road Closure Permit: SBACKSTAGE 14110715270
  • 26thFloor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (33 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

Wednesday, November 12

  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

ThursdayNovember 13

  • Rebar delivery from 7:00 am.
  • 27thFloor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (33 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

Friday, November 14

  • 27th Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (33 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

 NOTES:

    • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule November 1 – 7

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for November 1 – 7, 2014

 Please click here for general information on concrete pours

Backstage condominium October 31, 2014

Backstage condominium October 31, 2014

Saturday, November 1

  • Dominus construction crew doing housekeeping work on-site, from 9:00 am. 
  • Electrical and plumbing contractors working in the building from 9:00 am.

Monday, November 3

  • Rebar delivery from 7:00 am.
  • 25thFloor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

Tuesday, November 4

  • Rebar delivery from 7:00 am.
  • 25thFloor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

Wednesday, November 5

  • 25thFloor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

ThursdayNovember 6

  • Rebar delivery from 7:00 am.
  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Friday, November 7

  • 26th Floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

 NOTES:

    • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule October 25 – 31

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for October 25 – 31, 2014

 Please click here for general information on concrete pours

Backstage with concrete bucket.

Backstage with concrete bucket.

Saturday, October 25

  • Dominus construction crew doing housekeeping work on-site, from 9:00 am. 
  • Electrical and plumbing contractors working in the building from 9:00 am.

Monday, October 27

  • 24thFloor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.
  • Window delivery starting at 9:00am, south curb lane of The Esplanade will be occupied. from 2:00 pm to 5:00 pm

Tuesday, October 28

  • Rebar delivery from 7:00 am.
  • 24thFloor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

Wednesday, October 29

  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Thursday, October 30

  • 24th Floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab wall and column concrete pour (36 metres of concrete) to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

Friday, October 31

  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

 NOTES:

    • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule Saturday, September 20

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for Saturday, September 20

Backstage windows in black & white.

Backstage windows in black & white.

Saturday, September 20

  • Toro Aluminum will be delivering a tractor trailer load of windows starting at 1:00 pm and running until 5:00 pm.
  • Italform with small crew raising platform on south side from 9:00 am.
  • Dominus doing housekeeping from 9:00 am.

Backstage Construction Schedule September 13 – 19

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for September 13 – 19, 2014. UPDATED September 18.

Backstage condominium first floor of windows installed.

Backstage condominium first floor of windows installed.

 Please click here for general information on concrete pours

Saturday, September 13

  • Protective platform to be raised , by subcontractor Italform, scheduled to begin at 9:00 am.
  • Dominus crew testing the internal hoist and doing housekeeping duties on-site.

Monday, September 15

  • 17th Floor slab concrete pour #3, PART 2, by subcontractor Italform, scheduled to begin at 11:30 am.
  • An after-slab concrete pour for 9th floor walls and columns, 33 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

Tuesday, September 16

  • Rebar delivery from 7:00 am.
  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Wednesday, September 17

  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Thursday, September 18

  • 18th  Floor slab concrete pour #1, PART 1, by subcontractor Italform, scheduled to begin at 11:30 am.
  • An after-slab concrete pour for 9th floor walls and columns, 33 metres of concrete, to begin following the main slab pour.
  • NEW: Subcontractor, Italform will be raising the crane 3 storeys between 3 pm and 7 pm.
  • Concrete Finishing until to 10:30 pm.

Friday, September 19

  • Rebar delivery from 7:00 am.
  • 18th Floor slab concrete pour #1, PART 2, by subcontractor Italform, scheduled to begin at 11:30 am.
  • An after-slab concrete pour for 9th floor walls and columns, 33 metres of concrete, to begin following the main slab pour.
  • NEW: Toro Aluminum will be delivering a tractor trailer load of windows starting at 3:00 pm and running until 7:00 pm
  • Concrete Finishing until to 10:30 pm.

 NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.