Backstage Construction Schedule April 20 – 24, 2015
April 20, 2015 Leave a comment
This is the current construction schedule for 1 The Esplanade, Backstage condominium – for April 20 – 24, 2015.
Work on the podium deck outdoor swimming pool and interior suite drywall work are the main construction activities this week.
Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Apr-20-24-2015
Monday, April 20
- Drywall delivery from 8:00 am to 1:00 pm.
- Waterproofing 5th floor podium.
- Interior suite drywall and finishing.
Tuesday, April 21
- Concrete pour for the podium deck swimming pool starting at 11:00am, concrete finishing till 9:00pm.
- Interior suite drywall and finishing.
- Waterproofing 5th floor podium.
Wednesday, April 22
- Working on 5th floor swimming pool.
- Waterproofing main roof.
- Interior suite drywall and finishing.
Thursday, April 23
- Working on 5th floor swimming pool.
- Waterproofing main roof.
- Interior suite drywall and finishing.
Friday, April 24
- Working on 5th floor swimming pool.
- Waterproofing main roof.
- Interior suite drywall and finishing.
NOTES:
- All rebar deliveries are now complete.
- A Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete or delivery trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.