Transportation & Delivery Issues Impact Backstage today.

The expected Wide-Load steel delivery was CANCELLED today, September 18, due to traffic and transportation issues beyond the control of the construction management team.

This serious transportation and delivery issue may impact the deliveries planned for September 19 – 21st. This may involve canceling some or all of the remaining daytime (7 am – 6 pm) road closure for September 19 – 21 and rescheduling it. 

We will update information regarding planned deliveries and the road closure for September 19 – 21 as soon as it becomes available.

Wide-load steel deliveries to Backstage Sept 18 – 21

Wide-Load CANCELLED due to traffic and transportation issues — Please note that there will be wide-load steel deliveries under police escort to the Backstage construction site each morning from September 18 – 21 — We will update information regarding September 19 -21 as soon as it becomes available. 

  • These deliveries will be made to the site at 1 The Esplanade, via Scott Street, during the daily — September 18 – 21, 7 am to 6 pm — road closure period.
  • We expect the loads will arrive between 7 am and 10 am depending on traffic and road conditions.
  • We will update this information if there are changes to the delivery schedule or as new information becomes available.

The construction  management team apologizes for any inconvenience. All efforts will be made to ensure that this work is carried out as efficiently as possible. 