Backstage Construction Schedule June 6-12, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for June 6 – 12, 2015. 

NOTE: Cable Control Systems was delayed last week and will now be on site this week on The Esplanade digging trenches to lay cable for Rogers to service Backstage. The cable work will temporarily disrupt traffic along The Esplanade. Cable Control Systems will be applying for any relevant permits. 

Click on the link for a downloadable PDF June 6 – 12 Construction Summary: Backstage & L Tower Construction Summary-June 6-12-2015

Backstage suite kitchen June 5

Backstage suite kitchen June 5

Saturday, June 6

  • Interior suite work: drywall and finishing.
  • On-site housekeeping.

Monday, June 8 

  • Cable Control Systems for Rogers will be digging trenches for incoming services for Backstage.
  • NOTE: The cable work will disrupt traffic along The Esplanade. Cable Control Systems will be applying for any relevant permits. 
  • Interior suite finishing all day.
  • Toro Aluminum will be delivering windows for the roof. Their truck will occupy the south curb lane on The Esplanade from 8:00 am to approximately 12:00 pm.
  • Drywall delivery from 12:00 pm to 4:00 pm.

Tuesday, June 9

  • Cable Control Systems for Rogers will be digging trenches for incoming services for Backstage.
  • NOTE: The cable work will disrupt traffic along The Esplanade. Cable Control Systems will be applying for any relevant permits. 
  • Interior suite work: drywall and finishing.

Wednesday, June 10

  • Tile and Kitchen delivery after 7:00 am.
  • Drywall delivery after 12:00 pm
  • Interior suite work: drywall and finishing.

Thursday, June 11

  • Interior suite finishing all day.
  • Toro Aluminum will be delivering windows for the roof. Their truck will occupy the south curb lane on The Esplanade from 8:00 am to approximately 12:00 pm.

Friday, June 12

  • Cooltech and Professional Carpentry deliveries after 7:00 am.
  • Interior suite work: drywall and finishing all day.
Backstage interior work

Backstage interior work

 NOTES:

    • All rebar deliveries are now complete.
    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete or delivery trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule May 30 – June 5, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for May 30 – June 5, 2015. 

NOTE: Cable Control Systems (for Rogers) and Distinct Tech (for Beanfeild) will be digging for incoming services to Backstage on June 2 – 4. The cable work will temporarily disrupt traffic along The Esplanade. Cable Control Systems and Distinct Tech will be applying for any relevant permits. 

Backstage sans crane.

Backstage sans crane.

Click on the link for a downloadable PDF May 30 – June 5 Construction Summary: Backstage & L Tower Construction Summary-May 30-June 5-2015

South view from the 8th floor of Backstage

South view from the 8th floor of Backstage

Saturday, May 30

  • Interior suite work: drywall and finishing.
  • Exterior preparation work for cable laying next week with a mini excavator and breaker hammer, starting at 9:00 am.

Monday, June 1 

  • Interior suite finishing all day.
  • Toro railing delivery from 8:00 am to 12:00 pm.
  • Drywall delivery from 12:00 pm to 4:00 pm.

Tuesday, June 2

  • Cable Control Systems for Rogers and Distinct Tech for Beanfeild will be digging for incoming services for Backstage.
  • NOTE: The cable work will disrupt traffic along The Esplanade. Cable Control Systems and Distinct Tech will be applying for any relevant permits. 
  • Drywall delivery from 8:00 am to 12:00 pm
  • Interior suite work: drywall and finishing.

Wednesday, June 3

  • Cable Control Systems for Rogers and Distinct Tech for Beanfeild will be digging for incoming services for Backstage.
  • NOTE: The cable work will disrupt traffic along The Esplanade. Cable Control Systems and Distinct Tech will be applying for any relevant permits. 

Thursday, June 4

  • Cable Control Systems for Rogers and Distinct Tech for Beanfeild will be digging for incoming services for Backstage.
  • NOTE: The cable work will disrupt traffic along The Esplanade. Cable Control Systems and Distinct Tech will be applying for any relevant permits. 

Friday, June 5

  • Interior suite work: drywall and finishing all day.
Backstage interior work.

Backstage interior work.

 NOTES:

    • All rebar deliveries are now complete.
    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete or delivery trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule May 23 – 29, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for May 23 – 29, 2015. 

NOTICE: May 26, 27 & 28 the tower crane will be taken down from Backstage, The Esplanade will be closed to traffic from Yonge to the Novotel (east of Scott) from 7:00 am to 11:00 pm. There will be no access to Scott Street from The Esplanade. Pedestrian access to Yonge Street will be closed while the crane is taken down. 5 Paid Duty Police Officers will be on site to direct vehicular and pedestrian traffic. If and when safety permits, every effort will be made to permit pedestrian access to Yonge Street. However it is prudent to plan on having to use Front Street East during the crane removal work. 

Preliminary map of the May 26 - 28, Road Closure on The Esplanade

Preliminary map of the May 26 – 28, Road Closure on The Esplanade

Click on the link for a downloadable PDF May 23 – 29 Construction Summary: Backstage & L Tower Construction Summary-May 23-29-2015

May 26 – 28 City of Toronto Road Closure Permit: May 26 – 28 Road Closure Permit 13 The Esplanade St E

Backstage & L Tower Cranes as seen from Queen's Quay

Backstage & L Tower Cranes as seen from Queen’s Quay

Saturday, May 23

  • Interior suite work: drywall and finishing.
  • Site housekeeping work.

Monday, May 25 

  • Interior suite finishing all day.
  • Tile delivery from 8:00 am to 11:00 am.
  • Drywall delivery from 12:00 pm to 4:00 pm.

Tuesday, May 26

  • Dismantling tower crane, vehicular and pedestrian traffic on The Esplanade will be closed. There will be five (5) Paid Duty Police Officers on-site to direct vehicular and pedestrian traffic. Road Closure Permit Hours 7:00 am to 11:00 pm.
  • NOTE: Pedestrian access to Yonge Street on The Esplanade will be closed or restricted. However, every effort will be made to permit pedestrian access through the site when and if it is safe to do.
  • Interior suite work: drywall and finishing.

Wednesday, May 27

  • Dismantling tower crane, vehicular and pedestrian traffic on The Esplanade will be closed. There will be five (5) Paid Duty Police Officers on-site to direct vehicular and pedestrian traffic. Road Closure Permit Hours 7:00 am to 11:00 pm.
  • NOTE: Pedestrian access to Yonge Street on The Esplanade will be closed or restricted. However, every effort will be made to permit pedestrian access through the site when and if it is safe to do.
  • Interior suite work: drywall and finishing.

Thursday, May 28

  • Dismantling tower crane, vehicular and pedestrian traffic on The Esplanade will be closed. There will be five (5) Paid Duty Police Officers on-site to direct vehicular and pedestrian traffic. Road Closure Permit Hours 7:00 am to 11:00 pm.
  • NOTE: Pedestrian access to Yonge Street on The Esplanade will be closed or restricted. However, every effort will be made to permit pedestrian access through the site when and if it is safe to do.
  • Interior suite work: drywall and finishing.

Friday, May 29

  • Interior suite work: drywall and finishing all day.
  • Kitchen delivery from 8:00 am to 10:00 am
  • Toro Railing delivery from 10:00 am to 12:00 pm
View northwest from the 8th floor of Backstage

View northwest from the 8th floor of Backstage

 NOTES:

    • All rebar deliveries are now complete.
    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete or delivery trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule May 16 – 22, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for May 16 – 22, 2015. 

ADVANCE NOTICE: May 26, 27 & 28 the tower crane will be taken down from Backstage, The Esplanade will be closed to traffic from Yonge to the Novotel (east of Scott) and there will be no access to Scott Street from The Esplanade. Pedestrian access to Yonge Street will be closed while the crane is taken down. Please click here for more information. 

Click on the link for a downloadable PDF May 16 – 22 Construction Summary: Backstage & L Tower Construction Summary-May 16-22-2015

Backstage tower crane, to be removed May 26 - 27

Backstage tower crane, to be removed May 26 – 27

Saturday, May 16

  • Interior suite work: drywall and finishing.

MONDAYVICTORIA DAY – site closed 

Looking up the elevator shaft at Backstage

Looking up the elevator shaft at Backstage

Tuesday, May 19

  • Steel stud delivery for 19th floor, from 8:00 am to 12:00 pm 
  • Drywall delivery, from 1:00 pm to 4:00 pm
  • Interior suite work: drywall and finishing.

Wednesday, May 20

  • Interior suite work: drywall and finishing.

Thursday, May 21

  • Interior suite work: drywall and finishing.
  • Kitchen delivery for the 9th and 10th floors.

Friday, May 22

  • Interior suite work: drywall and finishing.
Suites coming together at Backstage

Suites coming together at Backstage

 NOTES:

    • All rebar deliveries are now complete.
    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete or delivery trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule May 9 – 15, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for May 9 – 15, 2015. 

Interior suite work, equipment material deliveries and podium deck clean-up are the main construction activities this week.

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-May 9-15-2015

8th Floor balcony view from Backstage, looking west to Union Station and the CN Tower.

8th Floor balcony view from Backstage, looking west to Union Station and the CN Tower.

Saturday, May 9

  • Interior suite work: drywall and finishing.

 

8th Floor suite at Backstage, facing north.

8th Floor suite at Backstage, facing north.

Monday, May 11

  • Subcontractor Itlaform cleaning up materials the podium deck.
  • Interior suite work: drywall and finishing.

Tuesday, May 12

  • Delivery of the chiller to the site. Some short-term impacts on traffic will occur.
  • Subcontractor Itlaform cleaning up materials the podium deck.
  • Interior suite work: drywall and finishing.
Outdoor pool at Backstage on the podium roof deck.

Outdoor pool at Backstage on the podium roof deck.

Wednesday, May 13

  • Subcontractor Itlaform cleaning up materials the podium deck.
  • Interior suite work: drywall and finishing.

Thursday, May 14

  • Interior suite work: drywall and finishing.

Friday, May 15

  • Interior suite work: drywall and finishing.
8th Floor suite at Backstage facing west.

8th Floor suite at Backstage facing west.

 NOTES:

    • All rebar deliveries are now complete.
    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete or delivery trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule May 2 – 8, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for May 2 – 8, 2015. 

Work on the podium deck outdoor swimming pool, interior suite work and material deliveries are the main construction activities this week. 

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-May 2-8-2015

Backstage podium deck - outdoor swimming pool

Backstage podium deck – outdoor swimming pool

Saturday, May 2

  • Interior suite work: drywall and finishing.

 Monday, May 4

  • Drywall delivery for the 17th Floor.
  • Interior suite work: drywall and finishing.

Tuesday, May 5

  • Delivery of roofing material.
  • Interior suite work: drywall and finishing.

Wednesday, May 6

  • Subcontractor Itlaform pouring concrete for the 5th floor outdoor swimming pool, from 1:00 pm.
  • Interior suite work: drywall and finishing.

Thursday, May 7

  • Interior suite work: drywall and finishing.

Friday, May 8

  • Wood trim delivery from 7:00 am
  • Interior suite work: drywall and finishing.
Backstage Interior with drywall

Backstage Interior with drywall

 NOTES:

    • All rebar deliveries are now complete.
    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete or delivery trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule April 25 – May 1, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for April 25 – May 1, 2015. 

Work on the podium deck outdoor swimming pool and interior suite drywall work are the main construction activities this week. 

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Apr-25-May 1-2015

South side of Backstage at the railway tracks

South side of Backstage at the railway tracks

Saturday, April 25

  • Subcontractor Itlaform forming the 5th floor outdoor swimming pool.
  • Interior suite drywall and finishing.

 Monday, April 27

  • Subcontractor Itlaform forming the 5th floor outdoor swimming pool.
  • Interior suite drywall and finishing.

Tuesday, April 28

  • Subcontractor Itlaform starting a concrete pour for the5th floor outdoor swimming pool starting at 10:00am.
  • Interior suite drywall and finishing.

Wednesday, April 29

  • Subcontractor Itlaform forming the 5th floor outdoor swimming pool.
  • Interior suite drywall and finishing.

Thursday, April 30

  • Subcontractor Itlaform starting a concrete pour for the5th floor outdoor swimming pool starting at 10:00am.
  • Interior suite drywall and finishing.

Friday, May 1

  • Subcontractor Itlaform forming the 5th floor outdoor swimming pool.
  • Interior suite drywall and finishing.
Interior future gallery : PATH space at Backstage

Interior future gallery : PATH space at Backstage

 NOTES:

    • All rebar deliveries are now complete.
    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete or delivery trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule April 20 – 24, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for April 20 – 24, 2015. 

Work on the podium deck outdoor swimming pool and interior suite drywall work are the main construction activities this week. 

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Apr-20-24-2015

Backstage swimming pool on the podium deck

Backstage swimming pool on the podium deck

 Monday, April 20

  • Drywall delivery from 8:00 am to 1:00 pm.
  • Waterproofing 5th floor podium.
  • Interior suite drywall and finishing.

Tuesday, April 21

  • Concrete pour for the podium deck swimming pool starting at 11:00am, concrete finishing till 9:00pm
  • Interior suite drywall and finishing.
  • Waterproofing 5th floor podium.

Wednesday, April 22

  • Working on 5th floor swimming pool.
  • Waterproofing main roof.
  • Interior suite drywall and finishing.

Thursday, April 23

  • Working on 5th floor swimming pool.
  • Waterproofing main roof.
  • Interior suite drywall and finishing.

Friday, April 24

  • Working on 5th floor swimming pool.
  • Waterproofing main roof.
  • Interior suite drywall and finishing.
Yonge Street Railway Bridge - future PATH connection to Union Station.

Yonge Street Railway Bridge – future PATH connection to Union Station.

 NOTES:

    • All rebar deliveries are now complete.
    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete or delivery trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule April 13 – 17, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for April 13 – 17, 2015. 

Last concrete pour for the tower and work on the podium deck outdoor swimming pool are the main construction activities this week. 

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Apr-13-17-2015

Backstage Swimming Pool on the Podium Deck looking east from the tower.

Backstage Swimming Pool on the Podium Deck looking east from the tower.

 Monday, April 13

  • Last concrete pour for the tower, elevator curbs on the roof (8 meters of concrete), starting at 12:00 pm. 
  • Interior suite drywall and finishing.

Tuesday, April 14

  • Subcontractor Italform demobilizing their equipment and materials.
  • Working on 5th floor swimming pool.
  • Waterproofing 5th floor podium.
  • Interior suite drywall and finishing.
  • 35th floor Window delivery occupying north curb lane of the Esplanade, starting at 2:00 pm to approximately 4:00 pm.

Wednesday, April 15

  • Subcontractor Italform demobilizing their equipment and materials.
  • Working on 5th floor swimming pool.
  • Waterproofing 5th floor podium.
  • Interior suite drywall and finishing.

Thursday, April 16

  • Subcontractor Italform demobilizing their equipment and materials.
  • Working on 5th floor swimming pool.
  • Waterproofing 5th floor podium.
  • Interior suite drywall and finishing.

Friday, April 17

  • Subcontractor Italform demobilizing their equipment and materials.
  • Working on 5th floor swimming pool.
  • Waterproofing 5th floor podium.
  • Interior suite drywall and finishing.
Backstage tower south west elevation

Backstage tower south west elevation

 NOTES:

    • All rebar deliveries are now complete.
    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete or delivery trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.