L Tower Construction Schedule October 20 – 26

  • This is the current construction schedule for 8 The Esplanade – L Tower – for October 20 – 26, 2012

Updated October 24, 2012

The L Tower celebrated it’s topping-off on October 10 – please click here for images of the celebration courtesy of Cityzen

Saturday, October 20

  • Washroom Servicing 9:00 am to Noon.
  • Delivery of 1 container of curtain wall between 9:00 am and 12:00 pm.
  • UECL to service the hoist between 9:00 am and 12:00 pm.

Monday, October 22

  • A 4.5M (cubic metre) concrete pour starting at 1:00 pm

Tuesday, October 23

  • CANCELLED due to rain: A 200CM (cubic metre) slab concrete pour at level 60, starting 1:00 pm, which is expected to finish prior to 7:00 pm.
  • Rebar delivery at 12:30 pm. 
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Wednesday, October 24

  • Rebar delivery at 12:30 pm. 
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Thursday, October 25

  • Rebar delivery at 12:30 pm. – cancelled

Friday, October 26

  • Rescheduled from October 24: A 200CM (cubic metre) slab concrete pour at level 60, starting 8:00 am, which is expected to finish prior to 7:00 pm.
  • Rebar delivery at 7:00 am.cancelled
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: 

L Tower Construction Schedule October 13 – 19

  • This is the current construction schedule for 8 The Esplanade – L Tower – for October 13 – 19, 2012

Updated October 16, 2012

The L Tower celebrated it’s topping-off on October 10 – please click here for images of the celebration courtesy of Cityzen

Saturday, October 13

  • Washroom Servicing 9:00 am to Noon.
  • Delivery of 3 containers of curtain wall between 9:00 am and 4:00 pm.

Monday, October 15 

  • Rebar delivery at 7:00 am.
  • Delivery of Medi-Group masonry blocks between 8:00 am and 1:00 pm.
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Tuesday, October 16

  • Rebar delivery at 7:00 am. 
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Wednesday, October 17

  • Generator removal and pick-up after 7:00 am.
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while teh generator is removed and loaded out.

Thursday, October 18

  • Rebar delivery at 7:00 am.
  • A delivery of four containers of windows.
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Friday, October 19

  • Hoist maintenance from 8:00 am.
  • Delivery of Medi-Group masonry blocks between 8:00 am and 12:00 pm.
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • A 200CM (cubic metre) slab concrete pour at level 60, starting 1:00 pm, which is expected to finish prior to 7:00 pm.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction October 13-19

L Tower Construction Schedule October 6 – 12

This is the current construction schedule for 8 The Esplanade – L Tower – for October 6 – 12, 2012

Posted October 5, 2012

The L Tower Celebrates it’s topping-off on Wednesday. 

Saturday, October 6

  • Washroom Servicing 9:00 am to Noon.

Sunday, October 7

  • Aerobatic ballet rehearsal on the north face of the L Tower. No construction noise will be created by this activity.

Monday, October 8 – THANKSGIVING DAY

  • Aerobatic ballet rehearsal on the north face of the L Tower. No construction noise will be created by this activity. 

Tuesday, October 9

  • Delivery of elevator equipment from the Yonge Street gate. 
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Wednesday, October 10

  • L Tower Topping-Off Ceremony at 1:00 pm. 

Thursday, October 11

  • Hoist lift – three (3) floors.

Friday, October 12

  • TBD – please check back for updates. 

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction October 6-12

L Tower Construction Schedule September 29 – October 5

This is the current construction schedule for 8 The Esplanade – L Tower – for September 29 – October 5, 2012

Posted September 28, 2012

Saturday, September 29

  • Washroom Servicing 9:00 am to Noon.
  • Crane raising. 

Monday, October 1

  • Delivery of (two) 2 lifts; Cooltech, HVAC at 7:00 am.
  • A rebar (steel) delivery starting at 7:00 am.
  • A delivery of 4 containers of window/curtain wall
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • An 18 to 27 cubic meter concrete pour for the housekeeping pads – 18 to 27 meters starting at 1 pm, to be completed by 5:00 pm..

Tuesday, October 2

  • A rebar (steel) delivery starting at 7:00 am.
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • An 18 to 27 cubic meter concrete pour for the housekeeping pads – 18 to 27 meters starting at 1 pm, to be completed by 5:00 pm.

Wednesday, October 3

  • An 18 to 27 cubic meter concrete pour for the housekeeping pads – 18 to 27 meters starting at 1 pm, to be completed by 5:00 pm.

Thursday, October 4

  • An 18 to 27 cubic meter concrete pour for the housekeeping pads – 18 to 27 meters starting at 1 pm, to be completed by 5:00 pm.

Friday, October 5

  • An 18 to 27 cubic meter concrete pour for the housekeeping pads – 18 to 27 meters starting at 1 pm, to be completed by 5:00 pm.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower – Backstage Construction Sept 29 – Oct 5