Backstage Construction Schedule – July 19 – 25

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for July 19 – July 25, 2014.

Concrete pour today at the Backstage Condo, July 18, 2014.

Concrete pour today at the Backstage Condo, July 18, 2014.

Please click here for general information on concrete pours.

Saturday, July 19

  • A forming crew working on 8th floor wall and 9th floor slab from 9:00 am. 
  • Dominus crew doing construction housekeeping on-site.

Monday, July 21

  • A 9th floor wall and column concrete pour, by subcontractor Italform (35 metres of concrete), scheduled to run from 12:30 pm.

 Tuesday, July 22

  • Rebar delivery from 7:00 am.
  • 10th Floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 1o:00 am.
  • An after-slab concrete pour for 9th floor walls and columns, 35 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

Wednesday, July 23

  • 10th Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 1o:00 am.
  • An after-slab concrete pour for 9th floor walls and columns, 35 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

Thursday, July 24

  • A 10th floor wall and column concrete pour, by subcontractor Italform (35 metres of concrete), scheduled to run from 1:00 pm.

 Friday July 25

  • Rebar delivery from 7:00 am.
  • 10th Floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 1o:00 am.
  • An after-slab concrete pour for 10th floor walls and columns, 35 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

NOTES:

      • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
      • Concrete pour schedules and times are subject to weather conditions.
      • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
      • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule – July 12 – 18

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for July 12 – July 18, 2014.

Backstage construction site Friday July 11 2014

Backstage construction site Friday July 11 2014

Please click here for general information on concrete pours.

Saturday, July 12

  • A forming crew working on 8th floor wall and 9th floor slab
  • Dominus crew doing construction housekeeping on-site.

Monday, July 14

  • An 8th floor wall and column concrete pour, by subcontractor Italform (35 metres of concrete), scheduled to run from 1:00 pm.

 Tuesday, July 15

  • Rebar delivery from 7:00 am.
  • 9th Floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 1o:00 am.
  • An after-slab concrete pour to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

Wednesday, July 16

  • An 8th floor wall and column concrete pour, by subcontractor Italform (35 metres of concrete), scheduled to run from 1:00 pm.

Thursday, July 17

  • 9th Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 1o:00 am.
  • An after-slab concrete pour to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

 Friday July 18

  • Rebar delivery from 7:00 am.
  • 9th Floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 1o:00 am.
  • An after-slab concrete pour to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

NOTES:

      • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
      • Concrete pour schedules and times are subject to weather conditions.
      • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
      • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule – July 5 – 11

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for July 5 – July 11, 2014.

Backstage Condominium at Yonge Street and The Esplanade, July 4, 2014

Backstage Condominium at Yonge Street and The Esplanade, July 4, 2014

Please click here for general information on concrete pours.

Saturday, July 5

  • Miscellaneous construction work is scheduled on site from 9:00 am.

Monday, July 7

  • A wall and column concrete pour, by subcontractor Italform, scheduled to run from 1:00 pm to 3:00 pm.

 Tuesday, July 8

  • Rebar delivery from 7:00 am.
  • A wall and column concrete pour, by subcontractor Italform, scheduled to run from 1:00 pm to 3:00 pm.

Wednesday, July 9

  • Final Eighth Floor Slab concrete pour, by subcontractor Italform, scheduled to begin at 10:00 am with the pour completed by 6:00 pm.
  • Concrete Finishing may be required until to 10:00 pm.

Thursday, July 10

  • A wall and column concrete pour, by subcontractor Italform, scheduled to run from 1:00 pm to 3:00 pm.

 Friday July 11

  • Rebar delivery from 7:00 am.
  • First Ninth Floor Slab concrete pour, by subcontractor Italform, scheduled to begin at 10:00 am with the pour completed by 6:00 pm.
  • Concrete Finishing may be required until to 10:00 pm.

NOTES:

      • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
      • Concrete pour schedules and times are subject to weather conditions.
      • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
      • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule – June 28 – July 4

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for June 28 – July 4, 2014.

The Backstage condo begins its rise above the podium.

The Backstage condo begins its rise above the podium.

Please click here for general information on concrete pours.

Saturday, June 28

  • No work is scheduled on site.

Monday, June 30

  • No work is scheduled on site.

 Tuesday, July 1 – Canada Day

  • Site Closed for the Holiday.

Wednesday, July 2

  • Final seventh floor concrete pour, by subcontractor Italform, scheduled to begin at 10:00 am with the pour completed by 7:00 pm.
  • Concrete Finishing may be required until to 11:00 pm.

Thursday, July 3

  • First Eighth floor concrete pour, by subcontractor Italform, scheduled to begin at 10:00 am with the pour completed by 7:00 pm.
  • Concrete Finishing may be required until to 11:00 pm.

 Friday July 4

  • Second Eighth floor concrete pour, by subcontractor Italform, scheduled to begin at 10:00 am with the pour completed by 7:00 pm.
  • Concrete Finishing may be required until to 11:00 pm.

NOTES:

      • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
      • Concrete pour schedules and times are subject to weather conditions.
      • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
      • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule – June 21 – 27

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for June 21 – 27, 2014.

Backstage condo under construction, June 20, 2014

Backstage condo under construction, June 20, 2014

Please click here for general information on concrete pours.

Saturday, June 21

  • Seventh floor slab concrete pour #2 by subcontractor Italform, scheduled to begin at 9:00 am.
  • Concrete Finishing to 7:00 pm.

Monday, June 23

  • Seventh floor concrete pour by subcontractor Italform. The pour is scheduled to run between 1:00 pm and 4:00 pm.

 Tuesday, June 24

  • Rebar (steel) delivery starting at 7:00 am
  • Seventh floor concrete pour by subcontractor Italform. The pour is scheduled to run between 1:00 pm and 3:00 pm.

Wednesday, June 25

  • Seventh floor slab concrete pour #3 by subcontractor Italform, scheduled to begin at 10:00 am.
  • Concrete Finishing to 9:00 pm.

Thursday, June 26

  • Seventh floor concrete pour by subcontractor Italform. The pour is scheduled to run between 1:00 pm and 3:00 pm.

 Friday June 27

  • Rebar (steel) delivery starting at 7:00 am
  • Seventh floor concrete pour by subcontractor Italform. The pour is scheduled to run between 1:00 pm and 3:00 pm.

NOTES:

      • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
      • Concrete pour schedules and times are subject to weather conditions.
      • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
      • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule – June 14 – 20

Backstage first tower floorplus 25 The Esplanade

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for June 14 – 20, 2014.

Please click here for general information on concrete pours.

Saturday, June 14

  • No work is scheduled.

Monday, June 16

  • Sixth floor concrete pour by subcontractor Italform. The pour is scheduled to run between 1:00 pm and 4:00 pm.

 Tuesday, June 17

  • Rebar (steel) delivery starting at 7:00 am
  • Sixth floor concrete pour by subcontractor Italform. The pour is scheduled to run between 1:00 pm and 3:00 pm.

Wednesday, June 18

  • Seventh floor slab concrete pour #1 by subcontractor Italform, scheduled to begin at 10:00 am.
  • Concrete Finishing to 7:00 pm.

Thursday, June 19

  • Seventh floor concrete pour by subcontractor Italform. The pour is scheduled to run between 1:00 pm and 3:00 pm.

 Friday June 20

  • Rebar (steel) delivery starting at 7:00 am
  • Seventh floor concrete pour by subcontractor Italform. The pour is scheduled to run between 1:00 pm and 3:00 pm.

NOTES:

      • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
      • Concrete pour schedules and times are subject to weather conditions.
      • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
      • Concrete trucks must keep their engines running during the pouring process.


Backstage Construction Schedule – June 7 – 13

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for June 7 – 13, 2014.

Please click here for general information on concrete pours.

First floor of the Backstage condo's tower section.

First floor of the Backstage condo’s tower section.

Saturday, June 7

  • No work is scheduled.

Monday, June 9

  • Sixth floor slab concrete pour #1 by subcontractor Italform, scheduled to begin at 9:00 am.
  • After slab concrete pour by subcontractor Italform.
  • Concrete Finishing to 10:00 pm.

 Tuesday, June 10

  • Rebar (steel) delivery starting at 7:00 am
  • Sixth floor concrete pour by subcontractor Italform. The pour is scheduled to run between 1:00 pm and 4:00 pm.

Wednesday, June 11

  • Sixth floor slab concrete pour #2 by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
  • Concrete Finishing to 10:00 pm.

Thursday, June 12

  • Rebar (steel) delivery starting at 7:00 am
  • Sixth floor concrete pour by subcontractor Italform. The pour is scheduled to run between 1:00 pm and 4:00 pm.

 Friday June 13

  • Sixth floor slab concrete pour #3 by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab concrete pour by subcontractor Italform.
  • Concrete Finishing to 9:00 pm.

NOTES:

      • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
      • Concrete pour schedules and times are subject to weather conditions.
      • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
      • Concrete trucks must keep their engines running during the pouring process.


Backstage Construction Schedule – May 31 – June 6

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for May 31 – June 6, 2014.

Please click here for general information on concrete pours.

First floor of the Backstage condo's tower section.

First floor of the Backstage condo’s tower section.

Saturday, May 31

  • Clean-up and minor construction activities on site on site from 9:00 am to 1 pm

Monday, June 2

  • 6th floor concrete pour by subcontractor Italform. The pour is scheduled to run between 1:00 pm and 4:00 pm.

 Tuesday, June 3

  • Rebar (steel) delivery starting at 7:00 am
  • 6th floor concrete pour by subcontractor Italform. The pour is scheduled to run between 1:00 pm and 4:00 pm.

Wednesday, June 4

  • 6th floor concrete pour by subcontractor Italform. The pour is scheduled to run between 1:00 pm and 4:00 pm.

Thursday, June 5 – Friday June 6

  • Moving the mobile crane.

  • PLEASE NOTE: The Esplanade will be closed to vehicular traffic from Yonge Street to the west TPA Lot entrance on the south and Scott Street on the north, while the crane work is conducted. Paid-Duty police officers will be on-site during the work. 

NOTES:

      • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
      • Concrete pour schedules and times are subject to weather conditions.
      • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
      • Concrete trucks must keep their engines running during the pouring process.


Backstage Construction Schedule – May 24 – 30

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for May 24 – 30, 2014.

Backstage podium under construction

Backstage podium under construction

Please click here for general information on concrete pours.

 

Saturday, May 24

  • Excavation work on site from 9:00 am to Noon 
  • Some general interior work

Monday, May 26

  • Rebar (steel) delivery starting at 7:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin after 12:30 pm and should be completed before 7:00 pm.

 Tuesday, May 27

  • Fifth floor slab concrete pour #8 by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
  • Concrete Finishing to 10:00 pm.

Wednesday, May 28

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin after 12:30 pm and should be completed before 7:00 pm.

Thursday, May 29

  • Rebar (steel) delivery starting at 7:00 am.
  • Fifth floor slab concrete pour #9 by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
  • Concrete Finishing to 10:00 pm.

Friday, May 30

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin after 12:30 pm and should be completed before 7:00 pm.

NOTES:

      • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
      • Concrete pour schedules and times are subject to weather conditions.
      • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
      • Concrete trucks must keep their engines running during the pouring process.


Backstage Construction Schedule – May 17 – 23

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for May 17 – 23, 2014.

Backstage Condo - podium concrete detail.

Backstage Condo – podium concrete detail.

Please click here for general information on concrete pours.

 

Saturday, May 17

 

  • Excavation work on site from 9:00 am to Noon 
  • Some general interior work

Monday, May 19 – Victoria Day Holiday

  • Site Closed for the holiday.

 Tuesday, May 20

  • Rebar (steel) delivery starting at 7:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin after 12:30 pm and should be completed before 7:00 pm.

Wednesday, May 21

  • Fifth floor slab concrete pour #7 by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
  • Concrete Finishing to 10:00 pm.

Thursday, May 22

  • Rebar (steel) delivery starting at 7:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin after 12:30 pm and should be completed before 7:00 pm.

Friday, May 23

  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin after 12:30 pm and should be completed before 7:00 pm.

NOTES:

      • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
      • Concrete pour schedules and times are subject to weather conditions.
      • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
      • Concrete trucks must keep their engines running during the pouring process.