1 The Esplanade Construction Schedule for October 17- 22

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condo for the week of October 17 – 22, 2011

Posted October 16, 2011

Please Note: The bulk excavating is schedule to get underway this week. Once it is in full operation, there will be high impact on traffic at Scott Street and The Esplanade due to a large number of dump trucks coming to and leaving the site. At this time there remains no firm schedule. This site will be updated as soon as this information becomes available.

1 The Esplanade Construction Schedule: July 18 – 22.

Scheduled construction activity for 1 The Esplanade–L Tower parking garage and Backstage condo–July 18 through July 22.

Monday, July 18

Sub-contractor, Deep Foundation has 4 semi-trailer truck deliveries at The Esplanade gate. During these deliveries there will be a significant impact on pedestrian and vehicular traffic movement on The Esplanade between Scott Street and Yonge Street.

Tuesday, July 19

Sub-contractor, Deep Foundation will be starting caisson wall drilling. There will be up to six concrete deliveries into the site at The Esplanade gate. During these deliveries there will be a moderate impact on pedestrian and vehicular traffic movement on The Esplanade between Scott Street and Yonge Street.

Wednesday, July 20

Sub-contractor, Deep Foundation will be drilling the caisson wall. There will be up to six concrete deliveries into the site at The Esplanade gate. Deep Foundation will also be delivering one load of steel pile on a semi-trailer truck. During these deliveries there will be a moderate impact on pedestrian and vehicular traffic movement on The Esplanade between Scott Street and Yonge Street.

Thursday, July 21

Sub-contractor, Deep Foundation will be drilling the caisson wall. There will be up to six concrete deliveries into the site at The Esplanade gate. During these deliveries there will be a moderate impact on pedestrian and vehicular traffic movement on The Esplanade between Scott Street and Yonge Street.

Friday July 22

Sub-contractor, Deep Foundation will be drilling the caisson wall. There will be up to six concrete deliveries into the site at The Esplanade gate. During these deliveries there will be a moderate impact on pedestrian and vehicular traffic movement on The Esplanade between Scott Street and Yonge Street.