Installing tie backs at Backstage

Tie back machine in operation at Backstage condo site, 1 The Esplanade - 4/3/12

Backstage Construction Schedule – April 2 – 6

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for April 2 – 6, 2012

Posted March 30, 2012

Monday, April 2

  • Sub-contractor, Deep Foundation, will be floating in the tie back machine in the morning.
  • NOTE: This will unfortunately cause short-term delays for vehicular and pedestrian traffic.

Tuesday, April 3

  • Sub-contractor, Deep Foundation, will be installing tie backs.

Wednesday, April 4

  • Sub-contractor, Deep Foundation, will be installing tie backs.
  • Sub-contractor, GFL Excavating, will be removing material from the site: 4 trucks doing 5 loads each.

Thursday, April 5

  • Sub-contractor, Deep Foundation, will be installing tie backs.
  • Sub-contractor, GFL Excavating, will be removing material from the site: 4 trucks doing 5 loads each.

Good Friday – Holiday – April 6

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Thursday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 2 – 6 summary update: L Tower & Backstage Construction April 2 – 6