Backstage Construction Schedule – August 27 – 31
August 24, 2012 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for August 27 – 31, 2012
Posted August 24, 2012
Monday, August 27
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
Tuesday, August 28
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
Wednesday, August 29
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
- Subcontractor, Deep Foundation will be bringing in a rock anchor drill and beginning to install the last row of tie backs.
- Please Note: there may be disrutions to pedestrian and vehicualr traffic during the delivery and unloading of the drill.
Thursday, August 30
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
- Subcontractor, Deep Foundation will be installing the last row of tie backs.
Friday, August 31
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
- Subcontractor, Deep Foundation will be installing the last row of tie backs.
NOTES:
* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.
Construction activities are dependent on whether.
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
Please click here for a downloadable construction summary: Revised L Tower & Backstage Construction August 28-31