Backstage Construction Schedule – August 27 – 31

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for August 27 – 31, 2012

Posted August 24, 2012

Monday, August 27

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Tuesday, August 28

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Wednesday, August 29

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
  • Subcontractor, Deep Foundation will be bringing in a rock anchor drill and beginning to install the last row of tie backs.
    • Please Note: there may be disrutions to pedestrian and vehicualr traffic during the delivery and unloading of the drill.

Thursday, August 30

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
  • Subcontractor, Deep Foundation will be installing the last row of tie backs.

Friday, August 31

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
  • Subcontractor, Deep Foundation will be installing the last row of tie backs.

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: Revised L Tower & Backstage Construction August 28-31

Backstage Construction Schedule – June 25 – 29

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for June 25 – 29, 2012

Posted June 22, 2012

NOTE: For photos illustrating the current forms of work at the Backstage site please click here.

Monday, June 25

  • Subcontractor, GFL Excavating will be removing material from the site: three (3) dump trucks will take 10 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

Tuesday, June 26

  • Subcontractor, GFL Excavating will be removing material from the site: three (3) dump trucks will take 10 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

Wednesday, June 27

  • Subcontractor, GFL Excavating will be removing material from the site: three (3) dump trucks will take 10 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

Thursday, June 28

  • Subcontractor, GFL Excavating will be removing material from the site: three (3) dump trucks will take 10 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

Friday, June 29

  • Subcontractor, GFL Excavating will be removing material from the site: three (3) dump trucks will take 10 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

* * *

NOTES:

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage June 25 – 29 summary highlights: L Tower & Backstage Construction June 25-29

Backstage Saturday June 16

This is the current construction schedule for 1 The Esplanade – Backstage – for  Saturday, June 16, 2012

Posted June 15, 2012

Saturday, June 16

  • Deep Foundation will have three welders on site installing tie back connections.

Backstage Construction Schedule – June 18 – 22

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for June 18 – 22, 2012

Posted June 15, 2012

NOTE: For photos illustrating the current forms of work at the Backstage site please click here.

Monday, June 18

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs. 

Tuesday, June 19

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

Wednesday, June 20

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs. 

Thursday, June 21

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

Friday, June 22

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

* * *

NOTES:

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage June 18 – 22 summary highlights: L Tower & Backstage Construction June 18-22

Backstage Construction Schedule – June 11 – 15

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for June 11 – 15, 2012

Posted June 8, 2012

NOTE: For photos illustrating the current forms of work at the Backstage site please click here.

Monday, June 11

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs. 

Tuesday, June 12

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

Wednesday, June 13

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs. 

Thursday, June 14

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

Friday, June 15

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

* * *

NOTES:

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage June 11 – 15 summary highlights: L Tower & Backstage Construction June 11-15

Backstage Construction Schedule – June 4 – 8

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for June 4 – 8, 2012

Posted June 1, 2012

NOTE:

  • We have also been advised that the final phase of the Waterfront Toronto sewer construction contract will begin on Monday, June 4 for approximately 8 weeks.  Jarvis Street will be reduced to one lane in each direction betweenThe Esplanade and Wilton Street.

Monday, June 4

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs. 

Tuesday, June 5

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

Wednesday, June 6

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs. 

Thursday, June 7

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

Friday, June 8

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

* * *

NOTES:

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage June 4 – 8 summary highlights: L Tower & Backstage Construction June 4-8

Backstage Construction Schedule – April 9 – 13

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for April 9 – 13, 2012

Updated April 10, 2012

NOTE: Subcontractor, Deep Foundation will be delivering a large drill rig to the site at 1 The Esplanade in order to complete the piles and caisson work this week. The delivery date is not confirmed at the time of posting. Please check back for updated information.

Monday, April 9

  • Subcontractor, Deep Foundation, will be installing a second row of tie backs.
  • Subcontractor, GFL Excavating will be removing material from the site: 4 dump trucks will take 5 loads each, for a total of 20 loads.

Tuesday, April 10

  • Subcontractor, Deep Foundation, will be installing a second row of tie backs.
  • Subcontractor, GFL Excavating will be removing material from the site: 4 dump trucks will take 5 loads each, for a total of 20 loads.

Wednesday, April 11

  • Subcontractor, Deep Foundation, will be delivering a drill rig to the site at 1 The Esplanade after 9 am, under police escort.
    • There will be short-term disruptions to vehicular and pedestrian traffic. The construction management team apologizes for any short-term inconvenience this may cause.
  • Subcontractor, Deep Foundation, will be installing a second row of tie backs.
  • Subcontractor, GFL Excavating will be removing material from the site: 4 dump trucks will take 5 loads each, for a total of 20 loads.

Thursday, April 12

  • Subcontractor, Deep Foundation, will be installing a second row of tie backs.
  • Subcontractor, GFL Excavating will be removing material from the site: 4 dump trucks will take 5 loads each, for a total of 20 loads.

Friday,  April 13

  • Subcontractor, Deep Foundation, will be installing a second row of tie backs.
  • Subcontractor, GFL Excavating will be removing material from the site: 4 dump trucks will take 5 loads each, for a total of 20 loads.

* * *

NOTES:

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 9 – 13 summary update: 1+8 The Esplanade – Construction Notice-April-9-13

Backstage Construction Schedule – April 2 – 6

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for April 2 – 6, 2012

Posted March 30, 2012

Monday, April 2

  • Sub-contractor, Deep Foundation, will be floating in the tie back machine in the morning.
  • NOTE: This will unfortunately cause short-term delays for vehicular and pedestrian traffic.

Tuesday, April 3

  • Sub-contractor, Deep Foundation, will be installing tie backs.

Wednesday, April 4

  • Sub-contractor, Deep Foundation, will be installing tie backs.
  • Sub-contractor, GFL Excavating, will be removing material from the site: 4 trucks doing 5 loads each.

Thursday, April 5

  • Sub-contractor, Deep Foundation, will be installing tie backs.
  • Sub-contractor, GFL Excavating, will be removing material from the site: 4 trucks doing 5 loads each.

Good Friday – Holiday – April 6

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Thursday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 2 – 6 summary update: L Tower & Backstage Construction April 2 – 6

1 The Esplanade – Construction Schedule December 19 – 23

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for the week of December 19 – 23, 2011

Posted December 16, 2011

Monday, December 19

  • Sub-contractor, Deep Foundation will be installing tie backs.
  • Sub-contractor, Deep Foundation drilling caisson wall along The Esplanade: 8 loads of concrete.
  • Sub-contractor, GFL Excavating digging. 10 dump trucks, 5 rounds each, 50 loads in total.

Tuesday, December 20

  • Sub-contractor, Deep Foundation will be installing tie backs.
  • Sub-contractor, Deep Foundation drilling caisson wall along The Esplanade: 8 loads of concrete.
  • Sub-contractor, GFL Excavating digging. 10 dump trucks, 5 rounds each, 50 loads in total.

Wednesday, December 21

  • Sub-contractor, Deep Foundation will be installing tie backs.
  • Sub-contractor, Deep Foundation drilling caisson wall along The Esplanade: 8 loads of concrete.
  • Sub-contractor, GFL Excavating digging. 10 dump trucks, 5 rounds each, 50 loads in total.

Thursday, December 22

  • Sub-contractor, Deep Foundation will be installing tie backs.
  • Sub-contractor, Deep Foundation drilling caisson wall along The Esplanade: 8 loads of concrete.
  • Sub-contractor, GFL Excavating digging. 10 dump trucks, 5 rounds each, 50 loads in total.

Friday, December 23

  • Sub-contractor, Deep Foundation will be installing tie backs.
  • Sub-contractor, Deep Foundation drilling caisson wall along The Esplanade: 8 loads of concrete.
  • Sub-contractor, GFL Excavating digging. 10 dump trucks, 5 rounds each, 50 loads in total.

Saturday, December 24

Happy Holidays!

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

1 The Esplanade – Construction Schedule November 28 – December 2

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for the week of November 28 – December 2, 2011

Posted November 25, 2011

Monday, November 28

  • Sub-contractor Deep Foundation will be installing tie backs.

Tuesday, November 29

  • Sub-contractor Deep Foundation will be installing tie backs.

Wedensday, November 30

  • Sub-contractor Deep Foundation will be installing tie backs.

Thursday, December 1

  • Sub-contractor Deep Foundation will be installing tie backs.

Friday, December 2

  • Sub-contractor Deep Foundation will be installing tie backs.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.