Backstage Construction Schedule June 6-12, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for June 6 – 12, 2015. 

NOTE: Cable Control Systems was delayed last week and will now be on site this week on The Esplanade digging trenches to lay cable for Rogers to service Backstage. The cable work will temporarily disrupt traffic along The Esplanade. Cable Control Systems will be applying for any relevant permits. 

Click on the link for a downloadable PDF June 6 – 12 Construction Summary: Backstage & L Tower Construction Summary-June 6-12-2015

Backstage suite kitchen June 5

Backstage suite kitchen June 5

Saturday, June 6

  • Interior suite work: drywall and finishing.
  • On-site housekeeping.

Monday, June 8 

  • Cable Control Systems for Rogers will be digging trenches for incoming services for Backstage.
  • NOTE: The cable work will disrupt traffic along The Esplanade. Cable Control Systems will be applying for any relevant permits. 
  • Interior suite finishing all day.
  • Toro Aluminum will be delivering windows for the roof. Their truck will occupy the south curb lane on The Esplanade from 8:00 am to approximately 12:00 pm.
  • Drywall delivery from 12:00 pm to 4:00 pm.

Tuesday, June 9

  • Cable Control Systems for Rogers will be digging trenches for incoming services for Backstage.
  • NOTE: The cable work will disrupt traffic along The Esplanade. Cable Control Systems will be applying for any relevant permits. 
  • Interior suite work: drywall and finishing.

Wednesday, June 10

  • Tile and Kitchen delivery after 7:00 am.
  • Drywall delivery after 12:00 pm
  • Interior suite work: drywall and finishing.

Thursday, June 11

  • Interior suite finishing all day.
  • Toro Aluminum will be delivering windows for the roof. Their truck will occupy the south curb lane on The Esplanade from 8:00 am to approximately 12:00 pm.

Friday, June 12

  • Cooltech and Professional Carpentry deliveries after 7:00 am.
  • Interior suite work: drywall and finishing all day.
Backstage interior work

Backstage interior work

 NOTES:

    • All rebar deliveries are now complete.
    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete or delivery trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule May 30 – June 5, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for May 30 – June 5, 2015. 

NOTE: Cable Control Systems (for Rogers) and Distinct Tech (for Beanfeild) will be digging for incoming services to Backstage on June 2 – 4. The cable work will temporarily disrupt traffic along The Esplanade. Cable Control Systems and Distinct Tech will be applying for any relevant permits. 

Backstage sans crane.

Backstage sans crane.

Click on the link for a downloadable PDF May 30 – June 5 Construction Summary: Backstage & L Tower Construction Summary-May 30-June 5-2015

South view from the 8th floor of Backstage

South view from the 8th floor of Backstage

Saturday, May 30

  • Interior suite work: drywall and finishing.
  • Exterior preparation work for cable laying next week with a mini excavator and breaker hammer, starting at 9:00 am.

Monday, June 1 

  • Interior suite finishing all day.
  • Toro railing delivery from 8:00 am to 12:00 pm.
  • Drywall delivery from 12:00 pm to 4:00 pm.

Tuesday, June 2

  • Cable Control Systems for Rogers and Distinct Tech for Beanfeild will be digging for incoming services for Backstage.
  • NOTE: The cable work will disrupt traffic along The Esplanade. Cable Control Systems and Distinct Tech will be applying for any relevant permits. 
  • Drywall delivery from 8:00 am to 12:00 pm
  • Interior suite work: drywall and finishing.

Wednesday, June 3

  • Cable Control Systems for Rogers and Distinct Tech for Beanfeild will be digging for incoming services for Backstage.
  • NOTE: The cable work will disrupt traffic along The Esplanade. Cable Control Systems and Distinct Tech will be applying for any relevant permits. 

Thursday, June 4

  • Cable Control Systems for Rogers and Distinct Tech for Beanfeild will be digging for incoming services for Backstage.
  • NOTE: The cable work will disrupt traffic along The Esplanade. Cable Control Systems and Distinct Tech will be applying for any relevant permits. 

Friday, June 5

  • Interior suite work: drywall and finishing all day.
Backstage interior work.

Backstage interior work.

 NOTES:

    • All rebar deliveries are now complete.
    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete or delivery trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Road Closure May 1 on The Esplanade

Please be advised that on Thursday May 1, 2014, the eastbound lane from Yonge Street to Scott Street on The Esplanade will be closed to vehicle traffic from 7:00 am to 5:30 pm.

Pedestrians will continue to have access through the site.

The City of Toronto has approved the request for the temporary road closure and the appropriate permit will be posted on site on Thursday, May 1.

NOTE: the western exit from the Toronto Parking Authority’s St. Lawrence Parking Garage will be closed to all exits and entries as part of this temporary road closure. 