L Tower Construction Schedule December 3 -7

This is the current construction schedule for 8 The Esplanade – L Tower – for  December 3 – 7, 2012

Updated  December 4, 2012

Monday, December 3

  • No activity is scheduled at this time.

Tuesday, December 4

  • CANCELLED: A 110 cubic metre, slab concrete pour at level 61, starting 8:00 am, which is not expected to finish later than 7:00 pm.

Wednesday, December 5

  • No activity is scheduled at this time.

Thursday, December 6

  • A rebar (steel) delivery starting at 7:00 am.

Friday, December 7 

  • A rebar (steel) delivery starting at 7:00 am.

Please note:

There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction December 3 – December 7


L Tower Construction Schedule November 24 – 30

This is the current construction schedule for 8 The Esplanade – L Tower – for  November 24 – 30, 2012

Updated  November 23, 2012

Saturday, November 24

  • Four containers of windows with delivery starting at 9:00 am and continuing to 4:00 pm.

Monday, November 26

  • A 1 cubic metre concrete pour at 9:00 am, levels 61 – 62, expected to finish prior to 7:00 pm.
  • A rebar (steel) delivery starting at 7:00 am.
  • Two containers of windows with delivery starting at 12:00 pm and continuing to 4:00 pm.
  • A delivery of window frames with delivery starting 1:00 pm and continuing to 2:00 pm.

Tuesday, November 27

  • A rebar (steel) delivery starting at 12:30 pm.

Wednesday, November 28

  • No activity is scheduled at this time.

Thursday, November 29

  • A rebar (steel) delivery starting at 7:00 am.

Friday, November 30

  • A rebar (steel) delivery starting at 7:00 am.

Please note:

There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

 

Please click here for a downloadable construction summary: L Tower & Backstage Construction November 26 – 30


L Tower Construction Schedule November 19 – 23

This is the current construction schedule for 8 The Esplanade – L Tower – for  November 19 – 23, 2012

Updated  November 20, 2012

Monday, November 19

  • Drywall delivery starting at 7:00 am.
  • A rebar (steel) delivery starting at 7:00 am.

Tuesday, November 20

  • A rebar (steel) delivery starting at 7:00 am.
  • Miscellaneous construction activities throughout the day.

Wednesday, November 21

  • Drywall delivery starting at 7:00 am.
  • One container of windows with delivery starting at 7:30 am.
  • Miscellaneous construction activities throughout the day.

Thursday, November 22

  • A rebar (steel) delivery starting at 7:00 am..
  • Electrical materials delivery starting at 8:00 am.
  • Three containers of windows with delivery starting at 10:00 am.

Friday, November 23

  • A delivery of duct work delivery starting at 7:00 am.
  • Electrical materials delivery starting at 8:00 am.
  • A rebar (steel) delivery starting at 12:30 pm.

Please note:

There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction November 19 – 23

L Tower Construction Schedule November 12 – 16

This is the current construction schedule for 8 The Esplanade – L Tower – for  November 12 – 16, 2012

Posted November 9, 2012

Monday, November 12

  • A delivery of 3 containers of window/curtain wall between 7:00 am and 4:00 pm

Tuesday, November 13

  • A 18 cubic metre concrete pour at 1:00 pm, levels 60 – 61, expected to finish prior to 7:00 pm.

Wednesday, November 14

  • A 18 cubic metre concrete pour at 1:00 pm, levels 60 – 61, expected to finish prior to 7:00 pm.

Thursday, November 15

  • A 18 cubic metre concrete pour at 1:00 pm, levels 60 – 61, expected to finish prior to 7:00 pm.
  • A rebar (steel) delivery starting at 12:30 pm.
  • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Friday, November 16

  • No scheduled work at this time.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction November 12 – 16

L Tower Construction Schedule November 3 – 9

This is the current construction schedule for 8 The Esplanade – L Tower – for  November 3 – 9, 2012

Posted November 2, 2012

Saturday, November 3

  • A delivery of 3 containers of window/curtain wall between 9:00 am and 2:00 pm
  • Platform removal continuing. 

Monday, November 5

  • Platform removal continuing. 
  • A rebar (steel) delivery starting at 7:00 am.
  • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • A 73 cubic metre concrete pour pour at 2:00 pm, levels 60 – 61, expected to finish prior to 7:00 pm.
  • Please note: this concrete pour may be shifted to Tuesday. 

Tuesday, November 6

  • A rebar (steel) delivery starting at 12:30 pm.
  • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • A 63 cubic metre concrete pour pour at 1:00 pm, levels 60 – 61, expected to finish prior to 7:00 pm.
  • Please note: this concrete pour may be shifted to Wednesday. 

Wednesday, November 7

  • A rebar (steel) delivery starting at 7:00 am.
  • A stud delivery starting scheduled from 7:00 am to 10:00 am.
  • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Thursday, November 8

  • A rebar (steel) delivery starting at 7:00 am.
  • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Friday, November 9

  • A rebar (steel) delivery starting at 12:30 pm.
  • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower – Backstage Construction Nov 5-9

L Tower Construction Schedule October 27 – November 2

This is the current construction schedule for 8 The Esplanade – L Tower – for October 27 – November 2, 2012

Posted October 26, 2012

Saturday, October 27

  • A delivery of 2 containers of window/curtain wall between 9:00 am and 2:00 pm

Monday, October 29

  • There will be a platform removal
  • A rebar (steel) delivery starting at 12:30 pm.

Tuesday, October 30

  • A rebar (steel) delivery starting at 12:30 pm.

Wednesday, October 31

  • The boom crane will be on site to move concrete pump.
  • A rebar (steel) delivery starting at 12:30 pm.

Thursday, November 1

  • A rebar (steel) delivery starting at 12:30 pm.

Friday, November 2

  • A rebar (steel) delivery starting at 7:00 am.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction October 27 – November 2

L Tower Construction Schedule September 29 – October 5

This is the current construction schedule for 8 The Esplanade – L Tower – for September 29 – October 5, 2012

Posted September 28, 2012

Saturday, September 29

  • Washroom Servicing 9:00 am to Noon.
  • Crane raising. 

Monday, October 1

  • Delivery of (two) 2 lifts; Cooltech, HVAC at 7:00 am.
  • A rebar (steel) delivery starting at 7:00 am.
  • A delivery of 4 containers of window/curtain wall
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • An 18 to 27 cubic meter concrete pour for the housekeeping pads – 18 to 27 meters starting at 1 pm, to be completed by 5:00 pm..

Tuesday, October 2

  • A rebar (steel) delivery starting at 7:00 am.
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • An 18 to 27 cubic meter concrete pour for the housekeeping pads – 18 to 27 meters starting at 1 pm, to be completed by 5:00 pm.

Wednesday, October 3

  • An 18 to 27 cubic meter concrete pour for the housekeeping pads – 18 to 27 meters starting at 1 pm, to be completed by 5:00 pm.

Thursday, October 4

  • An 18 to 27 cubic meter concrete pour for the housekeeping pads – 18 to 27 meters starting at 1 pm, to be completed by 5:00 pm.

Friday, October 5

  • An 18 to 27 cubic meter concrete pour for the housekeeping pads – 18 to 27 meters starting at 1 pm, to be completed by 5:00 pm.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower – Backstage Construction Sept 29 – Oct 5

L Tower Construction Schedule September 24 – 28

This is the current construction schedule for 8 The Esplanade – L Tower – for September 24 – 28, 2012

Posted September 21, 2012

Monday, September 24

  • A delivery of four (4) containers of glass from  7:00 am through 4:00 pm.
  • A second delivery of HVAC units at 7:00 am. 
    • Please note:
            1. There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded. 
            2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • Curbs concrete pour starting at approximately 2:00 pm, which is not expected to extend beyond 7:00 pm.

Tuesday, September 25

  • A delivery of door hardware from subcontractor CityWide at 10:00 am.
    • Please note:
          • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded. 
          • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Wednesday, September 26

  • To Be Determined – the website will be updated once information is available.

Thursday, September 27

  • A rebar (steel) delivery starting at 7:00 am.
    • Please note:
          • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded. 
          • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Friday, September 28

  • A rebar (steel) delivery starting at 7:00 am.
    • Please note:
          • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded. 
          • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction September 24-28

Transportation & Delivery Issues Impact Backstage today.

The expected Wide-Load steel delivery was CANCELLED today, September 18, due to traffic and transportation issues beyond the control of the construction management team.

This serious transportation and delivery issue may impact the deliveries planned for September 19 – 21st. This may involve canceling some or all of the remaining daytime (7 am – 6 pm) road closure for September 19 – 21 and rescheduling it. 

We will update information regarding planned deliveries and the road closure for September 19 – 21 as soon as it becomes available.

Wide-load steel deliveries to Backstage Sept 18 – 21

Wide-Load CANCELLED due to traffic and transportation issues — Please note that there will be wide-load steel deliveries under police escort to the Backstage construction site each morning from September 18 – 21 — We will update information regarding September 19 -21 as soon as it becomes available. 

  • These deliveries will be made to the site at 1 The Esplanade, via Scott Street, during the daily — September 18 – 21, 7 am to 6 pm — road closure period.
  • We expect the loads will arrive between 7 am and 10 am depending on traffic and road conditions.
  • We will update this information if there are changes to the delivery schedule or as new information becomes available.

The construction  management team apologizes for any inconvenience. All efforts will be made to ensure that this work is carried out as efficiently as possible. 