Backstage Construction Schedule – September 10 – 14

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for September 10 – 14, 2012

Posted September 7, 2012

Monday, September 10 

  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 14 loads each, for a total of fifty-six (56) loads. *
  • Subcontractor, Deep Foundation will be installing rock anchors.

Tuesday, September 11

  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 14 loads each, for a total of fifty-six (56) loads. *
  • Subcontractor, Deep Foundation will be installing rock anchors.

Wednesday, September 12

  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 14 loads each, for a total of fifty-six (56) loads. *
  • Subcontractor, Deep Foundation will be will be installing rock anchors.

Thursday, September 13

  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 14 loads each, for a total of fifty-six (56) loads. *
  • Subcontractor, Deep Foundation will be installing rock anchors.

Friday, September 14

  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 14 loads each, for a total of fifty-six (56) loads. *
  • Subcontractor, Deep Foundation will be installing rock anchors.

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction September 8-14

Backstage Construction Schedule – September 4 – 7

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for September 4 – 7, 2012

Posted August 31, 2012

Monday, September 3 – Labour Day – Holiday 

Tuesday, September 4

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
  • Subcontractor, Deep Foundation will be installing rock anchors.

Wednesday, September 5

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
  • Subcontractor, Deep Foundation will be will be installing rock anchors.

Thursday, September 6

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
  • Subcontractor, Deep Foundation will be installing rock anchors.

Friday, September 7

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
  • Subcontractor, Deep Foundation will be installing rock anchors.

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: Revised L Tower – Backstage Construction Sept 4-7

%d bloggers like this: