Update for Backstage Construction Schedule – April 5 & 6

This is the update t the construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for April 5 – 6, 2013

Updated April 5 –  2013

Friday, April 5 – Updated

  • Formwork deliveries by subcontractor Italform, from 7:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • Italform will be pouring parking level 5–pour #1. This pour will start at 9:30am and will take approximately 3 hours to place the concrete. It is anticipated that the concrete finishing will go to 10:30 pm.

Saturday, April 6 – Daytime Vehicular Road Closure

  • GFL Excavating will hoisting excavators out of the excavation to facilitate this Dominus is applying for a vehicular road closure on The Esplanade from Yonge Street to Scott Street. Domius has also requested two paid duty officers.
  • The hoisting operation is estimated to start at 9:00am and go to 1:00pm

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click here for a downloadable construction summary: 

Backstage Construction Schedule – April 3 – 6, 2013 – Updated

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for April 3 – 6, 2013

Updated April 5 –  2013

Wednesday, April 3 – – Updated

  • Formwork deliveries by subcontractor Italform, from 7:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A slab concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will extend to at least  8:30 pm this evening.

Thursday, April 4 

  • Formwork deliveries by subcontractor Italform, from 7:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour should  be completed prior to 7:00 pm, subject to weather conditions. 

Friday, April 5 – Updated

  • Formwork deliveries by subcontractor Italform, from 7:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • Italform will be pouring parking level 5–pour #1. This pour will start at 9:30am and will take approximately 3 hours to place the concrete. It is anticipated that the concrete finishing will go to 10:30 pm.

Saturday, April 6 – Daytime Vehicular Road Closure

  • GFL Excavating will hoisting excavators out of the excavation to facilitate this Dominus is applying for a vehicular road closure on The Esplanade from Yonge Street to Scott Street. Domius has also requested two paid duty officers.
  • The hoisting operation is estimated to start at 9:00am and go to 1:00pm

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click here for a downloadable construction summary: 

NOTICE OF COMMUNITY INFORMATION MEETING

Ferncastle invites you to attend an information meeting on

Tuesday May 31 at 7 p.m.  

RE: An application to request closing the eastbound lane of The Esplanade to vehicular traffic from Yonge Street to west side of Scott Street, during the construction of  L Tower and Backstage condominiums.

DATE:   Tuesday, May 31

TIME:   7:00 pm

LOCATIONNovotel, 45 The Esplanade,  Room: Champagne West

Click here for map.

Coffee, Soft Drinks and Cookies will be served.

ATTENDING:

  • Representatives of the Ferncastle development team, the development partnership for the Backstage and L Tower condominiums.
  • Councillor Pam McConnell

 NOTES:  

  • Pedestrian access to Yonge Street would be provided as part of this application.
  • Accommodation for neighbourhood festivals, such as Buskerfest, would be made on a per event basis.
  • Vehicular access to the west entrance/exit of the St. Lawrence
  • Toronto Parking Authority garage would be maintained.

If you have any questions please email: info@enconsulting.ca