Backstage Construction Schedule April 4 – 10, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for April 4 – 10, 2015.   More concrete pours for the roof and more window deliveries are the featured construction activities this week. 

Backstage podium deck April 2

Backstage podium deck showing the swimming pool liner, April 2, 2015

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Apr-4-10-2015

Saturday, April 4

  • No Construction Work is Scheduled. 

Monday, April 6

  • Concrete pour for the curbs on the roof (8 meters of concrete), starting at 2:00 pm. 
  •  Interior suite drywall and finishing.
  •  Waterproofing 5th floor podium.

Tuesday, April 7

  • Drywall deliveries for the 13th floor, from 8:00 am to 1:00 pm.
  • Elevator machine room roof  concrete pour by subcontractor Italform (35meters of concrete), starting at 11:00 am.
  • Waterproofing 5th floor podium.
  • Concrete finishing till 10:00 pm

Wednesday, April 8

  • Concrete pour for the curbs on the roof (8 meters of concrete), starting at 2:00 pm. 
  •  Interior suite drywall and finishing.
  •  Starting swimming pool work on the  5th floor podium.

Thursday, April 9

  • Concrete pour for the curbs on the roof (8 meters of concrete), starting at 2:00 pm. 
  •  Interior suite drywall and finishing.
  •  Continuing swimming pool work on the  5th floor podium.

Friday, April 10

  • Concrete pour for the curbs on the roof (8 meters of concrete), starting at 2:00 pm. 
  • Interior suite drywall and finishing.
  • Continuing swimming pool work on the  5th floor podium.
Backstage interior 13th floor.

Backstage interior 13th floor.

 NOTES:

    • All rebar deliveries are now complete.
    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule March 28 – April 3, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for March 28 – April 3, 2015.   More concrete pours for the roof and more window deliveries are the featured construction activities this week. 

Backstage Condo Rooftop

Backstage Condo Rooftop

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Mar-28-Apr-3-2015

Saturday, March 28

  • Window delivery occupying north curb lane of the Esplanade, three tractor trail loads, from 9:00 am to 2:30 pm.
  • We have been advised that the City of Toronto will  be carrying out road repair and resurfacing on The Esplanade.
Backstage Condo March 27

Backstage Condo March 27

Monday, March 30

  • Mechanical roof concrete pour #2 & #3, by subcontractor Italform, to begin at 10:30 am.
  • Concrete Finishing until 10:30 pm.

Tuesday, March 31

  •  Pouring curbs on the mechanical roof (9 metres of concrete), by subcontractor Italformscheduled to run from 2:30 pm.

Wednesday, April 1

  • Concrete pour for the elevator machine room roof (30 metres of concrete), by subcontractor Italform, to begin at 10:30 am.
  • Concrete Finishing until 10:30 pm.

Thursday, April 2

  • Pouring curbs on the mechanical roof (9 metres of concrete), by subcontractor Italform, scheduled to run from 2:30 pm.

Friday, April 3

  • TBA.
Backstage Concrete Truck March 27

Backstage Concrete Truck March 27

 NOTES:

    • All rebar deliveries are now complete.
    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule March 21 – 27, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for March 21 – 27, 2015.   The remaining protective platforms are coming down this Saturday from the south side of the tower. The mechanical roof slab and wall and column concrete pours continue through the week.

Backstage condo, crane and clouds

Backstage condo, crane and clouds

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Mar-21-27-2015

Saturday, March 21

  • Subcontractor Italform will be removing the remaining protection platforms from the south side of the building, facing the railway corridor. Three (3) tractor trails will be required to transport.
  • Three trailers will arrive at 11:00 am.
Remaining protective platforms at Backstage will be coming down March 21

Remaining protective platforms at Backstage will be coming down March 21

Monday, March 23

  • A wall and column concrete pour, by subcontractor Italform (12 metres of concrete), scheduled to run from 12:30 pm.

Tuesday, March 24

  • Mechanical roof concrete pour #1, by subcontractor Italform, to begin today at 10:30 am.
  • Concrete Finishing until 10:30 pm.

Wednesday, March 25

  • A wall and column concrete pour, by subcontractor Italform (9 metres of concrete), scheduled to run from 12:30 pm.

Thursday, March 26

  • A wall and column concrete pour, by subcontractor Italform (9 metres of concrete), scheduled to run from 12:30 pm.

Friday, March 27 A wall and column concrete pour, by subcontractor Italform (9 metres of concrete), scheduled to run from 12:30 pm.

Backstage 13th floor unfinished suite.

Backstage 13th floor unfinished suite.

 NOTES:

    • All rebar deliveries are now complete.
    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule March 14 – 20, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for March 14 – 20, 2015.   Protective platforms are coming down this Saturday and secondary slab and wall and column concrete pours continue through the week.

Drywall waiting to go up at Backstage

Drywall waiting to go up at Backstage

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Mar-14-20-2015

Saturday, March 14

  • Subcontractor Italform will be removing three (3) protection platforms from the south side of the building, facing the railway corridor. Three (3) tractor trails will be required to transport.
  • The first trailer will arrive at 11:00 am.
  • The second trailer at 1:00 pm, and
  • The third trailer at 2:00 pm.
  • Most of the work will take place on the 5th floor podium and then loaded on to trailers.

Monday, March 16

  • A wall and column concrete pour, by subcontractor Italform (14 metres of concrete), scheduled to run from 1:30 pm.

Tuesday, March 17

  • Secondary slab concrete pour #1, by subcontractor Italform, to begin today at 11:30 am.
  • A wall and column concrete pour, by subcontractor Italform (9 metres of concrete), scheduled to run from 1:30 pm.
  • Concrete Finishing until 10:30 pm.

Wednesday, March 18

  • Secondary slab concrete pour #2, by subcontractor Italform, to begin today at 11:30 am.
  • A wall and column concrete pour, by subcontractor Italform (14 metres of concrete), scheduled to run from 1:30 pm.
  • Concrete Finishing until 10:30 pm.

Thursday, March 19

  • A wall and column concrete pour, by subcontractor Italform (20 metres of concrete), scheduled to run from 1:30 pm.

Friday, March 20 A wall and column concrete pour, by subcontractor Italform (12 metres of concrete), scheduled to run from 1:30 pm.

Pouring concrete at Backstage on Friday the 13th of March

Pouring concrete at Backstage on Friday the 13th of March

 NOTES:

    • All rebar deliveries are now complete.
    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule March 9 – 13

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for March 7 – 13, 2015.  

Concrete pours for the ROOF slab began last week and should be completed. Weather, though milder, may once again affect the construction schedule. Please check back for regular updates. 

Backstage rising from the podium deck

Backstage rising from the podium deck

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Mar-9-13-2015

Monday, March 9

  • Rebar delivery scheduled to run from 7:00 am.
  • A wall and column concrete pour, by subcontractor Italform (15 metres of concrete), scheduled to run from 12:30 pm.

Tuesday, March 10

  • ROOF slab concrete pour #3, by subcontractor Italform, to begin today at 10:30 am.
  • Concrete Finishing until 11:30 pm.

Wednesday, March 11

  • A wall and column concrete pour, by subcontractor Italform (34 metres of concrete), scheduled to run from 12:30 pm.

Thursday, March 12

  • A wall and column concrete pour, by subcontractor Italform (22 metres of concrete), scheduled to run from 12:30 pm.

Friday, March 13

  • A wall and column concrete pour, by subcontractor Italform (18 metres of concrete), scheduled to run from 12:30 pm.
Crane work on the podium deck at Backstage.

Crane work on the podium deck at Backstage.

 NOTES:

    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule February 28 – March 7, 2015

UPDATED on March 6, 2015 – Schedule for March 7 updated below. 

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for February 28 – March 7, 2015.  

Concrete pours for the ROOF slab were not able to begin last week. The first roof slab concrete pour work is now slated to begin this Tuesday. We have included some photos below from our visit today to the podium roof deck, 8th and 13th floors. 

Extreme weather may once again affect the construction schedule. Please check back for regular updates. 

The CN Tower & Union Station seen from the 13th floor of Backstage

The CN Tower & Union Station seen from the 13th floor of Backstage

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Feb-28-Mar-7-2015

Saturday, February 28

  • Subcontractors will be delivering two floors of windows, occupying North curb lane of the Esplanade from 9:00 am to 2:30 pm.
Backstage pool and podium deck looking east from the 8th floor

Backstage pool and podium deck looking east from the 8th floor

Monday, March 2

  • Subcontractor Italform will be forming the main roof area in preparation for pouring concrete.

Tuesday, March 3

  • Rebar delivery scheduled to run from 7:00 am.
  • ROOF slab concrete pour #1, by subcontractor Italform, to begin today at 8:00 am.
  • Concrete Finishing until 11:00 pm.

Wednesday, March 4

  • A wall and column concrete pour, by subcontractor Italform (35 metres of concrete), scheduled to run from 12:30 pm.
Looking west toward the Dominion Building from the Backstage podium roof deck

Looking west toward the Dominion Building from the Backstage podium roof deck

Thursday, March 5

  • ROOF slab concrete pour #2, by subcontractor Italform, to begin today at 10:30 am.
  • Concrete Finishing until 11:30 pm.

Friday, March 6

  • A wall and column concrete pour, by subcontractor Italform (35 metres of concrete), scheduled to run from 12:30 pm.
Looking west toward the Dominion Building from the Backstage podium roof deck

Looking west toward the Dominion Building from the Backstage podium roof deck

Saturday, March 7 – UPDATED

  • Cancelled — ROOF slab concrete pour #3, hase been rescheduled to March 10. 
  • Subcontractors will be delivering two floors of windows, occupying North curb lane of the Esplanade from 9:00 am to 2:30 pm.
Getting ready for drywall on the 8th floor of Backstage

Getting ready for drywall on the 8th floor of Backstage

 NOTES:

    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.
Backstage & L Tower Feb 27, 2015

Backstage & L Tower Feb 27, 2015 as seen looking up from the podium roof deck at Backstage

Backstage Construction Schedule February 23 – 27, 2015

This is the REVISED construction schedule for 1 The Esplanade, Backstage condominium – for February 23 – 27, 2015.  

UPDATED: Concrete pours for the ROOF slab may now begin this Friday. Extreme weather may once again affect the construction schedule. Please check back for regular updates. 

Backstage winter

Backstage winter

Click on the link for a downloadable PDF Construction Summary: Revised-Backstage & L Tower Construction Summary-Feb-23-27-2015

Monday, February 23

  • CANCELLED due to weather: A wall and column concrete pour, by subcontractor Italform (35 metres of concrete), scheduled to run from 12:30 pm.

Tuesday, February 24

  • A wall and column concrete pour, by subcontractor Italform (35 metres of concrete), scheduled to run from 12:30 pm.

Wednesday, February 25

  • A wall and column concrete pour, by subcontractor Italform (35 metres of concrete), scheduled to run from 12:30 pm.

ThursdayFebruary 26

  • Rebar deliveries starting at 7 am
  • A wall and column concrete pour, by subcontractor Italform (35 metres of concrete), scheduled to run from 12:30 pm.

Friday, February 27

  • Tentative: 36th Floor slab concrete pour #3, by subcontractor Italform, may begin today at 11:00 am.
  • Tentative: After slab, wall & column pour (35 metres of concrete). 
  • Tentative: Concrete Finishing until to 11:30 pm.
Backstage. Snow. Construction,

Backstage. Snow. Construction,

 NOTES:

    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule February 17 – 20, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for February 17 – 20, 2015.  

Note: Concrete pours for the 36th Floor slab did begin last week but once again were interrupted by severe weather. With any luck from mother nature, the 36th floor should be completed this week. Please check back for regular updates. 

Backstage condo in the winter afternoon light

Backstage condo in the winter afternoon light

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Feb-17-20-2015

There was no work on site on Monday, February 16 as crews were off for the Family Day Holiday.

Tuesday, February 17

  • 36th Floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 11:00 am.
  • After slab, wall & column pour (53 metres of concrete). 
  • Concrete Finishing until to 11:30 pm.

Wednesday, February 18

  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

ThursdayFebruary 19

  • A wall and column concrete pour, by subcontractor Italform (35 metres of concrete), scheduled to run from 12:30 pm.

Friday, February 20

  • A wall and column concrete pour, by subcontractor Italform (35 metres of concrete), scheduled to run from 12:30 pm.
Waiting for concrete in the bitter cold at the Backstage construction site

Waiting for concrete in the bitter cold at the Backstage construction site

 NOTES:

    • Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Backstage Saturday, February 14, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for Saturday, February 14, 2015.  

Note: Extreme cold weather continues to cause delays and rescheduling of concrete pours and deliveries. 

The current Backstage "construction streetscape" will be replaced by a broad sidwalk, trees, animated by retail and the entrance to the new public exhibit space on the second floor of the building.

The current Backstage “construction streetscape” will be replaced by a broad sidewalk, trees, animated by retail and the entrance to the new public exhibit space on the 2nd floor.

Saturday, February 14

  • Weather permitting, a window delivery is scheduled to bring window and glazing for 2 floors, starting at 9:00am.

The construction schedule for Monday, February 16 – Friday, February 20 was not available at post time. We will post that information by Tuesday morning. Please check back. 

Backstage Construction Schedule February 7 – 13, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for February 7 – 13, 2015.  

Note: Concrete pours for the 36th Floor slab, scheduled to begin last week, were cancelled due to severe weather. Winter worked it’s magic and the first pour was postponed again to Tuesday, February 10. Weather conditions may once again interrupt construction plans. Please check back for regular updates. 

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Feb-7-13-2015

L Tower and Backstage - Looking up February 6, 2015

L Tower and Backstage – Looking up February 6, 2015

Saturday, February 7

  • Subcontractor Italform will be assembling wall forms, starting at 9:00am.

Monday, February 9

  • Rebar delivery starting at 7:00 am.
  • CANCELLED 36th Floor slab concrete pours #1, by subcontractor Italform, scheduled to begin at 11:o0 am.
  • CANCELLED After slab, wall & column pour (40 metres of concrete). 
  • CANCELLED Concrete Finishing until to 11:30 pm.

Tuesday, February 10

  • 36th Floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 11:00 am.
  • After slab, wall & column pour (53 metres of concrete). 
  • Concrete Finishing until to 11:30 pm.

Wednesday, February 11

  • 36th Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 11:00 am.
  • After slab, wall & column pour (50 metres of concrete). 
  • Concrete Finishing until to 11:30 pm.

ThursdayFebruary 12

  • Rebar delivery, scheduled to begin at 7:00 am.
  • Work cancelled due to extreme cold: 36th Floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 11:00 am.
  • Work cancelled due to extreme cold: After slab, wall & column pour (50 metres of concrete). 
  • Work cancelled due to extreme cold: Concrete Finishing until to 11:30 pm.

Friday, February 13

  • Work cancelled due to extreme cold. 
Too cold for concrete at the Backstage construction site.

Too cold for concrete at the Backstage construction site.

 NOTES:

    • Paid Duty Police Officer is on-site daily, when available, Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control when required. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.
%d bloggers like this: