Backstage Construction Schedule April 4 – 10, 2015
April 2, 2015 Leave a comment
This is the current construction schedule for 1 The Esplanade, Backstage condominium – for April 4 – 10, 2015. More concrete pours for the roof and more window deliveries are the featured construction activities this week.
Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Apr-4-10-2015
Saturday, April 4
- No Construction Work is Scheduled.
Monday, April 6
- Concrete pour for the curbs on the roof (8 meters of concrete), starting at 2:00 pm.
- Interior suite drywall and finishing.
- Waterproofing 5th floor podium.
Tuesday, April 7
- Drywall deliveries for the 13th floor, from 8:00 am to 1:00 pm.
- Elevator machine room roof concrete pour by subcontractor Italform (35meters of concrete), starting at 11:00 am.
- Waterproofing 5th floor podium.
- Concrete finishing till 10:00 pm
Wednesday, April 8
- Concrete pour for the curbs on the roof (8 meters of concrete), starting at 2:00 pm.
- Interior suite drywall and finishing.
- Starting swimming pool work on the 5th floor podium.
Thursday, April 9
- Concrete pour for the curbs on the roof (8 meters of concrete), starting at 2:00 pm.
- Interior suite drywall and finishing.
- Continuing swimming pool work on the 5th floor podium.
Friday, April 10
- Concrete pour for the curbs on the roof (8 meters of concrete), starting at 2:00 pm.
- Interior suite drywall and finishing.
- Continuing swimming pool work on the 5th floor podium.
NOTES:
- All rebar deliveries are now complete.
- A Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.