Recap on Dec 5 Long Reach Back-hoe delivery

UPDATE: The Long Reach Back-hoe that was scheduled to arrive Wednesday, December 5, under police escort between 6:20 am and 7:00 am. It actually arrived at 5:30 am as the City of Toronto permit stipulated that the semi-trailer float (truck) had to be out of the downtown core prior to 6:00 am. Unfortunately we did not receive accurate information on the timing of the delivery.

On December 4 we were advised by subcontractor GFL Excavating that the back-hoe was coming early in the morning, instead of the originally and preferred plan to deliver it at midday. GFL could not get a permit for midday because City of Toronto staff considered the impact on daytime traffic would be too onerous. The permit was issued for 5 am to 6 am delivery and GFL was instructed by the City and the Police to have their large delivery truck off the site an out of the downtown by 6:00 am.

In this case the regulations for large deliveries trumped the regulations for construction noise; the regulating bodies determined that the traffic regulations trumped the standard construction noise regulations.  

Please click here for a revised Backstage – 1 The Esplanade construction schedule.

 
Please click here for a revised Backstage – 1 The Esplanade construction schedule.

Backstage Update for December 1

This is a construction update for 1 The Esplanade – L Tower parking and Backstage condominium  for December 1, 2012

Updated November 29

The “Long Reach” Backhoe delivery that was scheduled to arrive at 1 The Esplanade under police escort midday Friday November 30 (below) – has been cancelled because subcontractor GFL Excavation was not able to schedule the police escort until Saturday. 

CANCELLED – The Long Reach will arrive on Saturday, December 1.

The semi-trailer float will travel south bound down Yonge Street in the north bound lanes. The Long Reach Backhoe will then be off-loaded and parked in the Backstage site at the North West corner of The Esplanade and Yonge Street. 

Vehicular and Pedestrian traffic will experience delays and interruptions during this delivery. We apologize in advance for the inconvenience. 

Backstage – 1 The Espalande – Thursday March 1, Crane Removal

This is an update for Thursday, March 1 2012 for construction activity at the Backstage condominium at 1 The Esplanade.

Thursday, March 1

  • Sub-contractor, Deep Foundation will have a float arriving at 8:00 am to remove the crawler crane from the construction site. The float will be leaving the site at 9:00 am under police escort. There will be unavoidable short-term disruptions to vehicular and pedestrian traffic during this process, in order to ensure the safety of the construction crew, drivers, cyclists and pedestrians.

Update for Friday October 7 and Saturday October 8

This is an update for 1 The Esplanade for Friday, October 7:

Sub-contractor Deep Foundation will be floating out the drill rig from The Esplanade gate. The float will arrive under police escort between 10:00 am and 1:00 pm. Once loaded the float will leave under police escort.

During these hours there will be significant impact on pedestrian and vehicular traffic.

The construction management team apologizes in advance for any temporary inconvenience. All efforts will be made to ensure the operation is carried out as efficiently and safely as possible.

This is an update for 8 The Esplanade for Saturday October 8:

Dominus and Sub-contractor, Premform will work from 9:00 am – 2:00 pm on the L Tower site.