Backstage Construction Schedule – April 30 – May 4
April 27, 2012 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and
Backstage condominium – for April 30 – May 4, 2012
Posted April 27/12
Monday, April 30
- Subcontractor, Deep Foundation, will be drilling piles and caissons.
- There will be five loads of concrete delivered to the site.
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.
Tuesday, May 1
- Subcontractor, Deep Foundation, will be drilling piles and caissons.
- There will be five loads of concrete delivered to the site.
- There will be five loads of concrete delivered to the site.
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.
Wednesday, May 2
- Subcontractor, Deep Foundation, will be drilling piles and caissons.
- There will be five loads of concrete delivered to the site.
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.
Thursday, May 3
- Subcontractor, Deep Foundation, will be drilling piles and caissons.
- There will be five loads of concrete delivered to the site.
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.
Friday, May 4
- Subcontractor, Deep Foundation, will be drilling piles and caissons.
- There will be five loads of concrete delivered to the site
- Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.
* * *
NOTES:
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
Click on the link for a printable PDF of the L Tower and Backstage April 30 – May 4 summary highlights: L Tower & Backstage Construction April 30-May 4