Backstage Construction Schedule – April 30 – May 4

This is the current construction schedule for 1 The Esplanade – L Tower parking and
Backstage condominium for April 30 – May 4, 2012

Posted April 27/12

Monday, April 30

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Tuesday, May 1

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Wednesday, May 2

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Thursday, May 3

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Friday, May 4

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

* * *

NOTES:

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 30 – May 4 summary highlights: L Tower & Backstage Construction April 30-May 4

Backstage – 1 The Esplanade – Construction Schedule Jan 30 – Feb 3

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for January 30 – February 3, 2012

UPDATED January 31, 2012

Monday, January 30

  • Sub-contractor, Deep Foundation will be removing one of the drill rigs from the site, beginning at 7:00 am.
  • At approximately 10:00 am, a semi-trailer with the float for the drill rig will arrive to take it off-site. There will be short-term disruptions to pedestrian and vehicular traffic.
  • The remaining drill rig on site will continue drilling caissons and piles.
  • Five (5) loads of concrete.

Tuesday, January 31

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Five (5) loads of concrete.

Wednesday, February 1

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Five (5) loads of concrete.
  • UPDATE – Sub-contractor GFL Excavating will have three (3) dump trucks removing material from the site at 1 The Esplanade. There will be three (3) truck doing 5 rounds of removal each.

Thursday, February 2

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Five (5) loads of concrete.

Friday, February 3

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Five (5) loads of concrete.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

1 The Esplanade – Construction Schedule Jan 23 – 27, 2012

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for January 23 – 27, 2012

Posted January 20, 2012

Monday, January 23

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Tuesday, January 24

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Wednesday, January 25

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Thursday, January 26

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Friday, January 27

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

1 The Esplanade – Construction Schedule Jan 16 – 20, 2012

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for January 16 – 20, 2012

Posted January 13, 2012

Monday, January 16

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Tuesday, January 17

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Wednesday, January 18

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Thursday, January 19

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Friday, January 20

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

1 The Esplanade – Construction Schedule Jan 9 – 13, 2012

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for January 9 – 13, 2012

Posted January 6, 2012

Monday, January 9

  • Steel pile delivery at 7:00 am.
  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete into the site.
  • Sub-contractor, GFL delivering an excavator.

Tuesday, January 10

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete into the site.
  • Sub-contractor, GFL breaking the bridge retaining wall.

Wednesday, January 11

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete into the site.
  • Sub-contractor, GFL breaking the bridge retaining wall.

Thursday, January 12

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete into the site.
  • Sub-contractor, GFL breaking the bridge retaining wall.

Friday, January 13

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete into the site.
  • Sub-contractor, GFL breaking the bridge retaining wall.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Construction Schedule August 15 – 19

This is the current construction schedule for 8 The Esplanade – L Tower and 1 The Esplanade – L Tower Parking + Backstage for the week of August 15 through August 19, 2011.

Post Date – August 16/11

Monday, August 15

8 The Esplanade – L Tower 

  • There will be a 45M concrete pour, which is not expected to beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Tuesday, August 16

8 The Esplanade – L Tower 

  • There will be a 72M concrete pour, which is not expected to beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Wednesday, August 17

8 The Esplanade – L Tower 

  • There will be a 72M concrete pour, which is not expected to beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Thursday, August 18

8 The Esplanade – L Tower 

  • No concrete is scheduled as of August 12.
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Friday, August 19

8 The Esplanade – L Tower 

  • No concrete is scheduled as of August 12.
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.
NOTE: A Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm Monday through Friday; and this week  Tuesday through Friday.