Backstage Construction Schedule November 8 – 14
November 7, 2014 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for November 8 – 14, 2014.
Please note: there will be a road closure of The Esplanade from Yonge Street to Scott Street from 9:00 am to 7:00 pm Monday, November 10 and Tuesday November 12. A copy of the ROAD CLOSURE PERMIT for November 10 – 11 is provided here: SBACKSTAGE 14110715270. Pedestrian access will be provided, as safety permits, on the north side The Esplanade adjacent the L Tower.
- Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-November-8-14-2014
- Please click here for general information on concrete pours.
Saturday, November 8
- Subcontractor, Italform doing high elevation rescue training off the crane.
- Dominus construction crew doing housekeeping work on-site, from 9:00 am.
- Electrical and plumbing subcontractors working in the building from 9:00 am.
Monday, November 10
- Rebar delivery from 7:00 am.
- ROAD CLOSURE OF THE ESPLANADE – 9:00 am – 7:00 pm to permit relocation of the hoardings and concrete barriers.
- Pedestrians will be permitted access to Yonge Street on the north side of The Esplanade adjacent to the L Tower.
- 2 Paid Duty Police Officers will be on site.
- Please click on the link to the right to view or download the Road Closure Permit: SBACKSTAGE 14110715270
- 26thFloor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:30 am.
- An after-slab wall and column concrete pour (42 metres of concrete) to begin following the main slab pour.
- Concrete Finishing until to 10:30 pm.
Tuesday, November 11
- ROAD CLOSURE OF THE ESPLANADE – 9:00 am – 7:00 pm to permit relocation of the hoardings and concrete barriers.
- Pedestrians will be permitted access to Yonge Street on the north side of The Esplanade adjacent to the L Tower.
- 2 Paid Duty Police Officers will be on site.
- Please click on the link to the right to view or download the Road Closure Permit: SBACKSTAGE 14110715270
- 26thFloor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 10:30 am.
- An after-slab wall and column concrete pour (33 metres of concrete) to begin following the main slab pour.
- Concrete Finishing until to 10:30 pm.
Wednesday, November 12
- A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.
Thursday, November 13
- Rebar delivery from 7:00 am.
- 27thFloor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 10:30 am.
- An after-slab wall and column concrete pour (33 metres of concrete) to begin following the main slab pour.
- Concrete Finishing until to 10:30 pm.
, Friday, November 14
- 27th Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 10:30 am.
- An after-slab wall and column concrete pour (33 metres of concrete) to begin following the main slab pour.
- Concrete Finishing until to 10:30 pm.
NOTES:
- A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.