L Tower Construction Schedule December 30 – January 3, 2014

This is the current construction schedule for 8 The Esplanade – L Tower –  December 30, 2013 – January 3, 2014

Posted December 32014-free-greeting-card-photo-10

Monday, December 30

  • There will be general construction work inside the L Tower.

Tuesday, December 31

  • There will be general construction work inside the L Tower in the early part of the day.

HAPPY NEW YEAR – January 1, 2014

New Year’s Day

  • Site closed for the holiday.

Thursday, January 2

  • Some deliveries to the hoist and interior work.

Friday, December 20

  • Some deliveries to the hoist and interior work.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site Thursday & Friday this week, from 7:00 am to 4:00 pm daily to assist with traffic control.


L Tower Construction Schedule December 23 – 27

This is the current construction schedule for 8 The Esplanade – L Tower –  December 23 – 27, 2013

Posted December 20

Monday, December 23

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, December 24

  • There will be deliveries to the hoist throughout the day from 7:00 am finishing early in the day.
  • There will be general construction work inside the L Tower in the early part of the day.

HAPPY HOLIDAYSchristmas-tree-pics-0111

Christmas Day

  • Site closed for the holiday.

Boxing Day

  • Site closed for the holiday.

Friday, December 20

  • Site closed.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site Monday & Tuesday this week, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary-Dec-23-27-2013

L Tower Construction Schedule December 16 – 20

This is the current construction schedule for 8 The Esplanade – L Tower –  December 16 – 20, 201320131128_101011-1

Posted December 13

Monday, December 16

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, December 17

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, December 18

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, December 19

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, December 20

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary-Dec 14-20-2013

L Tower Construction Schedule December 9 – 13

This is the current construction schedule for 8 The Esplanade – L Tower –  December 9 – 13, 2013

Posted December 6
20131128_100953

Monday, December 9

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, December 10

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, December 11

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, December 12

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, December 13

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary-Dec 7-13-2013

L Tower Construction Schedule December 2 – 6

This is the current construction schedule for 8 The Esplanade – L Tower –  December 2 – 6, 201320131128_101011

Posted November 29

Monday, December 2

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, December 3

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, December 4

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, December 5

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, December 6

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click on the link to download a construction summary:  Backstage & L Tower Construction Summary Nov 30- Dec 6-2013

L Tower Construction Schedule November 25 – 29

One of L Tower's 2-storey penthouses, image by Jack Landau from Urban Toronto - http://urbantoronto.ca

One of L Tower’s 2-storey penthouses, image by Jack Landau from Urban Toronto – http://urbantoronto.ca

This is the current construction schedule for 8 The Esplanade – L Tower –  November 25 – 29, 2013

Posted November 22

Monday, November 25

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, November 26

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, November 27

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, November 28

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, November 29

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click on the link to download a construction summary:  Backstage & L Tower Construction Summary Nov 25-29–2013

L Tower Construction Schedule November 18 – 22

This is the current construction schedule for 8 The Esplanade – L Tower –  November 18 – 22, 2013

Posted November 15

Monday, November 18

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, November 19

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, November 20

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, November 21

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, November 22

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click on the link to download a construction summary:  Backstage & L Tower Construction Summary Nov 16-18–2013

L Tower Construction Schedule November 11 – 15

This is the current construction schedule for 8 The Esplanade – L Tower –  November 11 – 15, 2013

Posted November 8

Monday, November 11

  • 473px-L_Tower_Toronto_04_Jun_2013There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, November 12

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, November 13

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, November 14

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, November 15

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click on the link to download a construction summary:  Backstage & L Tower Construction Summary Nov 11-15–2013

L Tower Construction Schedule November 4 – 8

This is the current construction schedule for 8 The Esplanade – L Tower –  November 4 – 8, 201320131101_104527

Posted November 1

Monday, November 4

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, November 5

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, November 6

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, November 7

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, November 8

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click on the link to download a construction summary:  Backstage & L Tower Construction Summary Nov 2-8–2013

L Tower Construction Schedule October 28 – November 1

L Tower seen from Yonge and Front, image by Jack Landau, courtesy of http://urbantoronto.ca

L Tower seen from Yonge and Front, image by Jack Landau, courtesy of http://urbantoronto.ca

This is the current construction schedule for 8 The Esplanade – L Tower –  October 28 – November 1, 2013

Posted October 25

Monday, October 28

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Tuesday, October 29

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Wednesday, October 30

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Thursday, October 31

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Friday, November 1

  • There will be deliveries to the hoist throughout the day from 7:00 am.
  • There will be general construction work inside the L Tower.

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click on the link to download a construction summary:  Backstage & L Tower Construction Summary Oct 26-Nov 1–2013