Backstage Construction Schedule January 24 – 30, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for January 24 – 30, 2015.  

Note: 35th Floor is scheduled to be poured this week. However, depending on the severity of the weather, concrete pours noted here may be cancelled and rescheduled. Please check back for regular updates. 

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Jan-24-30-2015

Backstage Concrete Truck

Backstage Concrete Truck

Saturday, January 24, 2015

  • Window delivery–2 floors worth of exterior windows, starting at 9:00 am. There may be some impact on eastbound traffic.

Monday, January 26, 2015

  • No rebar deliveries or concrete pours scheduled. 

Tuesday, January 27, 2015

  • 35th Floor slab concrete pours #1, by subcontractor Italform, scheduled to begin at 11:00 am.
  • After slab, wall & column pour (50 metres of concrete). 
  • Concrete Finishing until to 11:00 pm.

Wednesday, January 28, 2015

  • 35th Floor slab concrete pours #2, by subcontractor Italform, scheduled to begin at 10:30 am.
  • After slab, wall & column pour (40 metres of concrete). 
  • Concrete Finishing until to 11:00 pm.

Thursday, January 29, 2015

  • Rebar delivery, scheduled to begin at 7:00 am.
  • 35th Floor slab concrete pours #3, by subcontractor Italform, scheduled to begin at 11:00 am.
  • After slab, wall & column pour (53 metres of concrete). 
  • Concrete Finishing until to 11:00 pm.

Friday, January 23, 2015

  • A wall and column concrete pour, by subcontractor Italform (63 metres of concrete), scheduled to run from 12:30 pm.
Backstage Black and White Construction Site

Backstage Black and White Construction Site

 NOTES:

    • Paid Duty Police Officer is on-site daily, when available, Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control when required. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule January 17 – 23, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for January 17 – 23, 2015.  

Note: 34th Floor is scheduled to be poured this week. However, depending on the severity of the weather, concrete pours noted here may be cancelled and rescheduled. Please check back for regular updates. 

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Jan-17-23-2015

Backstage - Straight Up from The Esplanade, January 16, 2015

Backstage – Straight Up from The Esplanade, January 16, 2015

Saturday, January 17, 2015

  • Using concrete pump to pour L Tower Parking pedestrian tunnel floor, starting at 10:30am. There will be no impact to traffic.

Monday, January 19, 2015

  • Rebar delivery, scheduled to begin at 7:00 am.
  • A wall and column concrete pour, by subcontractor Italform (43 metres of concrete), scheduled to run from 12:30 pm

Tuesday, January 20, 2015

  • 34th Floor slab concrete pours #1, by subcontractor Italform, scheduled to begin at 10:30 am.
  • After slab, wall & column pour (33 metres of concrete). 
  • Concrete Finishing until to 11:00 pm.

Wednesday, January 21, 2015

  • 34th Floor slab concrete pours #2, by subcontractor Italform, scheduled to begin at 10:30 am.
  • After slab, wall & column pour (33 metres of concrete). 
  • Concrete Finishing until to 11:00 pm.

Thursday, January 22, 2015

  • Rebar delivery, scheduled to begin at 7:00 am.
  • 34th Floor slab concrete pours #3, by subcontractor Italform, scheduled to begin at 10:30 am.
  • After slab, wall & column pour (45 metres of concrete). 
  • Concrete Finishing until to 11:00 pm.

Friday, January 23, 2015

  • A wall and column concrete pour, by subcontractor Italform (43 metres of concrete), scheduled to run from 12:30 pm.
Backstage Looking Up - January 16, 2015

Backstage Looking Up – January 16, 2015

 NOTES:

    • Paid Duty Police Officer is on-site daily, when available, Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control when required. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule January 10 – 16, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for January 10 – 16, 2015.  Note: All concrete pours from last week have been rescheduled to this week due to last week’s severe weather. 

Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Jan-10-16-2015

Dominion Building from Backstage Condo

Dominion Building from Backstage Condo

 

Saturday, January 10, 2015

  • Three tractor trail loads of windows will be delivered, starting at 9:00 am.
  • The south curb lane of The Esplanade will be occupied during delivery times.

Monday, January 12, 2015

  • 33rdFloor slab concrete pours #1 + #2, by subcontractor Italform, scheduled to begin at 8:00 am.
  • Concrete Finishing until to 11:30 pm.

Tuesday, January 13, 2015

  • Rebar delivery, scheduled to begin at 7:00 am.
  • CANCELLED – A wall and column concrete pour, by subcontractor Italform (43 metres of concrete), scheduled to run from 12:30 pm

Wednesday, January 14, 2015

  • 33rdFloor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 10:30 am.
  • After slab, wall & column pour (33 metres of concrete). 
  • Concrete Finishing until to 11:00 pm.

Thursday, January 15, 2015

  • CANCELLED – Rebar delivery, scheduled to begin at 7:00 am.
  • A wall and column concrete pour, by subcontractor Italform (43 metres of concrete), scheduled to run from 12:30 pm.

Friday, January 16, 2015

  • A wall and column concrete pour, by subcontractor Italform (43 metres of concrete), scheduled to run from 12:30 pm.
Concrete Truck pulling into Backstage

Concrete Truck pulling into Backstage

 NOTES:

    • Paid Duty Police Officer is on-site daily, when available, Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control when required. 
    • Concrete pour schedules and times are subject to weather conditions.
    • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
    • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule January 5 – 9, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for January 5 – 9, 2015.  

Note: Due to severe weather all concrete pours were cancelled this week.

View from Backstge to the Dominon Building and the Royal York

View from Backstage to the Dominion Building and the Royal York

 

Monday, January 5, 2015

  • Concrete pours cancelled. 

Tuesday, January 6, 2015

  • Concrete pours cancelled. 

Wednesday, January 7, 2015

  • Concrete pours cancelled. 

Thursday, January 8, 2015

  • Tentative – Rebar delivery, scheduled to begin at 7:00 am.
  • Concrete pours cancelled. 

 

Friday, January 9, 2015

  • Concrete pours cancelled. 

 NOTES:

  • Paid Duty Police Officer is on-site daily, when available, Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control when required. 
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule December 29 – January 3

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for December 29, 2014 – January 3, 2015. The next schedule will be published by Monday, January 5.

NOTE: Concrete pours resume on January 5, 2015. 

Happy New Year!

Backstage 4th floor looking west

Backstage 4th floor looking west

Monday, December 29

  • Interior work on-site.
  • Housekeeping work on-site.

Tuesday, December 30

  • Interior work on-site.
  • Housekeeping work on-site.

Wednesday, December 31

  • Interior work. Site closing early. 

Thursday, January 1 – Site Closed for the Holiday. 

Friday, January 2

  • Internal work on site from 9:00 am.

Saturday, January 3 

  • Internal work on site from 9:00 am.
Backstage 4th Floor Looking Southwest

Backstage 4th Floor Looking Southwest

 NOTES:

  • Paid Duty Police Officer is on-site daily, when available, Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control when required. 
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule October 11 – 13

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for October 11 – 13, 2014

 Please click here for general information on concrete pours

Saturday, October 11

  • Dominus construction doing housekeeping work on site, from 9:00 am.

Monday, October 13 – Site Closed for Thanksgiving 

Backstage condo, October 10, 2014

Backstage condo, October 10, 2014

NOTE: The construction update for Tuesday, October 14 – Friday, October 17, will be posted by Tuesday morning, October 14. 