Backstage Construction Schedule – October 1 – 5

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for October 1 – 5, 2012

Posted September 28, 2012

Monday, October 1 

  • Hydraulic breaking of the shale.
  • Tentative – Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Tuesday, October 2 

  • Hydraulic breaking of the shale.
  • Subcontractor C&M McNally pouring concrete. Please note: that there here may be short-term disruptions to pedestrian and vehicular traffic.
  • Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Wednesday, October 3

  • Hydraulic breaking of the shale.
  • Subcontractor C&M McNally pouring concrete. Please note: that there here may be short-term disruptions to pedestrian and vehicular traffic.
  • Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Thursday, October 4

  • Hydraulic breaking of the shale.
  • Subcontractor C&M McNally pouring concrete. Please note: that there here may be short-term disruptions to pedestrian and vehicular traffic.
  • Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Friday, October 5

  • Hydraulic breaking of the shale.
  • Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower – Backstage Construction Sept 29 – Oct 5

Friday, September 28 – Daytime Road Closure of the Esplanade from Scott to Yonge – 7 am – 6 pm

REMINDER – Backstage Construction Update

Posted September 27, 2012

Friday, September 28 – Daytime Road Closure of the Esplanade from Scott to Yonge – 7 am – 6 pm

  • The Esplanade will be closed between 7 am and 6 pm for the mobile crane that will hoist steel lining sections into place. *
  • Subcontractor C&M McNally will be continuing work to complete the stainless steel tunnel lining. *
  • Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. **

NOTES: 

* The daytime road closure will be necessary to ensure public safety during the loading in, with a heavy crane of the stainless steel lining. Each lining section must be completed within the same day that it is delivered in order to ensure that it is properly installed and sealed. 

** Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Backstage Construction Schedule – September 24 – 28

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for September 24 – 28, 2012

Updated September 27, 2012

Monday, September 24 – Daytime Road Closure of the Esplanade from Scott to Yonge – 7 am – 6 pm

  • The Esplanade will be closed between 7 am and 6 pm for the mobile crane that will hoist steel lining sections into place. *
  • Wide-load delivery with police escort, via Scot Street, expected after 10 am, depending on traffic conditions.
  • Subcontractor C&M McNally will be installing the stainless steel tunnel lining. *
  • Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. **

Tuesday, September 25 

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. **

Wednesday, September 26 

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. **

Thursday, September 27 

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. **

Friday, September 28 – Daytime Road Closure of the Esplanade from Scott to Yonge – 7 am – 6 pm

  • The Esplanade will be closed between 7 am and 6 pm for the mobile crane that will hoist steel lining sections into place. *
  • Subcontractor C&M McNally will be continuing work to complete the stainless steel tunnel lining. *
  • Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. **

NOTES: 

* The daytime road closure will be necessary to ensure public safety during the loading in, with a heavy crane of the stainless steel lining. Each lining section must be completed within the same day that it is delivered in order to ensure that it is properly installed and sealed. 

** Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction September 24-28

Backstage Construction Schedule – September 17 – 21

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for September 17 – 21, 2012

Updated September 16, 2012

NOTE: Further details on the daytime road closures will be posted on Monday, September 17

Monday, September 17 

  • Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Tuesday, September 18 – Daytime Road Closure of the Esplanade from Scott to Yonge – 7 am – 6 pm

  • Wide-load delivery with police escort, via Scot Street, expected between 7 am and 10 am, depending on traffic conditions. 
  • Subcontractor C&M McNally will be installing the stainless steel tunnel lining. *
  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 14 loads each, for a total of fifty-six (56) loads. **

Wednesday, September 19 – Daytime Road Closure of the Esplanade from Scott to Yonge – 7 am – 6 pm

  • Wide-load delivery with police escort, via Scot Street, expected between 7 am and 10 am, depending on traffic conditions.
  • Subcontractor C&M McNally will be installing the stainless steel tunnel lining. *
  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 14 loads each, for a total of fifty-six (56) loads. **

Thursday, September 20 – Daytime Road Closure of the Esplanade from Scott to Yonge – 7 am – 6 pm

  • Wide-load delivery with police escort, via Scot Street, expected between 7 am and 10 am, depending on traffic conditions.
  • Subcontractor C&M McNally will be installing the stainless steel tunnel lining. *
  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 14 loads each, for a total of fifty-six (56) loads. **

Friday, September 21– Daytime Road Closure of the Esplanade from Scott to Yonge – 7 am – 6 pm

  • Wide-load delivery with police escort, via Scot Street, expected between 7 am and 10 am, depending on traffic conditions.
  • Subcontractor C&M McNally will be installing the stainless steel tunnel lining. * 
  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 14 loads each, for a total of fifty-six (56) loads. **

NOTES: 

* The daytime road closure will be necessary to ensure public safety during the loading in, with a heavy crane of the stainless steel lining. Each lining section must be completed within the same day that it is delivered in order to ensure that it is properly installed and sealed. 

** Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction September 8-14

Backstage Construction Schedule – September 10 – 14

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for September 10 – 14, 2012

Posted September 7, 2012

Monday, September 10 

  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 14 loads each, for a total of fifty-six (56) loads. *
  • Subcontractor, Deep Foundation will be installing rock anchors.

Tuesday, September 11

  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 14 loads each, for a total of fifty-six (56) loads. *
  • Subcontractor, Deep Foundation will be installing rock anchors.

Wednesday, September 12

  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 14 loads each, for a total of fifty-six (56) loads. *
  • Subcontractor, Deep Foundation will be will be installing rock anchors.

Thursday, September 13

  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 14 loads each, for a total of fifty-six (56) loads. *
  • Subcontractor, Deep Foundation will be installing rock anchors.

Friday, September 14

  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 14 loads each, for a total of fifty-six (56) loads. *
  • Subcontractor, Deep Foundation will be installing rock anchors.

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction September 8-14

Backstage Construction Schedule – September 4 – 7

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for September 4 – 7, 2012

Posted August 31, 2012

Monday, September 3 – Labour Day – Holiday 

Tuesday, September 4

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
  • Subcontractor, Deep Foundation will be installing rock anchors.

Wednesday, September 5

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
  • Subcontractor, Deep Foundation will be will be installing rock anchors.

Thursday, September 6

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
  • Subcontractor, Deep Foundation will be installing rock anchors.

Friday, September 7

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
  • Subcontractor, Deep Foundation will be installing rock anchors.

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: Revised L Tower – Backstage Construction Sept 4-7

Backstage Construction Schedule – August 27 – 31

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for August 27 – 31, 2012

Posted August 24, 2012

Monday, August 27

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Tuesday, August 28

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Wednesday, August 29

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
  • Subcontractor, Deep Foundation will be bringing in a rock anchor drill and beginning to install the last row of tie backs.
    • Please Note: there may be disrutions to pedestrian and vehicualr traffic during the delivery and unloading of the drill.

Thursday, August 30

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
  • Subcontractor, Deep Foundation will be installing the last row of tie backs.

Friday, August 31

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
  • Subcontractor, Deep Foundation will be installing the last row of tie backs.

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: Revised L Tower & Backstage Construction August 28-31

Backstage Construction Schedule – August 20 – August 24

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for August 20 – August 24, 2012

Posted August 17, 2012

Monday, August 20

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Tuesday, August 21

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Wednesday, August 22

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Thursday, August 23

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Friday, August 24

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction August 18 – 24

Backstage Construction Schedule – August 13 – August 17

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for August 11 – August 17, 2012

Updated August 13, 2012

PLEASE NOTE:

  • The Esplanade reopened on August 13th to Eastbound vehicles between Yonge Street and Scott Street and pedestrians Eastbound and Westbound between Yonge Street and Scott Street.

Monday, August 13

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Tuesday, August 14

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Wednesday, August 15

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Thursday, August 16

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Friday, August 17

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction August 11 -17

Backstage Construction Schedule – August 4 – August 10

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for August 4 – August 10, 2012

Updated August 3, 2012

  • The 30 day road closure of The Esplanade from Scott Street to Yonge Street remains in effect.

Monday, August 6 – Civic Holiday

Tuesday, August 7

  • Sub-contractor, C & M McNally boring the tunnel.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Wednesday, August 8

  • Sub-contractor, C & M McNally boring the tunnel.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Thursday, August 9

  • C & M McNally removing Tunnel Boring Machine
  • There will be significant impact to The Esplanade and surrounding streets due to the setup of a 500 ton crane, support semis and 130 foot long float to take away the Tunnel Boring Machine. There will be a police escort for the float as it leaves the site.

Friday, August 10

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: Construction Summary August 4 – August 10

%d bloggers like this: