Backstage Construction Schedule – October 1 – 5
September 28, 2012 Leave a comment
This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium – for October 1 – 5, 2012
Posted September 28, 2012
Monday, October 1
- Hydraulic breaking of the shale.
- Tentative – Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
Tuesday, October 2
- Hydraulic breaking of the shale.
- Subcontractor C&M McNally pouring concrete. Please note: that there here may be short-term disruptions to pedestrian and vehicular traffic.
- Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
Wednesday, October 3
- Hydraulic breaking of the shale.
- Subcontractor C&M McNally pouring concrete. Please note: that there here may be short-term disruptions to pedestrian and vehicular traffic.
- Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
Thursday, October 4
- Hydraulic breaking of the shale.
- Subcontractor C&M McNally pouring concrete. Please note: that there here may be short-term disruptions to pedestrian and vehicular traffic.
- Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
Friday, October 5
- Hydraulic breaking of the shale.
- Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
NOTES:
* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.
Construction activities are dependent on whether.
A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
Please click here for a downloadable construction summary: L Tower – Backstage Construction Sept 29 – Oct 5