L Tower Construction Schedule November 12 – 16

This is the current construction schedule for 8 The Esplanade – L Tower – for  November 12 – 16, 2012

Posted November 9, 2012

Monday, November 12

  • A delivery of 3 containers of window/curtain wall between 7:00 am and 4:00 pm

Tuesday, November 13

  • A 18 cubic metre concrete pour at 1:00 pm, levels 60 – 61, expected to finish prior to 7:00 pm.

Wednesday, November 14

  • A 18 cubic metre concrete pour at 1:00 pm, levels 60 – 61, expected to finish prior to 7:00 pm.

Thursday, November 15

  • A 18 cubic metre concrete pour at 1:00 pm, levels 60 – 61, expected to finish prior to 7:00 pm.
  • A rebar (steel) delivery starting at 12:30 pm.
  • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Friday, November 16

  • No scheduled work at this time.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction November 12 – 16

L Tower Construction Schedule November 3 – 9

This is the current construction schedule for 8 The Esplanade – L Tower – for  November 3 – 9, 2012

Posted November 2, 2012

Saturday, November 3

  • A delivery of 3 containers of window/curtain wall between 9:00 am and 2:00 pm
  • Platform removal continuing. 

Monday, November 5

  • Platform removal continuing. 
  • A rebar (steel) delivery starting at 7:00 am.
  • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • A 73 cubic metre concrete pour pour at 2:00 pm, levels 60 – 61, expected to finish prior to 7:00 pm.
  • Please note: this concrete pour may be shifted to Tuesday. 

Tuesday, November 6

  • A rebar (steel) delivery starting at 12:30 pm.
  • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • A 63 cubic metre concrete pour pour at 1:00 pm, levels 60 – 61, expected to finish prior to 7:00 pm.
  • Please note: this concrete pour may be shifted to Wednesday. 

Wednesday, November 7

  • A rebar (steel) delivery starting at 7:00 am.
  • A stud delivery starting scheduled from 7:00 am to 10:00 am.
  • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Thursday, November 8

  • A rebar (steel) delivery starting at 7:00 am.
  • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Friday, November 9

  • A rebar (steel) delivery starting at 12:30 pm.
  • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower – Backstage Construction Nov 5-9

L Tower Construction Schedule October 27 – November 2

This is the current construction schedule for 8 The Esplanade – L Tower – for October 27 – November 2, 2012

Posted October 26, 2012

Saturday, October 27

  • A delivery of 2 containers of window/curtain wall between 9:00 am and 2:00 pm

Monday, October 29

  • There will be a platform removal
  • A rebar (steel) delivery starting at 12:30 pm.

Tuesday, October 30

  • A rebar (steel) delivery starting at 12:30 pm.

Wednesday, October 31

  • The boom crane will be on site to move concrete pump.
  • A rebar (steel) delivery starting at 12:30 pm.

Thursday, November 1

  • A rebar (steel) delivery starting at 12:30 pm.

Friday, November 2

  • A rebar (steel) delivery starting at 7:00 am.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction October 27 – November 2

L Tower Construction Schedule September 29 – October 5

This is the current construction schedule for 8 The Esplanade – L Tower – for September 29 – October 5, 2012

Posted September 28, 2012

Saturday, September 29

  • Washroom Servicing 9:00 am to Noon.
  • Crane raising. 

Monday, October 1

  • Delivery of (two) 2 lifts; Cooltech, HVAC at 7:00 am.
  • A rebar (steel) delivery starting at 7:00 am.
  • A delivery of 4 containers of window/curtain wall
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • An 18 to 27 cubic meter concrete pour for the housekeeping pads – 18 to 27 meters starting at 1 pm, to be completed by 5:00 pm..

Tuesday, October 2

  • A rebar (steel) delivery starting at 7:00 am.
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • An 18 to 27 cubic meter concrete pour for the housekeeping pads – 18 to 27 meters starting at 1 pm, to be completed by 5:00 pm.

Wednesday, October 3

  • An 18 to 27 cubic meter concrete pour for the housekeeping pads – 18 to 27 meters starting at 1 pm, to be completed by 5:00 pm.

Thursday, October 4

  • An 18 to 27 cubic meter concrete pour for the housekeeping pads – 18 to 27 meters starting at 1 pm, to be completed by 5:00 pm.

Friday, October 5

  • An 18 to 27 cubic meter concrete pour for the housekeeping pads – 18 to 27 meters starting at 1 pm, to be completed by 5:00 pm.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower – Backstage Construction Sept 29 – Oct 5

L Tower Construction Schedule September 24 – 28

This is the current construction schedule for 8 The Esplanade – L Tower – for September 24 – 28, 2012

Posted September 21, 2012

Monday, September 24

  • A delivery of four (4) containers of glass from  7:00 am through 4:00 pm.
  • A second delivery of HVAC units at 7:00 am. 
    • Please note:
            1. There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded. 
            2. To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • Curbs concrete pour starting at approximately 2:00 pm, which is not expected to extend beyond 7:00 pm.

Tuesday, September 25

  • A delivery of door hardware from subcontractor CityWide at 10:00 am.
    • Please note:
          • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded. 
          • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Wednesday, September 26

  • To Be Determined – the website will be updated once information is available.

Thursday, September 27

  • A rebar (steel) delivery starting at 7:00 am.
    • Please note:
          • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded. 
          • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Friday, September 28

  • A rebar (steel) delivery starting at 7:00 am.
    • Please note:
          • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded. 
          • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction September 24-28