Backstage Construction Schedule – April 1 – 5, 2013 – Updated

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for April 1 65, 2013

Updated April 3 –  2013

Monday, April 1

  • Formwork deliveries by subcontractor Italform, from 7:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour should  be completed prior to 7:00 pm, subject to weather conditions. 

Tuesday, April 2

  • Formwork deliveries by subcontractor Italform, from 7:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour should  be completed prior to 7:00 pm, subject to weather conditions. 

Wednesday, April 3 – Updated

  • Formwork deliveries by subcontractor Italform, from 7:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A slab concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will extend to at least  8:30 pm this evening.

Thursday, April 4 

  • Formwork deliveries by subcontractor Italform, from 7:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour should  be completed prior to 7:00 pm, subject to weather conditions.

Friday, April 5

  • Formwork deliveries by subcontractor Italform, from 7:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour may extend later than 7:00 pm, subject to weather conditions. 

Saturday, April 6 – Daytime Vehicular Road Closure – click here for details

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click here for a downloadable construction summary: Backstage & L Tower Construction Summary April 1-5-2013

Update – Backstage Construction Schedule – March 28 – 30

This is an update to the construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  March 28 – 30, 2013

UPDATED March 28, 2013

Thursday, March 28 

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • The long reach will be used to take material out from the site; 3 dump trucks will be taking approximately 10 loads each, for an estimated total of 30 loads
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will be completed prior to 7:00 pm.
  • Installation of new hoardings and covered walkway on The Esplanade.

Friday, March 29 – GOOD FRIDAY – Holiday

Saturday, March 30

  • Dominus will be doing clean up work on-site.
  • The long reach will be removed from the site. There may be some short-term interruptions to traffic access through the site during this process.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

The schedule for April 2 – 5, 2013 will be posted on March 28. Backstage & L Tower Construction Summary April 1-5-2013

Backstage Construction Schedule – March 23 – 29

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  March 23 – 29, 2013

Updated – March 27, 2013

Saturday, March 23

  • Dominus will be doing clean up work on-site.

Monday, March 25

  • Dominus will receive gravel for the slab on the lowest grade base. Two dump trucks will be working throughout the day approximately 10 loads of  gravel.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will be completed prior to 7:00 pm.

Tuesday, March 26

  • GFL Excavating will be using the Long Reach to remove material, there will be 3 dump trucks taking up to 14 loads each for an estimated total of 42 loads.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will be completed prior to 7:00 pm.

Wednesday, March 27

  • Dominus will receive gravel for the slab on the lowest grade base. Two dump trucks will be working throughout the day approximately 10 loads of  gravel.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings and slab concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour should be completed by to 7:00 pm.

Thursday, March 28 

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will be completed prior to 7:00 pm.

Friday, March 29 – GOOD FRIDAY – Holiday

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click here for a downloadable construction summary: Backstage & L Tower Construction Summary March 23-29

Backstage Construction Schedule – March 16 – 22

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  March 16 – 22, 2013

Posted March 15, 2013

Saturday, March 16

  • Dominus will be doing general labour work on-site, no machinery is scheduled to be operating.

Monday, March 18

  • GFL Excavating will be using the Long Reach to remove material, there will be 4 dump trucks taking up to 12 loads each for an estimated total of 48 loads.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, at levels P6 and P5. The pour will be completed prior to 7:00 pm.

Tuesday, March 19

  • GFL Excavating will be using the Long Reach to remove material, there will be 4 dump trucks taking up to 12 loads each for an estimated total of 48 loads.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, at levels P6 and P5. The pour will be completed prior to 7:00 pm.

Wednesday, March 20

  • There will be a Reinforcing Steel delivery starting at 7:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, at levels P6 and P5. The pour will be completed prior to 7:00 pm.

Thursday, March 21 

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, at levels P6 and P5. The pour will be completed prior to 7:00 pm.

Friday, March 22

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, at levels P6 and P5. The pour will be completed prior to 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click here for a downloadable construction summary: Backstage & L Tower Construction Summary March 16-22

Backstage Construction Schedule – March 9 – 15

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  March 9 – 15, 2013

Posted March 8, 2013

Saturday, March 9

  • Dominus will be operating a compressor with a 60lb breaker to break-up shale – work is scheduled to start at 9:00 am.

Monday, March 11

  • Rebar delivery is scheduled between 9:00 am and 11:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, that will use five (5) loads of concrete. The pour will be completed prior to 7:00 pm.

Tuesday, March 12

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, that will use five (5) loads of concrete. The pour will be completed prior to 7:00 pm.

Wednesday, March 13

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, that will use five (5) loads of concrete. The pour will be completed prior to 7:00 pm.

Thursday, March 14 

  • A rebar delivery is scheduled to occur between 9:00 am and 11:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, that will use five (5) loads of concrete. The pour will be completed prior to 7:00 pm.

Friday, March 15

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, that will use five (5) loads of concrete. The pour will be completed prior to 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click here for a downloadable construction summary: Update – L Tower & Backstage Construction Summary March 9 -15

Backstage Construction Schedule – March 4 – 8

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  March 4 – 8, 2013

Posted March 1, 2013

Monday, March 4

  • GFL Excavating will be removing material with the long reach: five (5) dump trucks are scheduled to take fourteen (14) loads each from the site for an estimated total of 70 loads.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall concrete pour by subcontractor Italform, that will use three (3) loads of concrete. The pour will be completed prior to 7:00 pm.

Tuesday, March 5

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, that will use three (3) loads of concrete. The pour will be completed prior to 7:00 pm.

Wednesday, March 6

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, that will use three (3) loads of concrete. The pour will be completed prior to 7:00 pm.

Thursday, March 7 

  • A rebar delivery is scheduled to occur between 9:00 am and 11:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, that will use three (3) loads of concrete. The pour will be completed prior to 7:00 pm.

Friday, March 8

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, that will use three (3) loads of concrete. The pour will be completed prior to 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click here for a downloadable construction summary: L Tower & Backstage Construction – Mar 4-8

Backstage Construction Schedule – February 25 – March 1

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  February 25 – March 1, 2013

Posted February 22, 2013

Monday, February 25 

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A 50M (cubic metre) concrete pour by subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm.

Tuesday, February 26 

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A 50M (cubic metre) concrete pour by subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm.

Wednesday, February 27

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A 50M (cubic metre) concrete pour by subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm.

Thursday, February 28

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A 50M (cubic metre) concrete pour by subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm.

Friday, March 1

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A 50M (cubic metre) concrete pour by subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click here for a downloadable construction summary: L Tower & Backstage Construction – Feb 25 – Mar 1

Backstage Construction Schedule – February 18 – 22

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  February 18 – 22, 2013

Posted February 15, 2013

Monday, February 18 – FAMILY DAY HOLIDAY 

  • Site closed for the holiday.

Tuesday, February 19 

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A 50M (cubic metre) concrete pour by Subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm.

Wednesday, February 20

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A 50M (cubic metre) concrete pour by Subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm.

Thursday, February 21

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A 50M (cubic metre) concrete pour by Subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm.

Friday, February 22

  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A 50M (cubic metre) concrete pour by Subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click here for a downloadable construction summary: L Tower & Backstage Construction – Feb 16-22

Updates for Backstage Construction Schedule – February 12 & 15

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  February 11 – 15, 2013

Updated February 11, 2013

Tuesday, February 12 – UPDATED 

  • GFL Excavating will be preparing material using the hydraulic breaker to prepare the footings.
  • GFL Excavating will be removing material, 3 dump trucks 14 loads each.

Wednesday, February 13

  • GFL Excavating will be preparing material using the hydraulic breaker to prepare the footings.
  • A 20M (cubic metre) concrete pour by Subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm.

Thursday, February 14

  • GFL Excavating will be preparing material using the hydraulic breaker to prepare the footings.
  •  A 20M (cubic metre) concrete pour by Subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm.

Friday, February 15 – UPDATED

  • GFL Excavating will be preparing material using the hydraulic breaker to prepare the footings.
  • A rebar delivery is scheduled to begin at 11:00 am.
  • A 20M (cubic metre) concrete pour by Subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm. 

NOTES:Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control


Backstage Construction Schedule – February 11 – 15

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  February 11 – 15, 2013

Updated February 11, 2013

Monday, February 11

  • GFL Excavating will be preparing material using the hydraulic breaker to prepare the footings.

Tuesday, February 12 – UPDATED 

  • GFL Excavating will be preparing material using the hydraulic breaker to prepare the footings.
  • GFL Excavating will be removing material, 3 dump trucks 14 loads each.

Wednesday, February 13

  • GFL Excavating will be preparing material using the hydraulic breaker to prepare the footings.
  • A 20M (cubic metre) concrete pour by Subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm

Thursday, February 14

  • GFL Excavating will be preparing material using the hydraulic breaker to prepare the footings.
  •  A 20M (cubic metre) concrete pour by Subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm.

Friday, February 15 – UPDATED

  • GFL Excavating will be preparing material using the hydraulic breaker to prepare the footings.
  • A rebar delivery is scheduled to begin at 11:00 am.
  • A 20M (cubic metre) concrete pour by Subcontractor Italform is scheduled today. The pour will be completed prior to 7:00 pm. 

NOTES:Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control

Please click here for a downloadable construction summary: L Tower & Backstage Construction – Feb 9-15