Update for Backstage Construction Schedule – April 5 & 6

This is the update t the construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for April 5 – 6, 2013

Updated April 5 –  2013

Friday, April 5 – Updated

  • Formwork deliveries by subcontractor Italform, from 7:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • Italform will be pouring parking level 5–pour #1. This pour will start at 9:30am and will take approximately 3 hours to place the concrete. It is anticipated that the concrete finishing will go to 10:30 pm.

Saturday, April 6 – Daytime Vehicular Road Closure

  • GFL Excavating will hoisting excavators out of the excavation to facilitate this Dominus is applying for a vehicular road closure on The Esplanade from Yonge Street to Scott Street. Domius has also requested two paid duty officers.
  • The hoisting operation is estimated to start at 9:00am and go to 1:00pm

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click here for a downloadable construction summary: 

Backstage Construction Schedule – April 3 – 6, 2013 – Updated

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for April 3 – 6, 2013

Updated April 5 –  2013

Wednesday, April 3 – – Updated

  • Formwork deliveries by subcontractor Italform, from 7:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A slab concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour will extend to at least  8:30 pm this evening.

Thursday, April 4 

  • Formwork deliveries by subcontractor Italform, from 7:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • A wall and footings concrete pour by subcontractor Italform, 50 cubic metres of concrete. The pour should  be completed prior to 7:00 pm, subject to weather conditions. 

Friday, April 5 – Updated

  • Formwork deliveries by subcontractor Italform, from 7:00 am.
  • GFL Excavating will be using the hydraulic breaker to prepare the footings; the footings will then be dug out.
  • Italform will be pouring parking level 5–pour #1. This pour will start at 9:30am and will take approximately 3 hours to place the concrete. It is anticipated that the concrete finishing will go to 10:30 pm.

Saturday, April 6 – Daytime Vehicular Road Closure

  • GFL Excavating will hoisting excavators out of the excavation to facilitate this Dominus is applying for a vehicular road closure on The Esplanade from Yonge Street to Scott Street. Domius has also requested two paid duty officers.
  • The hoisting operation is estimated to start at 9:00am and go to 1:00pm

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click here for a downloadable construction summary: 

Backstage Construction Schedule – December 17 – December 21

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for December 17 – December 21, 2012

Updated December 17, 2012

Monday, December 17

  • GFL Excavating will be setting up long reach and will be removing material from the site: six (6) dump trucks will take fourteen (14) loads each, for a total of eighty-four (84) loads. **
  • OJCR will be tying in water lines on the Esplanade.

Tuesday, December 18

  • GFL Excavating will not be removing material. They will be operating the hydraulic breaker and preparing material, this will cause significant noise during construction hours.
  • OJCR will be tying in water lines on the Esplanade.

Wednesday, December 19

  • GFL Excavating will not be removing material. They will be operating the hydraulic breaker and preparing material.
  • OJCR will be tying in water lines on the Esplanade.

Thursday, December 20

  • GFL Excavating will be using the long reach and will be removing material from the site: six (6) dump trucks will take fourteen (14) loads each, for a total of eighty-four (84) loads. **

Friday, December 21

  • GFL Excavating will be using the long reach and will be removing material from the site: six (6) dump trucks will take fourteen (14) loads each, for a total of eighty-four (84) loads. **

NOTES: 

** Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Continuing Sanitary Sewer & Water Main work on The Esplanade 

City of Toronto contractor — OJCR Construction — continues water main work on The Esplanade between Yonge Street and Scott Street. 

  1. Pedestrian traffic will remain open. 
  2. Eastbound Vehicular Traffic may be closed during work hours. 
  3. We have advised the City of complaints we have received in respect to their work. 

If you have further questions please contact: 

Joseph Sinopoli
Toronto Water
416-338-6526 Office

Paid Duty Police Officer is on-site  daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction December 17 – December 21

Backstage Construction Schedule – December 8 – December 14

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for December 8 – December 14, 2012

Posted December 7, 2012

Saturday, December 8

  • GFL Excavating will be assembling the long reach backhoe.

Monday, December 10

  • GFL Excavating will be operating machinery in the hole moving material in preparation for the long reach.
  • OJCR will be working on Yonge Street due to the L Tower concrete pour.

Tuesday, December 11

  • GFL Excavating will be operating machinery in the hole moving material in preparation for the long reach.
  • OJCR will be working on service connection on the Esplanade.

Wednesday, December 12

  • GFL Excavating will be setting up long reach and will be removing material from the site: six (6) dump trucks will take fourteen (14) loads each, for a total of eighty-four (84) loads.
  • OJCR will be tying in water lines on the Esplanade.

Thursday, December 13

  • GFL Excavating will be using the long reach and will be removing material from the site: six (6) dump trucks will take fourteen (14) loads each, for a total of eighty-four (84) loads.
  • OJCR will be tying in water lines on the Esplanade.

Friday, December 14

  • GFL Excavating will be using the long reach and will be removing material from the site: six (6) dump trucks will take fourteen (14) loads each, for a total of eighty-four (84) loads.
  • OJCR will be working on Yonge Street connecting the storm drain.

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site  daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction December 8 – December 14

Backstage Construction Schedule – December 3 – December 7

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for December 3 – December 7, 2012

Updated December 4, 2012

Monday, December 3 

  •  CANCELED GFL Excavating will be assembling the long reach backhoe and will be operating machinery in the hole moving material in preparation for the long reach. 
  • OJCR will be working on service connection on the Esplanade.

Tuesday, December 4

  •  CANCELED GFL Excavating will be assembling the long reach backhoe and will be operating machinery in the hole moving material in preparation for the long reach. 
  • OJCR will be working on service connection on the Esplanade.

Wednesday, December 5

  • The Long Reach back-hoe will be delivered to the site midday under police escort
  • OJCR will be tying in water lines on the Esplanade.

Thursday, December 6

  • GFL Excavating will be assembling the long reach backhoe and will be operating machinery in the hole moving material in preparation for the long reach.
  • OJCR will be tying in water lines on the Esplanade.

Friday, December 7

  • GFL Excavating will be assembling the long reach backhoe and will be operating machinery in the hole moving material in preparation for the long reach. 
  • OJCR will be tying in water lines on the Esplanade.

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site  daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction December 3 – December 7

Backstage Construction Site Photos March 16/12

Backstage Construction site March 16, 2012 looking west to Yonge Street Railway Bridge

Excavating bulk - 1 The Esplanade - March 16, 2012

Excavating 1 The Esplanade - March 16, 2012

Loading the dirt into the dump truck - 1 load of 50 per day - 1 The Esplanade March 16, 2012

Backstage – Construction Schedule Feb 27 – Mar 2

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for February 27 – March 2, 2012

Posted February 24, 2012

Monday, February 27

  • Sub-contractor, GFL Excavating, doing bulk excavating, with fifteen (15) dump trucks removing material from the site, doing five (5) rounds each.

Tuesday, February 28

  • Sub-contractor, GFL Excavating, doing bulk excavating, with fifteen (15) dump trucks removing material from the site, doing five (5) rounds each.

Wednesday, February 29

  • Sub-contractor, GFL Excavating, doing bulk excavating, with fifteen (15) dump trucks removing material from the site, doing five (5) rounds each.

Thursday, March 1

  • Sub-contractor, GFL Excavating, doing bulk excavating, with fifteen (15) dump trucks removing material from the site, doing five (5) rounds each.

Friday, March 2

  • Sub-contractor, GFL Excavating, doing bulk excavating, with fifteen (15) dump trucks removing material from the site, doing five (5) rounds each.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.