Backstage Construction Schedule – August 20 – August 24

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for August 20 – August 24, 2012

Posted August 17, 2012

Monday, August 20

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Tuesday, August 21

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Wednesday, August 22

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Thursday, August 23

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Friday, August 24

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction August 18 – 24

Backstage Construction Schedule – August 13 – August 17

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for August 11 – August 17, 2012

Updated August 13, 2012

PLEASE NOTE:

  • The Esplanade reopened on August 13th to Eastbound vehicles between Yonge Street and Scott Street and pedestrians Eastbound and Westbound between Yonge Street and Scott Street.

Monday, August 13

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Tuesday, August 14

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Wednesday, August 15

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Thursday, August 16

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Friday, August 17

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction August 11 -17

Backstage Construction Schedule – August 4 – August 10

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for August 4 – August 10, 2012

Updated August 3, 2012

  • The 30 day road closure of The Esplanade from Scott Street to Yonge Street remains in effect.

Monday, August 6 – Civic Holiday

Tuesday, August 7

  • Sub-contractor, C & M McNally boring the tunnel.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Wednesday, August 8

  • Sub-contractor, C & M McNally boring the tunnel.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Thursday, August 9

  • C & M McNally removing Tunnel Boring Machine
  • There will be significant impact to The Esplanade and surrounding streets due to the setup of a 500 ton crane, support semis and 130 foot long float to take away the Tunnel Boring Machine. There will be a police escort for the float as it leaves the site.

Friday, August 10

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: Construction Summary August 4 – August 10

Backstage Construction Schedule – July 30 – August 3

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for July 30 – August 3, 2012

Updated July 31, 2012

  • The 30 day road closure of The Esplanade from Scott Street to Yonge Street remains in effect.

Monday, July 30

  • Sub-contractor, C & M McNally boring the tunnel.
  • The tunnel connects the P4 parking level on the Backstage site at 1 The Esplanade with the L Tower. All L Tower residents will use this private tunnel to access their parking spaces which will be located underneath the future Backstage condominium.  
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Tuesday, July 31

  • Sub-contractor, C & M McNally boring the tunnel.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Wednesday, August 1

  • Sub-contractor, C & M McNally boring the tunnel.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Thursday, August 2 

  • Sub-contractor, C & M McNally boring the tunnel.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Friday, August 3

  • Sub-contractor, C & M McNally boring the tunnel.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

NOTES: 

RESCHEDULED to August 9: Sub-contractor, C & M McNally will be removing the Tunnel Boring Machine from the site with a 500-ton crane.

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: Construction Summary July 30 – August 3

Backstage Construction Schedule – July 21 – 27

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for July 21 – 27, 2012

Revised July 26, 2012

Saturday, July 21

  • Site preparation work for the tunnel boring may continue today depending on contractor availability. 

Monday, July 23

  • Mobile crane delivery and supporting equipment will be delivered to the site and installed commencing after 9:00 am 
  • Continuing key slot digging and preparation work in advance of the tunnel boring will continue on site.

Tuesday, July 24

  • Continuing key slot digging and preparation work in advance of the tunnel boring will continue on site.
  •  GFL Excavating will haul excavate from the site as required.

Wednesday, July 25

  • The float arrives with the tunnel boring machine under police escort. It is expected to arrive on site late morning or midday depending on traffic conditions through the city.
  • Placing the tunnel boring machine into operational position, site set-up and related work will occupy most of the day.

Thursday, July 26 – REVISED

  • Delayed by Wednesday night rain storm: Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 12 -13 loads each, for a total of seventy-two to seventy-four (72 – 74) loads.
  • Tunnel boring delayed by rain storm. Pumping out water from the site. 

Friday, July 27 – REVISED

  • Tunnel Boring Machine testing.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 12 -13 loads each, for a total of seventy-two to seventy-four (72 – 74) loads.

NOTES: 

Construction activities are dependent on whether and delivery times and frequencies are dependent on road and traffic conditions.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction July 21-27


Backstage Construction Schedule – July 3 – 6

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for July 3 – 6, 2012

Updated July 2, 2012

NOTE: With 6 trucks doing 10 loads each this week there will be a greater amount of truck traffic to and from the site. Please be prepared for short-terms traffic delays as the trucks move in and out of the 1 The Esplanade gate.

For photos illustrating the current forms of work at the Backstage site please click here.

Tuesday, July 3

  • Subcontractor, GFL Excavating will be removing material from the site: three (6) dump trucks will take 10 loads each, for a total of sixty (60) loads.

Wednesday, July 4

  • Subcontractor, GFL Excavating will be removing material from the site: three (6) dump trucks will take 10 loads each, for a total of sixty (60) loads.

Thursday, July 5

  • Subcontractor, GFL Excavating will be removing material from the site: three (6) dump trucks will take 10 loads each, for a total of sixty (60) loads..

Friday, July 6

  • Subcontractor, GFL Excavating will be removing material from the site: three (6) dump trucks will take 10 loads each, for a total of sixty (60) loads.

* * *

NOTES:

Paid Duty Police Officer is on-site daily Tuesday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage July 3 – 6 summary highlights: L Tower & Backstage Construction July 3-6

Backstage – Excavation East & West views

Backstage at, 1 The Esplanade, excavation looking east, June 29, 2012

 

Backstage, at 1 The Esplanade, excavation looking west, June 29, 2012

Backstage Construction Schedule – June 25 – 29

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for June 25 – 29, 2012

Posted June 22, 2012

NOTE: For photos illustrating the current forms of work at the Backstage site please click here.

Monday, June 25

  • Subcontractor, GFL Excavating will be removing material from the site: three (3) dump trucks will take 10 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

Tuesday, June 26

  • Subcontractor, GFL Excavating will be removing material from the site: three (3) dump trucks will take 10 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

Wednesday, June 27

  • Subcontractor, GFL Excavating will be removing material from the site: three (3) dump trucks will take 10 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

Thursday, June 28

  • Subcontractor, GFL Excavating will be removing material from the site: three (3) dump trucks will take 10 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

Friday, June 29

  • Subcontractor, GFL Excavating will be removing material from the site: three (3) dump trucks will take 10 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

* * *

NOTES:

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage June 25 – 29 summary highlights: L Tower & Backstage Construction June 25-29

Backstage Construction Schedule – June 18 – 22

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for June 18 – 22, 2012

Posted June 15, 2012

NOTE: For photos illustrating the current forms of work at the Backstage site please click here.

Monday, June 18

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs. 

Tuesday, June 19

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

Wednesday, June 20

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs. 

Thursday, June 21

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

Friday, June 22

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

* * *

NOTES:

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage June 18 – 22 summary highlights: L Tower & Backstage Construction June 18-22

Backstage Construction Schedule – June 11 – 15

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for June 11 – 15, 2012

Posted June 8, 2012

NOTE: For photos illustrating the current forms of work at the Backstage site please click here.

Monday, June 11

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs. 

Tuesday, June 12

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

Wednesday, June 13

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs. 

Thursday, June 14

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

Friday, June 15

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

* * *

NOTES:

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage June 11 – 15 summary highlights: L Tower & Backstage Construction June 11-15