Backstage Construction Schedule – March 10 – 14, 2014

UPDATED March 14 – This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  March 10 – 14, 2014.

Please click here for general information on concrete pours.

First floor Backstage Condo, 1 The Esplanade

First floor Backstage Condo, 1 The Esplanade

 MondayMarch 10

  • Fourth floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
  • Concrete Finishing to 10:00 pm.

 Tuesday, March 11

  • Rebar (steel) delivery starting at 7:00 am.
  • Crash Wall concrete pour, scheduled to begin at 9:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin once the Crash Wall pour is completed and should be finished by or before 7:00 pm.

Wednesday, March 12

  • Elevator parts delivery starting at 7:00 am.
  • CANCELLED  – 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin at 12:30 pm and should be completed before 7:00 pm.

Thursday, March 13

  • CANCELLED
    • Fourth floor slab concrete pour #4, by subcontractor Italform, scheduled to begin at 10:00 am.
    • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
    • Concrete Finishing to 10:00 pm.

Friday, March 14

  • Rebar (steel) delivery starting at 7:00 am.

CONCRETE POUR CANCELLED & RESCHEDULED TO SATURDAY MARCH 15 – 9:00 AM.

  • Fourth floor slab concrete pour #4, by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
  • Concrete Finishing to 10:00 pm.
  • RESCHEDULED – Crash Wall concrete pour, scheduled to begin at 9:00 am.
  • RESCHEDULED – 50 cubic metre, wall and column concrete pour by subcontractor Italform. The pour is scheduled to begin once the Crash Wall pour is completed and should be finished by or before 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.


Backstage Construction Update – October 2 – 4

This is a construction update for 1 The Esplanade – L Tower parking and Backstage condominium for  October 2 – 4, 2013

Please click here for general information on concrete pours.

Posted October 1

Wednesday, October 2

  • A small ground floor slab concrete pour, by subcontractor Italform. The pour is scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.
  • Concrete finishing, scheduled to proceed until 8 PM.

Thursday, October 3

  • Elevator equipment delivery at 7:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Friday, October 4

  • There will be a rebar delivery at 7:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary SEP 28-Oct 4-2013

Backstage Construction Schedule – September 28 – October 4

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  September 28 – October 4, 2013

Please click here for general information on concrete pours.

Updated October 1

Saturday, September 28

  • Plumbing work on site at Parking Level 5.

Monday, September 30

  • Elevator equipment delivery at 7:00 am.
  • Pouring ground floor slab pour #7, part1, by subcontractor Italform. The pour is scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.
  • Concrete finishing, scheduled to proceed until 10 PM.

Tuesday, October 1

  • Elevator equipment delivery at 7:00 am.
  • Pouring ground floor slab pour #7, part1, by subcontractor Italform. The pour is scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.
  • Concrete finishing, scheduled to proceed until 10 PM.

Wednesday, October 2

  • A small ground floor slab concrete pour, by subcontractor Italform. The pour is scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.
  • Concrete finishing, scheduled to proceed until 8 PM.

Thursday, October 3

  • Elevator equipment delivery at 7:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

Friday, October 4

  • There will be a rebar delivery at 7:00 am.
  • 50 cubic metre, wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 7:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Please click on the link to download a construction summary: Backstage & L Tower Construction Summary SEP 28-Oct 4-2013

L Tower Construction Schedule October 6 – 12

This is the current construction schedule for 8 The Esplanade – L Tower – for October 6 – 12, 2012

Posted October 5, 2012

The L Tower Celebrates it’s topping-off on Wednesday. 

Saturday, October 6

  • Washroom Servicing 9:00 am to Noon.

Sunday, October 7

  • Aerobatic ballet rehearsal on the north face of the L Tower. No construction noise will be created by this activity.

Monday, October 8 – THANKSGIVING DAY

  • Aerobatic ballet rehearsal on the north face of the L Tower. No construction noise will be created by this activity. 

Tuesday, October 9

  • Delivery of elevator equipment from the Yonge Street gate. 
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.

Wednesday, October 10

  • L Tower Topping-Off Ceremony at 1:00 pm. 

Thursday, October 11

  • Hoist lift – three (3) floors.

Friday, October 12

  • TBD – please check back for updates. 

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.