Backstage Construction Schedule – February 2 – 8

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  February 2 – 8, 2013

The site at 1 The Esplanade showing the retaining wall and the depth of the dig.

The site at 1 The Esplanade showing the retaining wall and the depth of the dig.

Updated February 4, 2013

Saturday, February 2

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator.
  • There will be 5 dump trucks taking 10 loads of material each, for an estimated  total of 50 loads.

Monday, February 4

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator.
  • There will be 5 dump trucks taking 14 loads of material each, for an estimated  total of  70 loads.

Tuesday, February 5

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator.
  • There will be 5 dump trucks taking 14 loads of material each, for an estimated  total of  70 loads.

Wednesday, February 6

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator.
  • There will be 3 to 5 dump trucks taking 14 loads of material each, for an estimated total of 42 to 70 loads.

Thursday, February 7

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator.
  • There will be 3 to 5 dump trucks taking 14 loads of material each, for an estimated total of 42 to 70 loads.

Friday, February 8 

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator.
  • There will be 3 to 5 dump trucks taking 14 loads of material each, for an estimated total of 42 to 70 loads.

NOTES:Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control

Please click here for a downloadable construction summary: Update – L Tower & Backstage Construction Summary Feb 5 – 8

Backstage Construction Schedule – January 28 – February 1

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  January 28 – February 1, 2013

Posted January 25, 2013

Monday, January 28

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator.
  • There will be 4 dump trucks taking 14 loads of material each, for an estimated  total of 56 loads

Tuesday, January 29

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator.
  • There will be 4 dump trucks taking 14 loads of material each, for an estimated  total of 56 loads

Wednesday, January 30

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator.
  • There will be 4 dump trucks taking 14 loads of material each, for an estimated  total of 56 loads

Thursday, January 31

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator.
  • There will be 4 dump trucks taking 14 loads of material each, for an estimated  total of 56 loads

Friday, February 1 

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator.
  • There will be 4 dump trucks taking 14 loads of material each, for an estimated  total of 56 loads

NOTES:Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control

Please click here for a downloadable construction summary: L Tower & Backstage Construction Jan 28 – Feb 1

Backstage Construction Schedule – January 21 – 25

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  January 21 – 25, 2013

Posted January 18, 2013

Monday, January 21 – Crane installation – Vehicular Road Closure

  • Italforming will be erecting tower crane today: The Esplanade will closed to vehicular traffic per hoisting permit 58988001 as approved by City of Toronto.
  • Pedestrian access through the site will remain open.
  • Please note: The will be significant construction traffic to the site: one 300 ton mobile crane and two support trucks and nine semi-trailer trucks bring in the tower crane and related components throughout the day.

Tuesday, January 22

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator, 5 dump trucks 14 loads each, for an estimated  total of 70 loads.

Wednesday, January 23

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator, 5 dump trucks 14 loads each, for an estimated  total of 70 loads.

Thursday, January 24

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator, 5 dump trucks 14 loads each, for an estimated  total of 70 loads.

Friday, January 25 

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator, 5 dump trucks 14 loads each, for an estimated  total of 70 loads.

NOTES:Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control

Please click here for a downloadable construction summary: L Tower & Backstage Construction Summary Jan 21 – 25

Backstage Construction Schedule – December 17 – December 21

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for December 17 – December 21, 2012

Updated December 17, 2012

Monday, December 17

  • GFL Excavating will be setting up long reach and will be removing material from the site: six (6) dump trucks will take fourteen (14) loads each, for a total of eighty-four (84) loads. **
  • OJCR will be tying in water lines on the Esplanade.

Tuesday, December 18

  • GFL Excavating will not be removing material. They will be operating the hydraulic breaker and preparing material, this will cause significant noise during construction hours.
  • OJCR will be tying in water lines on the Esplanade.

Wednesday, December 19

  • GFL Excavating will not be removing material. They will be operating the hydraulic breaker and preparing material.
  • OJCR will be tying in water lines on the Esplanade.

Thursday, December 20

  • GFL Excavating will be using the long reach and will be removing material from the site: six (6) dump trucks will take fourteen (14) loads each, for a total of eighty-four (84) loads. **

Friday, December 21

  • GFL Excavating will be using the long reach and will be removing material from the site: six (6) dump trucks will take fourteen (14) loads each, for a total of eighty-four (84) loads. **

NOTES: 

** Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Continuing Sanitary Sewer & Water Main work on The Esplanade 

City of Toronto contractor — OJCR Construction — continues water main work on The Esplanade between Yonge Street and Scott Street. 

  1. Pedestrian traffic will remain open. 
  2. Eastbound Vehicular Traffic may be closed during work hours. 
  3. We have advised the City of complaints we have received in respect to their work. 

If you have further questions please contact: 

Joseph Sinopoli
Toronto Water
416-338-6526 Office

Paid Duty Police Officer is on-site  daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction December 17 – December 21

Backstage Construction Schedule – December 8 – December 14

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for December 8 – December 14, 2012

Posted December 7, 2012

Saturday, December 8

  • GFL Excavating will be assembling the long reach backhoe.

Monday, December 10

  • GFL Excavating will be operating machinery in the hole moving material in preparation for the long reach.
  • OJCR will be working on Yonge Street due to the L Tower concrete pour.

Tuesday, December 11

  • GFL Excavating will be operating machinery in the hole moving material in preparation for the long reach.
  • OJCR will be working on service connection on the Esplanade.

Wednesday, December 12

  • GFL Excavating will be setting up long reach and will be removing material from the site: six (6) dump trucks will take fourteen (14) loads each, for a total of eighty-four (84) loads.
  • OJCR will be tying in water lines on the Esplanade.

Thursday, December 13

  • GFL Excavating will be using the long reach and will be removing material from the site: six (6) dump trucks will take fourteen (14) loads each, for a total of eighty-four (84) loads.
  • OJCR will be tying in water lines on the Esplanade.

Friday, December 14

  • GFL Excavating will be using the long reach and will be removing material from the site: six (6) dump trucks will take fourteen (14) loads each, for a total of eighty-four (84) loads.
  • OJCR will be working on Yonge Street connecting the storm drain.

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site  daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction December 8 – December 14

Backstage Construction Schedule – December 3 – December 7

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for December 3 – December 7, 2012

Updated December 4, 2012

Monday, December 3 

  •  CANCELED GFL Excavating will be assembling the long reach backhoe and will be operating machinery in the hole moving material in preparation for the long reach. 
  • OJCR will be working on service connection on the Esplanade.

Tuesday, December 4

  •  CANCELED GFL Excavating will be assembling the long reach backhoe and will be operating machinery in the hole moving material in preparation for the long reach. 
  • OJCR will be working on service connection on the Esplanade.

Wednesday, December 5

  • The Long Reach back-hoe will be delivered to the site midday under police escort
  • OJCR will be tying in water lines on the Esplanade.

Thursday, December 6

  • GFL Excavating will be assembling the long reach backhoe and will be operating machinery in the hole moving material in preparation for the long reach.
  • OJCR will be tying in water lines on the Esplanade.

Friday, December 7

  • GFL Excavating will be assembling the long reach backhoe and will be operating machinery in the hole moving material in preparation for the long reach. 
  • OJCR will be tying in water lines on the Esplanade.

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site  daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction December 3 – December 7

Backstage Construction Schedule – October 22 – 26

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for October 22 – 26, 2012

Updated October 24, 2012

Please note efforts are being made to ensure pedestrian safety as dump trucks access the site. Traffic control staff are on site and safety cones will be placed on the sidewalk and roadway to indicate the pedestrian route through the work zone. Starting November 9, a new alignment of the vehicular and pedestrian routes will be put in place, providing enhanced safety. More information will be provided next week. 

Monday, October 22 

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take fourteen (14) loads each, for a total of eighty-four (84) loads. The last dump truck loads are scheduled between 2:00 pm and 2:30 pm.
  • Subcontractor, GFL Excavating will be breaking shale with hydraulic breaker from approximately 2:30 pm until no later than 7:00 pm.

Tuesday, October 23

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take fourteen (14) loads each, for a total of eighty-four (84) loads. The last dump truck loads are scheduled between 2:00 pm and 2:30 pm.
  • Subcontractor, GFL Excavating will be breaking shale with hydraulic breaker from approximately 2:30 pm until no later than 7:00 pm.

Wednesday, October 24

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take fourteen (14) loads each, for a total of eighty-four (84) loads. The last dump truck loads are scheduled between 2:00 pm and 2:30 pm.
  • Subcontractor, GFL Excavating will be breaking shale with hydraulic breaker from approximately 2:30 pm until no later than 7:00 pm.

Thursday, October 25

  • Subcontractor, GFL Excavating will be breaking shale with hydraulic breaker from all day between 7:00 am and 7:00 pm.

Friday, October 26

  • Subcontractor, GFL Excavating will be breaking shale with hydraulic breaker from all day between 7:00 am and 7:00 pm.

 

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: 

Backstage Construction Schedule – October 15 – 19

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for October 15 – 19, 2012

Posted October 12, 2012

Monday, October 15 

  • Subcontractor, GFL Excavating will be breaking shale with hydraulic breaker all day, until no later than 7:00 pm.

Tuesday, October 16 

  • Subcontractor, GFL Excavating will be breaking shale with hydraulic breaker all day, until no later than 7:00 pm.

Wednesday, October 17

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. The last dump truck loads are scheduled between 2:00 pm and 2:30 pm.
  • Subcontractor, GFL Excavating will be breaking shale with hydraulic breaker from approximately 2:30 pm until no later than 7:00 pm.

Thursday, October 18

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. The last dump truck loads are scheduled between 2:00 pm and 2:30 pm.
  • Subcontractor, GFL Excavating will be breaking shale with hydraulic breaker from approximately 2:30 pm until no later than 7:00 pm

Friday, October 19

  • Subcontractor, GFL Excavating will be removing material from the site: six(6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. The last dump truck loads are scheduled between 2:00 pm and 2:30 pm.
  • Subcontractor, GFL Excavating will be breaking shale with hydraulic breaker from approximately 2:30 pm until no later than 7:00 pm.

 

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction October 13-19

Backstage Construction Schedule – October 9 – 12

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for October 9 – 12, 2012

Posted October 5, 2012

Monday, October 8 – THANKSGIVING DAY

Tuesday, October 9 

  • Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Wednesday, October 10

  • Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Thursday, October 11

  • Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Friday, October 12

  • Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction October 6-12

Backstage Construction Schedule – October 1 – 5

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for October 1 – 5, 2012

Posted September 28, 2012

Monday, October 1 

  • Hydraulic breaking of the shale.
  • Tentative – Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Tuesday, October 2 

  • Hydraulic breaking of the shale.
  • Subcontractor C&M McNally pouring concrete. Please note: that there here may be short-term disruptions to pedestrian and vehicular traffic.
  • Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Wednesday, October 3

  • Hydraulic breaking of the shale.
  • Subcontractor C&M McNally pouring concrete. Please note: that there here may be short-term disruptions to pedestrian and vehicular traffic.
  • Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Thursday, October 4

  • Hydraulic breaking of the shale.
  • Subcontractor C&M McNally pouring concrete. Please note: that there here may be short-term disruptions to pedestrian and vehicular traffic.
  • Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Friday, October 5

  • Hydraulic breaking of the shale.
  • Subcontractor, GFL Excavating will be removing material from the site: four (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower – Backstage Construction Sept 29 – Oct 5