L Tower Construction Schedule February 9 – 15

This is the current construction schedule for 8 The Esplanade – L Tower –  February 9 – 15, 2013

Posted February 8, 2012

SaturdayFebruary 9

  • Hoist maintenance to begin after 9:00 am and continue through till Noon.

MondayFebruary 11

  • A delivery of drywall starting at 7:00 am.

Tuesday, February 12

  • A 9M (cubic metre) column concrete pour, at levels 61 – 62, starting 1:00 pm, scheduled to to finish prior to 7:00 pm.

Wednesday, February 13

  • A 9M (cubic metre) column concrete pour, at levels 61 – 62, starting 1:00 pm, scheduled to to finish prior to 7:00 pm.

Thursday, February 14

  • A 9M (cubic metre) column concrete pour, at levels 61 – 62, starting 1:00 pm, scheduled to to finish prior to 7:00 pm.

Friday, February 15

  • A 100M (cubic metre) slab concrete pour, at level 62, starting 1:00 pm, scheduled to to finish prior to 7:00 pm..

Please note:

  • There may be some short-term disruptions to vehicular traffic while delivery trucks are moved into position and unloaded.
  • Concrete trucks must continue to operate with their engines on while concrete is being poured.
  • A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction – Feb 9-15

L Tower Construction Schedule November 24 – 30

This is the current construction schedule for 8 The Esplanade – L Tower – for  November 24 – 30, 2012

Updated  November 23, 2012

Saturday, November 24

  • Four containers of windows with delivery starting at 9:00 am and continuing to 4:00 pm.

Monday, November 26

  • A 1 cubic metre concrete pour at 9:00 am, levels 61 – 62, expected to finish prior to 7:00 pm.
  • A rebar (steel) delivery starting at 7:00 am.
  • Two containers of windows with delivery starting at 12:00 pm and continuing to 4:00 pm.
  • A delivery of window frames with delivery starting 1:00 pm and continuing to 2:00 pm.

Tuesday, November 27

  • A rebar (steel) delivery starting at 12:30 pm.

Wednesday, November 28

  • No activity is scheduled at this time.

Thursday, November 29

  • A rebar (steel) delivery starting at 7:00 am.

Friday, November 30

  • A rebar (steel) delivery starting at 7:00 am.

Please note:

There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

 

Please click here for a downloadable construction summary: L Tower & Backstage Construction November 26 – 30


L Tower Construction Schedule November 19 – 23

This is the current construction schedule for 8 The Esplanade – L Tower – for  November 19 – 23, 2012

Updated  November 20, 2012

Monday, November 19

  • Drywall delivery starting at 7:00 am.
  • A rebar (steel) delivery starting at 7:00 am.

Tuesday, November 20

  • A rebar (steel) delivery starting at 7:00 am.
  • Miscellaneous construction activities throughout the day.

Wednesday, November 21

  • Drywall delivery starting at 7:00 am.
  • One container of windows with delivery starting at 7:30 am.
  • Miscellaneous construction activities throughout the day.

Thursday, November 22

  • A rebar (steel) delivery starting at 7:00 am..
  • Electrical materials delivery starting at 8:00 am.
  • Three containers of windows with delivery starting at 10:00 am.

Friday, November 23

  • A delivery of duct work delivery starting at 7:00 am.
  • Electrical materials delivery starting at 8:00 am.
  • A rebar (steel) delivery starting at 12:30 pm.

Please note:

There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction November 19 – 23