Drilling and “breaking” for Backstage

These pictures show site work today–1/9/12–at 1 The Esplanade, preparing the way for the Backstage Condominium from Castlepoint, Cityzen and Fernbrook Homes. The site will also house the underground parking for the adjacent L Tower. The work this week is focused on drilling caissons and “breaking” parts of the railway bridge structure that will be replaced by the Backstage podium. During construction work there are also some temporary holds on eastbound traffic but with every effort made to minimize delays.

Between Backstage and L Tower, temporarily holding traffic on The Esplanade, 1/9/12

"Breaking" a section of railway bridge with a pneumatic hammer, 1 The Esplanade, 1/9/12

Drilling at the Backstage construction site, 1 The Esplanade, 1/9/12

Backstage construction site looking west, 1 The Esplanade, 1/9/12

A "found" metal "flower" at the Backstage construction site, 1 The Esplanade, 1/9/12

Backstage construction site, looking east, 1 The Esplanade, 1/9/12

1 The Esplanade – Construction Schedule Jan 9 – 13, 2012

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for January 9 – 13, 2012

Posted January 6, 2012

Monday, January 9

  • Steel pile delivery at 7:00 am.
  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete into the site.
  • Sub-contractor, GFL delivering an excavator.

Tuesday, January 10

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete into the site.
  • Sub-contractor, GFL breaking the bridge retaining wall.

Wednesday, January 11

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete into the site.
  • Sub-contractor, GFL breaking the bridge retaining wall.

Thursday, January 12

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete into the site.
  • Sub-contractor, GFL breaking the bridge retaining wall.

Friday, January 13

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete into the site.
  • Sub-contractor, GFL breaking the bridge retaining wall.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

1 The Esplanade – Construction Schedule December 12 – 16

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for the week of December 12 – 16, 2011

Posted December 9, 2011

Monday, December 12

  • Sub-contractor Deep Foundation will be installing tie backs.
  • Sub-contractor GFL Excavating removing bulk. 5 dump trucks 5 rounds each.

Tuesday, December 13

  • Sub-contractor Deep Foundation will be installing tie backs.
  • Sub-contractor GFL Excavating removing bulk. 5 dump trucks 5 rounds each.

Wednesday, December 14

  • Sub-contractor Deep Foundation will be installing tie backs.
  • Sub-contractor GFL Excavating removing bulk. 5 dump trucks 5 rounds each.

Thursday, December 15

  • Sub-contractor Deep Foundation will be installing tie backs.
  • Deep Foundation delivering drill rig with police escort.
  • Sub-contractor GFL Excavating removing bulk. 5 dump trucks 5 rounds each.

Friday, December 16

  • Sub-contractor Deep Foundation will be installing tie backs.
  • Deep Foundations drilling piles and caissons. 5 concrete truckloads.
  • Sub-contractor GFL Excavating removing bulk. 5 dump trucks 5 rounds each.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Construction Schedule October 3 – 7

This is the current construction schedule for 8 The Esplanade – L Tower and 1 The Esplanade – L Tower Parking + Backstage for the week of October 3 – 7, 2011

 

Posted: September 30, 2011

 

Monday, October 3

 

8 The Esplanade – L Tower

  • There will be a 180M concrete pour, which may go beyond 7:00 pm.

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Tuesday, October 4

 

8 The Esplanade – L Tower

  • There will be a 90M concrete pour, which may go beyond 7:00 pm.

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Wednesday, October 5

 

8 The Esplanade – L Tower

  • There will be a 90M concrete pour, which may go beyond 7:00 pm.

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Thursday, October 6

 

8 The Esplanade – L Tower

  • There will be a 72M concrete pour, which may go beyond 7:00 pm.

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be dismantling the drill rig on site.

Friday, October 7

 

8 The Esplanade – L Tower
  • No concrete scheduled.

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be dismantling the crane on site.
NOTE 1: Several daily deliveries throughout the week with little or no impact on traffic.
NOTE 2. A Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm Monday through Friday. A security guard on site from 4:00 pm – 6:00 am daily.

Construction Schedule September 26 – October 1, 2011

This is the current construction schedule for 8 The Esplanade – L Tower and 1 The Esplanade – L Tower Parking + Backstage for the week of September 26 – October 1, 2011

Posted: September 30, 2011

Monday, September 26

8 The Esplanade – L Tower

  • There will be a 72M concrete pour, which may go beyond 7:00 pm.

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete accessing The Esplanade.

Tuesday, September 27

8 The Esplanade – L Tower

  • There will be a 100M concrete pour, which may go beyond 7:00 pm.

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete accessing The Esplanade.

Wednesday, September 28

8 The Esplanade – L Tower

  • There will be a 72M concrete pour, which may go beyond 7:00 pm.

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Thursday, September 29

8 The Esplanade – L Tower

  • No concrete scheduled.

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.
Friday, September 30
8 The Esplanade – L Tower
  • No concrete scheduled.

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.
  • Sub-Contractor Deep Foundation has scheduled an 85-foot steel pile delivery at Noon. 

Saturday, October 1

8 The Esplanade – L Tower

  • Dominus site labour in 9:00 am – 1:00 pm to perform housekeeping duties.
  • Sub-contractor, Premform will work from on the site from 9:00 am – 4:00 pm.

1 The Esplanade – L Tower Parking + Backstage

  • No construction activity is scheduled.
NOTE 1: Several daily deliveries throughout the week with little or no impact on traffic.
NOTE 2. A Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm Monday through Friday. A security guard on site from 4:00 pm – 6:00 am daily.

Construction Schedule – September 19 – 23, 2011

 

This is the current construction schedule for 8 The Esplanade – L Tower and 1 The Esplanade – L Tower Parking + Backstage for the week of September 19 – 23, 2011.

Posting Date: September 18, 2011

Monday, September 19

8 The Esplanade – L Tower

  • There will be a 72M concrete pour which is not expected to go past 7:00 pm

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete accessing The Esplanade.
  • Deep Foundation has schedule an 85 foot steel pile delivery for the afternoon at approximately  2:00 pm.
    • There will be some temporary impact on vehicular and pedestrian traffic in the area of Scott Street and The Esplanade.

Tuesday, September 20

8 The Esplanade – L Tower

  • There will be a 45M concrete pour which is not expected to go past 7:00 pm

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete accessing The Esplanade.

Wednesday, September 21

8 The Esplanade – L Tower

  • No concrete pour is scheduled as of posting date – September 18, 2011.

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.
  • GFL Excavating will be removing spoils from the site: 4 trucks taking 16 loads.

Thursday, September 22

8 The Esplanade – L Tower

  • No concrete pour is scheduled as of posting date – September 18, 2011.

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.
  • GFL Excavating will be removing spoils from the site: 4 trucks taking 16 loads.

Friday, September 23

8 The Esplanade – L Tower

  • No concrete pour is scheduled as of posting date – September 18, 2011.

1 The Esplanade – L Tower Parking + Backstage

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

NOTE 1: Several daily deliveries throughout the week with little or no impact on traffic.
NOTE 2. A Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm Monday through Friday. A security guard on site from 4:00 pm – 6:00 am daily.

Caisson Drilling at 1 The Esplanade

Drilling at 1 The Esplanade

image

Drill at work on The Embankment - 1 The Esplanade

image

Steel piles wating to be placed into the caissons

image

Steel and drill. 1 The Esplanade.

image

Casisson drilling.

image

Crane & Sky. 25 The Esplanade in the background.

image

Drill at 1 The Esplanade seen from Platform 1 Union Station.

Active construction photographs at 1 The Esplanade, site of the Backstage Condominium and the L Tower’s underground parking, from the week of August 22.

Construction Schedule August 15 – 19

This is the current construction schedule for 8 The Esplanade – L Tower and 1 The Esplanade – L Tower Parking + Backstage for the week of August 15 through August 19, 2011.

Post Date – August 16/11

Monday, August 15

8 The Esplanade – L Tower 

  • There will be a 45M concrete pour, which is not expected to beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Tuesday, August 16

8 The Esplanade – L Tower 

  • There will be a 72M concrete pour, which is not expected to beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Wednesday, August 17

8 The Esplanade – L Tower 

  • There will be a 72M concrete pour, which is not expected to beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Thursday, August 18

8 The Esplanade – L Tower 

  • No concrete is scheduled as of August 12.
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Friday, August 19

8 The Esplanade – L Tower 

  • No concrete is scheduled as of August 12.
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.
NOTE: A Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm Monday through Friday; and this week  Tuesday through Friday.

Construction Schedule August 8 – 12

This is the current construction schedule for 8 The Esplanade – L Tower and 1 The Esplanade – L Tower Parking + Backstage for the week of August 8 through August 12, 2011.

Updated August 5, 2011

Monday, August 8

8 The Esplanade – L Tower 

  • There will be a 120M concrete pour which may go beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • GFL Excavating will be drilling spoils most of the day: Dump trucks will be in and out at The Esplanade gate, just west of Scott Street.
    • There will be a significant impact on eastbound vehicular traffic.
    • There will be a significant impact on eastbound and westbound pedestrian traffic.

Tuesday, August 9

8 The Esplanade – L Tower 

  • There will be a 72M concrete pour starting at 1 pm, which is not expected to beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 5 loads of concrete delivered throughout the day.
  • There will be a large steel delivery: Deep Foundation, has scheduled an oversized delivery of steel piles 85 feet long in the afternoon. The load will come to The Esplanade gate.
    • There will be some impact on eastbound vehicular traffic.
    • There will be some significant impact on eastbound and westbound pedestrian traffic.

Wednesday, August 10

8 The Esplanade – L Tower 

  • There will be a 72M concrete pour starting at 1 pm, which is not expected to beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Thursday, August 11

8 The Esplanade – L Tower 

  • No concrete is scheduled as of August 5.
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Friday, August 12

8 The Esplanade – L Tower 

  • There will be a 185M concrete pour which may go beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.
NOTE: A Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm Monday through Friday; and this week  Tuesday through Friday.

Construction Schedule – August 2 – 6

This is the current construction schedule for 8 The Esplanade – L Tower and 1 The Esplanade – L Tower Parking + Backstage for the week of August 2 through August 6, 2011.

Updated August 2, 2011

t

Tuesday, August 2

8 The Esplanade – L Tower 

  • There will be a 180M concrete pour which may go beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons.
  • Concrete truck deliveries are scheduled throughout the day.

Wednesday, August 3

8 The Esplanade – L Tower 

  • There will be a 72M concrete pour which is not expected to beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons.
  • Concrete truck deliveries are scheduled throughout the day.
  • There will be a large steel delivery: Deep Foundation, has scheduled an oversized delivery of steel piles 85 feet long. The load will come to The Esplanade gate.
    • Because it is an oversized load the truck delivering it will leave Deep Foundation’s yard at approximately 9:00 am under police escort and make its way to the site via Jarvis St, west across The Esplanade toward Yonge Street.
    • Unfortunately, during delivery there will be a significant impact on vehicular and pedestrian traffic in the vicinity of 1 The Esplanade. This is expected to occur between approximately 10 am and 11 am.

Thursday, August 4

8 The Esplanade – L Tower 

  • There will be a 72M concrete pour which is not expected to beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons.
  • Concrete truck deliveries are scheduled throughout the day.

Friday, August 5

8 The Esplanade – L Tower 

  • There will be a 108M concrete pour which may go beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons.
  • Concrete truck deliveries are scheduled throughout the day.

Saturday, August 6

8 The Esplanade – L Tower 

  • There will be a Dominus labour crew in for housekeeping activities on the site between 9:00 am and 1:00 pm

 

NOTE: A Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm Monday through Friday; and this week  Tuesday through Friday.