Backstage Construction Schedule – April 16 – 20

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for April 16 – 20, 2012

Posted April 13, 2012

Monday, April 16

  • Subcontractor, Deep Foundation, will be installing tie backs and drilling piles and caissons.
    • There will be two (2) concrete trucks doing four rounds each (8 in total) in and out of the site.
  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 5 loads each, for a total of 20 loads.

Tuesday, April 17

  • Subcontractor, Deep Foundation, will be installing tie backs and drilling piles and caissons.
    • There will be two (2) concrete trucks doing four rounds each (8 in total) in and out of the site.
  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 5 loads each, for a total of 20 loads.

Wednesday, April 18

  • Subcontractor, Deep Foundation, will be installing tie backs and drilling piles and caissons.
    • There will be two (2) concrete trucks doing four rounds each (8 in total) in and out of the site.
  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 5 loads each, for a total of 20 loads.

Thursday, April 19

  • Subcontractor, Deep Foundation, will be installing tie backs and drilling piles and caissons.
    • There will be two (2) concrete trucks doing four rounds each (8 in total) in and out of the site.
  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 5 loads each, for a total of 20 loads.

Friday, April 20

  • Subcontractor, Deep Foundation, will be installing tie backs and drilling piles and caissons.
    • There will be two (2) concrete trucks doing four rounds each (8 in total) in and out of the site.
  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 5 loads each, for a total of 20 loads.

* * *

NOTES:

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 14 – 21 summary highlights: L Tower & Backstage Construction Summary Highlights April 14-21

1 The Esplanade Construction Schedule November 7 – 9

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for the week of November 7 – 9, 2011

Posted November 5, 2011

For example images of this work please click here.

Monday, November 7

  • Sub-contractor GFL will be doing bulk excavating. There will be 15 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.

    • The trucks will enter from eastbound from Yonge Street, travel just west of the Esplanade gate toward Scott Street, then reverse  into the site to pick up the excavated bulk. The trucks will then pull out and exit east along The Esplanade.
    • There will be short-term impacts to vehicular and pedestrian traffic while the trucks are entering and departing the site.

Tuesday, November 8

  • Sub-contractor GFL will be doing bulk excavating. There will be 15 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.
    • The trucks will enter from eastbound from Yonge Street, travel just west of the Esplanade gate toward Scott Street, then reverse  into the site to pick up the excavated bulk. The trucks will then pull out and exit east along The Esplanade.
    • There will be short-term impacts to vehicular and pedestrian traffic while the trucks are entering and departing the site.

Wednesday, November 9

  • Sub-contractor GFL will be doing bulk excavating. There will be 15 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.
    • The trucks will enter from eastbound from Yonge Street, travel just west of the Esplanade gate toward Scott Street, then reverse into the site to pick up the excavated bulk. The trucks will then pull out and exit east along The Esplanade.
    • There will be short-term impacts to vehicular and pedestrian traffic while the trucks are entering and departing the site.
NOTES:
  • Bulk excavating should be complete at 1 The Esplanade on Wednesday, November 9.  
  • Following the excavation work, sub-contractor, Deep Foundation, will start the first row tie back installation. An update on will be provided once information is available.
  • Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm daily to assist with traffic control.

Construction Schedule for 1 The Esplanade October 24 – 28

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for the week of October 24 – 28, 2011

Posted October 24, 2011

Monday, October 24

  • No activity is scheduled for Monday at 1 The Esplanade.

Tuesday, October 25

  • Sub-contractor GFL will be removing bulk from the site. There will be 15 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street. 

Wednesday, October 26

  • Sub-contractor GFL will be removing bulk from the site. There will be 15 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.

Thursday, October 27

  • Sub-contractor GFL will be removing bulk from the site. There will be 15 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.
Friday, October 28
  • Sub-contractor GFL will be removing bulk from the site. There will be 15 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.
NOTES:
  • A Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm daily to assist with traffic control.

Updated: Construction Schedule September 5 – September 9

This is the current construction schedule for 8 The Esplanade – L Tower and 1 The Esplanade – L Tower Parking + Backstage for the week of September 5 through September 9, 2011.

Updated: 6 September 2011

Monday, September 5

8 The Esplanade – L Tower

  • No concrete is scheduled as of September 2.

1 The Esplanade – L Tower Parking + Backstage 

  • No work scheduled.

 Tuesday, September 6

8 The Esplanade – L Tower 

  • There will be a Steel Delivery at 7:00am.

1 The Esplanade – L Tower Parking + Backstage (Updated)

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.  There will be 10 loads of concrete accessing the site from The Esplanade.
  • GFL Excavating will be removing 16 loads of dirt.

Wednesday, September 7

8 The Esplanade – L Tower

  • There will be a 45M concrete pour starting at 1:00pm and it is not expected to go beyond 7:00pm.

1 The Esplanade – L Tower Parking + Backstage  (Updated)

  • There will be a steel pile delivery by a regular semi-tractor trailer.
  • Sub-contractor, Deep Foundation will be drilling caissons and piles.  There will be 10 loads of concrete accessing the site from The Esplanade.

Thursday, September 8

8 The Esplanade – L Tower 

  • There will be a steel delivery at 7:00am and 27M concrete pour starting at 1:00pm that is not expected to go beyond 7:00pm

1 The Esplanade – L Tower Parking + Backstage (Updated)

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.  There will be 10 loads of concrete accessing the site from The Esplanade.

Friday, September 9

8 The Esplanade – L Tower 

  • There will be a steel Delivery at 7:00am and 144M Concrete Pour starting at 11:00 that is not expected to go beyond 7:00pm.

1 The Esplanade – L Tower Parking + Backstage (Updated)

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.  There will be 10 loads of concrete accessing the site from The Esplanade.
NOTE 1:  Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm Monday through Friday.

Updated: Construction Schedule August 29 – September 2

This is the current construction schedule for 8 The Esplanade – L Tower and 1 The Esplanade – L Tower Parking + Backstage for the week of August 29 through September 2, 2011.

UPDATED: 30 August 2011

Monday, August 29

8 The Esplanade – L Tower 

  • No concrete is scheduled as of August 26.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete accessing The Esplanade.

 Tuesday, August 30

8 The Esplanade – L Tower 

  • There will be a 140M concrete pour beginning at 9AM

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete accessing The Esplanade.

Wednesday, August 31

8 The Esplanade – L Tower

  • There will be a steel delivery at 7:00am and 86M Concrete pour starting at 1:00pm which is not expected to go beyond 7:00pm.

1 The Esplanade – L Tower Parking + Backstage  (Updated)

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete accessing The Esplanade.
  • Update: Deep Foundations has an 85 foot long load of steel piles being delivered under police escort at 1:00 pm. The load will come down The Esplanade.

Thursday, September 1

8 The Esplanade – L Tower 

  • There will be a 86M concrete pour starting at 1:00pm which not expected to go beyond 7:00pm.

1 The Esplanade – L Tower Parking + Backstage (Updated)

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.
  • Update: GFL Excavating will be on site removing drilling spoils. There will be 4 dump trucks doing 4 rounds each for a total of 16 loads.

Friday, September 2

8 The Esplanade – L Tower 

  • There will be a 86M concrete pour starting at 1:00pm which not expected to go beyond 7:00pm.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.
NOTE 1:  Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm Monday through Friday.

Construction Schedule August 22 – 26

This is the current construction schedule for 8 The Esplanade – L Tower and 1 The Esplanade – L Tower Parking + Backstage for the week of August 22 through August 26, 2011.

r

Post Date – August 19/11

r

Monday, August 22

8 The Esplanade – L Tower 

  • There will be a 72M concrete pour, which is not expected to beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day
  • GFL Excavating will be removing dirt from the site. There will be 24 loads taken out via The Esplanade gate.

Tuesday, August 23

8 The Esplanade – L Tower 

  • There will be a 72M concrete pour, which is not expected to beyond 7:00 pm
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day
  • GFL Excavating will be removing dirt from the site. There will be 24 loads taken out via The Esplanade gate.

Wednesday, August 24

8 The Esplanade – L Tower

  • No concrete is scheduled as of August 19.
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Thursday, August 25

8 The Esplanade – L Tower 

  • No concrete is scheduled as of August 19.
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.

Friday, August 26

8 The Esplanade – L Tower 

  • No concrete is scheduled as of August 19.
  • Several deliveries to site are scheduled throughout the day. These should have little or no impact on traffic.

1 The Esplanade – L Tower Parking + Backstage 

  • Sub-contractor, Deep Foundation will be drilling caissons and piles.
  • There will be 10 loads of concrete delivered throughout the day.
NOTE 1: During the week there will be a delivery of steel piles to the site at 1 The Esplanade. An update on precise times will be posted when the information is available.
NOTE 2: A Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm Monday through Friday; and this week  Tuesday through Friday.