Backstage Construction Schedule – July 3 – 6

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for July 3 – 6, 2012

Updated July 2, 2012

NOTE: With 6 trucks doing 10 loads each this week there will be a greater amount of truck traffic to and from the site. Please be prepared for short-terms traffic delays as the trucks move in and out of the 1 The Esplanade gate.

For photos illustrating the current forms of work at the Backstage site please click here.

Tuesday, July 3

  • Subcontractor, GFL Excavating will be removing material from the site: three (6) dump trucks will take 10 loads each, for a total of sixty (60) loads.

Wednesday, July 4

  • Subcontractor, GFL Excavating will be removing material from the site: three (6) dump trucks will take 10 loads each, for a total of sixty (60) loads.

Thursday, July 5

  • Subcontractor, GFL Excavating will be removing material from the site: three (6) dump trucks will take 10 loads each, for a total of sixty (60) loads..

Friday, July 6

  • Subcontractor, GFL Excavating will be removing material from the site: three (6) dump trucks will take 10 loads each, for a total of sixty (60) loads.

* * *

NOTES:

Paid Duty Police Officer is on-site daily Tuesday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage July 3 – 6 summary highlights: L Tower & Backstage Construction July 3-6

Backstage Construction Schedule – June 25 – 29

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for June 25 – 29, 2012

Posted June 22, 2012

NOTE: For photos illustrating the current forms of work at the Backstage site please click here.

Monday, June 25

  • Subcontractor, GFL Excavating will be removing material from the site: three (3) dump trucks will take 10 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

Tuesday, June 26

  • Subcontractor, GFL Excavating will be removing material from the site: three (3) dump trucks will take 10 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

Wednesday, June 27

  • Subcontractor, GFL Excavating will be removing material from the site: three (3) dump trucks will take 10 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

Thursday, June 28

  • Subcontractor, GFL Excavating will be removing material from the site: three (3) dump trucks will take 10 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

Friday, June 29

  • Subcontractor, GFL Excavating will be removing material from the site: three (3) dump trucks will take 10 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

* * *

NOTES:

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage June 25 – 29 summary highlights: L Tower & Backstage Construction June 25-29

Backstage Saturday June 16

This is the current construction schedule for 1 The Esplanade – Backstage – for  Saturday, June 16, 2012

Posted June 15, 2012

Saturday, June 16

  • Deep Foundation will have three welders on site installing tie back connections.

Backstage Construction Schedule – June 18 – 22

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for June 18 – 22, 2012

Posted June 15, 2012

NOTE: For photos illustrating the current forms of work at the Backstage site please click here.

Monday, June 18

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs. 

Tuesday, June 19

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

Wednesday, June 20

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs. 

Thursday, June 21

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

Friday, June 22

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

* * *

NOTES:

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage June 18 – 22 summary highlights: L Tower & Backstage Construction June 18-22

Backstage Construction Schedule – June 11 – 15

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for June 11 – 15, 2012

Posted June 8, 2012

NOTE: For photos illustrating the current forms of work at the Backstage site please click here.

Monday, June 11

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs. 

Tuesday, June 12

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

Wednesday, June 13

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs. 

Thursday, June 14

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

Friday, June 15

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

* * *

NOTES:

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage June 11 – 15 summary highlights: L Tower & Backstage Construction June 11-15

Backstage Construction Schedule – June 4 – 8

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for June 4 – 8, 2012

Posted June 1, 2012

NOTE:

  • We have also been advised that the final phase of the Waterfront Toronto sewer construction contract will begin on Monday, June 4 for approximately 8 weeks.  Jarvis Street will be reduced to one lane in each direction betweenThe Esplanade and Wilton Street.

Monday, June 4

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs. 

Tuesday, June 5

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

Wednesday, June 6

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs. 

Thursday, June 7

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

Friday, June 8

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing tie backs.

* * *

NOTES:

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage June 4 – 8 summary highlights: L Tower & Backstage Construction June 4-8

Backstage Construction Schedule – May 28 – June 1

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for May 28 – June 1, 2012

Posted May 25, 2012

NOTE: We have been advised that The Sony Centre has an event on May 31. TV trucks may be parked adjacent to the Stage Door area on Scott Street. Traffic may be affected.

Monday, May 28 

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing the tie back drill. 

Tuesday, May 29

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing the tie back drill.

Wednesday, May 30

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing the tie back drill. 

Thursday, May 31

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing the tie back drill.

Friday, June 1

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of thirty (30) loads.
  • Subcontractor, Deep Foundation installing the tie back drill. 

* * *

NOTES:

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage May 28 – June 1 summary highlights: L Tower & Backstage Construction May 28 – June 1

Backstage Construction Schedule – May 7 – 11

This is the current construction schedule for 1 The Esplanade – L Tower parking and
Backstage condominium for May 7 – 11, 2012

Posted May 04, 2012

Monday, May 7

  • Between 9 am and 3 pm, Deep Foundation, will be “float out” the drill rig from the site at 1 The Esplanade on a large truck, under police escort.
    • Pedestrian and vehicular traffic will be impacted during this operation. 
    • Please check back on May 7 for a more precise time for the “float out.”
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Tuesday, May 8

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Wednesday, May 9

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Thursday, May 10

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Friday, May 11

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

* * *

NOTES:

All the piles and caissons are complete on the site.

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage May 7 – 11 summary highlights: L Tower & Backstage Construction May 7 – 11

Backstage Construction Schedule – April 23 – 27

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for April 23 – 27, 2012

Posted April 20, 2012

Monday, April 23

  • Subcontractor, Deep Foundation, will be removing the tie drill in the morning.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Tuesday, April 24

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Wednesday, April 25

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Thursday, April 26

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Friday, April 27

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

* * *

NOTES:

Deep Foundation will complete the pile and caisson drilling this week. The drill rig will be removed from the site once drilling is completed. Please check back for an update on the time and date of the drill rig removal. 

A Paid Duty Police Officer is on-site daily Monday to Thursday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 23 – 27 summary highlights: L Tower & Backstage Construction April 23-27

Backstage Construction Schedule – April 16 – 20

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for April 16 – 20, 2012

Posted April 13, 2012

Monday, April 16

  • Subcontractor, Deep Foundation, will be installing tie backs and drilling piles and caissons.
    • There will be two (2) concrete trucks doing four rounds each (8 in total) in and out of the site.
  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 5 loads each, for a total of 20 loads.

Tuesday, April 17

  • Subcontractor, Deep Foundation, will be installing tie backs and drilling piles and caissons.
    • There will be two (2) concrete trucks doing four rounds each (8 in total) in and out of the site.
  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 5 loads each, for a total of 20 loads.

Wednesday, April 18

  • Subcontractor, Deep Foundation, will be installing tie backs and drilling piles and caissons.
    • There will be two (2) concrete trucks doing four rounds each (8 in total) in and out of the site.
  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 5 loads each, for a total of 20 loads.

Thursday, April 19

  • Subcontractor, Deep Foundation, will be installing tie backs and drilling piles and caissons.
    • There will be two (2) concrete trucks doing four rounds each (8 in total) in and out of the site.
  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 5 loads each, for a total of 20 loads.

Friday, April 20

  • Subcontractor, Deep Foundation, will be installing tie backs and drilling piles and caissons.
    • There will be two (2) concrete trucks doing four rounds each (8 in total) in and out of the site.
  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 5 loads each, for a total of 20 loads.

* * *

NOTES:

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 14 – 21 summary highlights: L Tower & Backstage Construction Summary Highlights April 14-21