Backstage Construction Schedule – June 14 – 20

Backstage first tower floorplus 25 The Esplanade

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for June 14 – 20, 2014.

Please click here for general information on concrete pours.

Saturday, June 14

  • No work is scheduled.

Monday, June 16

  • Sixth floor concrete pour by subcontractor Italform. The pour is scheduled to run between 1:00 pm and 4:00 pm.

 Tuesday, June 17

  • Rebar (steel) delivery starting at 7:00 am
  • Sixth floor concrete pour by subcontractor Italform. The pour is scheduled to run between 1:00 pm and 3:00 pm.

Wednesday, June 18

  • Seventh floor slab concrete pour #1 by subcontractor Italform, scheduled to begin at 10:00 am.
  • Concrete Finishing to 7:00 pm.

Thursday, June 19

  • Seventh floor concrete pour by subcontractor Italform. The pour is scheduled to run between 1:00 pm and 3:00 pm.

 Friday June 20

  • Rebar (steel) delivery starting at 7:00 am
  • Seventh floor concrete pour by subcontractor Italform. The pour is scheduled to run between 1:00 pm and 3:00 pm.

NOTES:

      • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
      • Concrete pour schedules and times are subject to weather conditions.
      • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
      • Concrete trucks must keep their engines running during the pouring process.


Backstage Construction Schedule – June 7 – 13

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for June 7 – 13, 2014.

Please click here for general information on concrete pours.

First floor of the Backstage condo's tower section.

First floor of the Backstage condo’s tower section.

Saturday, June 7

  • No work is scheduled.

Monday, June 9

  • Sixth floor slab concrete pour #1 by subcontractor Italform, scheduled to begin at 9:00 am.
  • After slab concrete pour by subcontractor Italform.
  • Concrete Finishing to 10:00 pm.

 Tuesday, June 10

  • Rebar (steel) delivery starting at 7:00 am
  • Sixth floor concrete pour by subcontractor Italform. The pour is scheduled to run between 1:00 pm and 4:00 pm.

Wednesday, June 11

  • Sixth floor slab concrete pour #2 by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
  • Concrete Finishing to 10:00 pm.

Thursday, June 12

  • Rebar (steel) delivery starting at 7:00 am
  • Sixth floor concrete pour by subcontractor Italform. The pour is scheduled to run between 1:00 pm and 4:00 pm.

 Friday June 13

  • Sixth floor slab concrete pour #3 by subcontractor Italform, scheduled to begin at 10:00 am.
  • After slab concrete pour by subcontractor Italform.
  • Concrete Finishing to 9:00 pm.

NOTES:

      • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
      • Concrete pour schedules and times are subject to weather conditions.
      • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
      • Concrete trucks must keep their engines running during the pouring process.


Backstage Construction Schedule – May 31 – June 6

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for May 31 – June 6, 2014.

Please click here for general information on concrete pours.

First floor of the Backstage condo's tower section.

First floor of the Backstage condo’s tower section.

Saturday, May 31

  • Clean-up and minor construction activities on site on site from 9:00 am to 1 pm

Monday, June 2

  • 6th floor concrete pour by subcontractor Italform. The pour is scheduled to run between 1:00 pm and 4:00 pm.

 Tuesday, June 3

  • Rebar (steel) delivery starting at 7:00 am
  • 6th floor concrete pour by subcontractor Italform. The pour is scheduled to run between 1:00 pm and 4:00 pm.

Wednesday, June 4

  • 6th floor concrete pour by subcontractor Italform. The pour is scheduled to run between 1:00 pm and 4:00 pm.

Thursday, June 5 – Friday June 6

  • Moving the mobile crane.

  • PLEASE NOTE: The Esplanade will be closed to vehicular traffic from Yonge Street to the west TPA Lot entrance on the south and Scott Street on the north, while the crane work is conducted. Paid-Duty police officers will be on-site during the work. 

NOTES:

      • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
      • Concrete pour schedules and times are subject to weather conditions.
      • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
      • Concrete trucks must keep their engines running during the pouring process.


L Tower Construction Schedule Updates – March 14 & 15

The Construction Schedule for the L Tower Condominium has been updated for March 14 and Saturday, March 15 below. 

Friday March 14

Crane work added to Friday’s schedule of work

Saturday, March 15

  • Deliveries to the hoist from 9:00 am
  • Some light crane work as required.