Backstage Crane Rising 3 storeys on Thursday

The crane at the Backstage Condominium will be raised three (3) storeys on Thursday, September 18. The work will be done by subcontractor Italform and is scheduled to take place between 3 pm and 7 pm.

Backstage Crane to be raised 3 additional storeys on September 18.

Backstage Crane to be raised 3 additional storeys on September 18.

 

Update re Backstage crane raising today, August 27

UPDATED at 5: 50 pm WEDNESDAY AUGUST 27, 2014

Looking up to see the crane at Backstage.

Looking up to see the crane at Backstage.

This afternoon’s crane raising has been delayed, work will unfortunately have to go past 8:00 pm tonight. Every effort will be made to complete the crane raising as soon as is safely possible tonight.

Concrete delivery was delayed today, causing the 15th floor concrete slab pour to be run late, and therefore delaying the large crane work.

 

NOTE: Thursday and Friday schedules for Backstage & L Tower remain as currently posted on this site.

Backstage crane to be raised 4 storeys today, August 27

UPDATE FOR WEDNESDAY AUGUST 27, 2014

Following today’s concrete slab pour but prior to the completion of concrete finishing, subcontractor Italform will be raising the large crane 4 storeys . This is scheduled to occur between 3:30 pm and 8:00 pm. 

Today’s concrete pour schedule – as previously posted.

  • 15th Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 1o:30 am.
  • An after-slab concrete pour for 9th floor walls and columns, 45 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

Thursday and Friday schedules for Backstage & L Tower remain as currently posted on this site.

  • Looking up to see the crane at Backstage.

    Looking up to see the crane at Backstage.

L Tower Construction Schedule October 27 – November 2

This is the current construction schedule for 8 The Esplanade – L Tower – for October 27 – November 2, 2012

Posted October 26, 2012

Saturday, October 27

  • A delivery of 2 containers of window/curtain wall between 9:00 am and 2:00 pm

Monday, October 29

  • There will be a platform removal
  • A rebar (steel) delivery starting at 12:30 pm.

Tuesday, October 30

  • A rebar (steel) delivery starting at 12:30 pm.

Wednesday, October 31

  • The boom crane will be on site to move concrete pump.
  • A rebar (steel) delivery starting at 12:30 pm.

Thursday, November 1

  • A rebar (steel) delivery starting at 12:30 pm.

Friday, November 2

  • A rebar (steel) delivery starting at 7:00 am.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction October 27 – November 2

L Tower Construction Schedule September 29 – October 5

This is the current construction schedule for 8 The Esplanade – L Tower – for September 29 – October 5, 2012

Posted September 28, 2012

Saturday, September 29

  • Washroom Servicing 9:00 am to Noon.
  • Crane raising. 

Monday, October 1

  • Delivery of (two) 2 lifts; Cooltech, HVAC at 7:00 am.
  • A rebar (steel) delivery starting at 7:00 am.
  • A delivery of 4 containers of window/curtain wall
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • An 18 to 27 cubic meter concrete pour for the housekeeping pads – 18 to 27 meters starting at 1 pm, to be completed by 5:00 pm..

Tuesday, October 2

  • A rebar (steel) delivery starting at 7:00 am.
    • Please note:
    • There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.
    • To ensure public safety pedestrian and cycling traffic may also be disrupted briefly during crane lifts and swings.
  • An 18 to 27 cubic meter concrete pour for the housekeeping pads – 18 to 27 meters starting at 1 pm, to be completed by 5:00 pm.

Wednesday, October 3

  • An 18 to 27 cubic meter concrete pour for the housekeeping pads – 18 to 27 meters starting at 1 pm, to be completed by 5:00 pm.

Thursday, October 4

  • An 18 to 27 cubic meter concrete pour for the housekeeping pads – 18 to 27 meters starting at 1 pm, to be completed by 5:00 pm.

Friday, October 5

  • An 18 to 27 cubic meter concrete pour for the housekeeping pads – 18 to 27 meters starting at 1 pm, to be completed by 5:00 pm.

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower – Backstage Construction Sept 29 – Oct 5

Urban Toronto captures Crane Raising at L Tower

Thanks to our friends at Urban Toronto for these pictures of the L Tower Crane Raising on Saturday, March 17, 2012.

Please click on this link to see the pictures.

L Tower Crane Raising – March 17

On Saturday, March 17 the crane at the L Tower will be raised 6 metres (20 feet).

Preparations will begin starting at 9:00 am. It is expected the crane will be raised at approximately 11:00 am. Work should be completed by Noon. However, it is possible the work may take longer.

L Tower Crane as seen on Friday, March 16

o

L Tower – 8 The Esplanade – Saturday March 3 – Crane Raising and Concrete Pour

UPDATE for Saturday, March 3,  8 The Esplanade – L Tower for February 27 – March 3, 2012

Updated March 3, 2012

NOTE: Bad weather this past week delayed the pouring of the concrete slab at Level 29, so significant Saturday work is required; as is permitted by the City of Toronto by-law.

Saturday, March 3

  • The crane will be raised beginning at 9:00 am but is dependent on weather. For example, if there is significant wind the crane raising may be delayed or re-scheduled.
  • Concrete pour CANCELLED due to high winds.

  • A 220M concrete pour for the slab at Level 29 beginning at 9:00 am, which is not expected to extend beyond 7:00 pm.
  • A Paid Duty Officer will be in attendance.