Late Concrete Finishing Tonight at Backstage

CONSTRUCTION UPDATE for Backstage January 15, 2014

Due to tower crane mechanical problems the duration of today’s slab pour went late. Concrete finishing will extend to 12:30 am. 

The construction management team apologizes for any inconvenience this may cause. 

Backstage Construction Schedule – April 30 – May 4

This is the current construction schedule for 1 The Esplanade – L Tower parking and
Backstage condominium for April 30 – May 4, 2012

Posted April 27/12

Monday, April 30

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Tuesday, May 1

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Wednesday, May 2

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Thursday, May 3

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Friday, May 4

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

* * *

NOTES:

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 30 – May 4 summary highlights: L Tower & Backstage Construction April 30-May 4

Revised L Tower Concrete Pour Schedule March 5 – 9

Please note that the concrete pour schedule for L Tower for the week of March 5th, has been revised due to weather conditions that prevented the concrete pour that had been scheduled for Saturday, March 3.

There will now be concrete pours Monday through Friday. For details please click on this link.

Backstage – 1 The Esplanade – Construction Schedule Feb 13 – 17

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for February 13 – 17, 2012

Posted February 10, 2012

Monday, February 13

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.
  • Sub-contractor, GFL and will have four (4) dump trucks removing material from the site, doing five (5) rounds each.

Tuesday, February 14

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.

Wednesday, February 15

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.

Thursday, February 16

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.

Friday, February 17

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Backstage – 1 The Esplanade – UPDATE for February 1

UPDATE January 31, 2012

Wednesday, February 1

  • UPDATE – Sub-contractor GFL Excavating will have three (3) dump trucks removing material from the site at 1 The Esplanade. There will be three (3) truck doing 5 rounds of removal each.
  • For a full listing of construction activity for the week at 1 The Esplanadeplease click here.

Backstage – 1 The Esplanade – Construction Schedule Jan 30 – Feb 3

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for January 30 – February 3, 2012

UPDATED January 31, 2012

Monday, January 30

  • Sub-contractor, Deep Foundation will be removing one of the drill rigs from the site, beginning at 7:00 am.
  • At approximately 10:00 am, a semi-trailer with the float for the drill rig will arrive to take it off-site. There will be short-term disruptions to pedestrian and vehicular traffic.
  • The remaining drill rig on site will continue drilling caissons and piles.
  • Five (5) loads of concrete.

Tuesday, January 31

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Five (5) loads of concrete.

Wednesday, February 1

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Five (5) loads of concrete.
  • UPDATE – Sub-contractor GFL Excavating will have three (3) dump trucks removing material from the site at 1 The Esplanade. There will be three (3) truck doing 5 rounds of removal each.

Thursday, February 2

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Five (5) loads of concrete.

Friday, February 3

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Five (5) loads of concrete.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

1 The Esplanade – Construction Schedule Jan 23 – 27, 2012

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for January 23 – 27, 2012

Posted January 20, 2012

Monday, January 23

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Tuesday, January 24

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Wednesday, January 25

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Thursday, January 26

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Friday, January 27

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

1 The Esplanade – Construction Schedule Jan 16 – 20, 2012

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for January 16 – 20, 2012

Posted January 13, 2012

Monday, January 16

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Tuesday, January 17

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Wednesday, January 18

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Thursday, January 19

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Friday, January 20

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

1 The Esplanade – Construction Schedule Jan 9 – 13, 2012

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for January 9 – 13, 2012

Posted January 6, 2012

Monday, January 9

  • Steel pile delivery at 7:00 am.
  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete into the site.
  • Sub-contractor, GFL delivering an excavator.

Tuesday, January 10

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete into the site.
  • Sub-contractor, GFL breaking the bridge retaining wall.

Wednesday, January 11

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete into the site.
  • Sub-contractor, GFL breaking the bridge retaining wall.

Thursday, January 12

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete into the site.
  • Sub-contractor, GFL breaking the bridge retaining wall.

Friday, January 13

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete into the site.
  • Sub-contractor, GFL breaking the bridge retaining wall.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

1 The Esplanade – Construction Schedule Jan 3 – 6, 2012

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for January 3 – 6, 2012

Posted January 3, 2012

Tuesday, January 3

  • Sub-contractor, Deep Foundation drilling caissons: 5 loads of concrete.

Wednesday, January 4

  • Sub-contractor, Deep Foundation drilling caissons: 5 loads of concrete.

Thursday, January 5

  • Sub-contractor, Deep Foundation drilling caissons: 5 loads of concrete.

Friday, January 6

  • Sub-contractor, Deep Foundation drilling caissons: 5 loads of concrete..

* * *

Best wishes for the New Year!

NOTES:

A Paid Duty Police Officer is on-site daily Tuesday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.