Backstage Construction Schedule April 13 – 17, 2015
April 13, 2015 Leave a comment
This is the current construction schedule for 1 The Esplanade, Backstage condominium – for April 13 – 17, 2015.
Last concrete pour for the tower and work on the podium deck outdoor swimming pool are the main construction activities this week.
Click on the link for a downloadable PDF Construction Summary: Backstage & L Tower Construction Summary-Apr-13-17-2015
Monday, April 13
- Last concrete pour for the tower, elevator curbs on the roof (8 meters of concrete), starting at 12:00 pm.
- Interior suite drywall and finishing.
Tuesday, April 14
- Subcontractor Italform demobilizing their equipment and materials.
- Working on 5th floor swimming pool.
- Waterproofing 5th floor podium.
- Interior suite drywall and finishing.
- 35th floor Window delivery occupying north curb lane of the Esplanade, starting at 2:00 pm to approximately 4:00 pm.
Wednesday, April 15
- Subcontractor Italform demobilizing their equipment and materials.
- Working on 5th floor swimming pool.
- Waterproofing 5th floor podium.
- Interior suite drywall and finishing.
Thursday, April 16
- Subcontractor Italform demobilizing their equipment and materials.
- Working on 5th floor swimming pool.
- Waterproofing 5th floor podium.
- Interior suite drywall and finishing.
Friday, April 17
- Subcontractor Italform demobilizing their equipment and materials.
- Working on 5th floor swimming pool.
- Waterproofing 5th floor podium.
- Interior suite drywall and finishing.
NOTES:
- All rebar deliveries are now complete.
- A Paid Duty Police Officer may be on-site when required and when available to assist with traffic control, Monday to Friday, from 7:00 am to 4:00 pm daily.
- Concrete pour schedules and times are subject to weather conditions.
- There may be some short-term impacts on traffic flow as concrete or delivery trucks are moved into position.
- Concrete trucks must keep their engines running during the pouring process.