Backstage Construction Schedule – August 30 – September 5

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for August 30 – September 5, 2014.             Please click here for general information on concrete pours

 

The crane in action at Backstage condominium, August 28, 2014

The crane in action at Backstage condominium, August 28, 2014

Saturday, August 30

  • A Italform crew working on the Protective Platform on the south side for the building from 9:00 am – 3:00 pm. 
  • A Dominus Construction crew doing housekeeping on-site from from 9:00 am – 2:00 pm. 

Monday, September 1 – Labour Day – SITE CLSOED FOR THE HOLIDAY

Tuesday, September 2

  • Rebar delivery from 7:00 am.
  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Wednesday, September 3

  • 16th  Floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab concrete pour for 9th floor walls and columns, 45 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

Thursday, September 4

  • 16th Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 1o:30 am.
  • An after-slab concrete pour for 9th floor walls and columns, 45 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

Friday, September 5

  • Rebar delivery from 7:00 am.
  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

 NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Update re Backstage crane raising today, August 27

UPDATED at 5: 50 pm WEDNESDAY AUGUST 27, 2014

Looking up to see the crane at Backstage.

Looking up to see the crane at Backstage.

This afternoon’s crane raising has been delayed, work will unfortunately have to go past 8:00 pm tonight. Every effort will be made to complete the crane raising as soon as is safely possible tonight.

Concrete delivery was delayed today, causing the 15th floor concrete slab pour to be run late, and therefore delaying the large crane work.

 

NOTE: Thursday and Friday schedules for Backstage & L Tower remain as currently posted on this site.

Backstage crane to be raised 4 storeys today, August 27

UPDATE FOR WEDNESDAY AUGUST 27, 2014

Following today’s concrete slab pour but prior to the completion of concrete finishing, subcontractor Italform will be raising the large crane 4 storeys . This is scheduled to occur between 3:30 pm and 8:00 pm. 

Today’s concrete pour schedule – as previously posted.

  • 15th Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 1o:30 am.
  • An after-slab concrete pour for 9th floor walls and columns, 45 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

Thursday and Friday schedules for Backstage & L Tower remain as currently posted on this site.

  • Looking up to see the crane at Backstage.

    Looking up to see the crane at Backstage.

Backstage Construction Schedule Updates – March 14 & 15

The Construction Schedule for Backstage Condominium has been updated for March 14 and Saturday, March 15 below. 

Friday March 14

Concrete Slab Pour cancelled. 

Saturday, March 15

  • Fourth floor slab concrete pour #4, by subcontractor Italform, scheduled to begin at 9:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform.
  • Concrete Finishing to 10:00 pm.

Late Concrete Finishing Tonight at Backstage

CONSTRUCTION UPDATE for Backstage January 15, 2014

Due to tower crane mechanical problems the duration of today’s slab pour went late. Concrete finishing will extend to 12:30 am. 

The construction management team apologizes for any inconvenience this may cause. 

Backstage Construction Update – November 1

This is the construction update for 1 The Esplanade – Backstage condominium for  November 1, 2013

Please click here for general information on concrete pours.

UPDTED October 31

Friday, November 1

  • There will be a rebar delivery at 7:00 am.
  • Pouring second floor slab pour by subcontractor Italform. The pour is tentatively  scheduled to begin 10:00 am.
  • After slab, 50 cubic metre wall and column concrete pour by subcontractor Italform. This pour is scheduled to begin at 12:30 pm and should be completed no later than 5:00 pm.
  • Concrete finishing, scheduled to proceed until 10:00 PM.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.


Backstage Concrete Pour UPDATE for October 29

Please note: that the tentatively scheduled 2nd floor concrete slab pour at the Backstage Condo site is underway today and unfortunately will require concrete finishing until 11:30 pm this evening.

The construction management team apologies for any inconvenience this may cause.

Please click here for the full updated Backstage construction schedule for the week of October 28. 

NOTE: Concrete pours are exempt from the City of Toronto Construction Noise By-law weekday hours of 7:00 am to 7:00 pm.

Backstage Concrete Pour UPDATE – August 19

This is an update for the construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  August 19, 2013

Please click here for general information on concrete pours.

Updated August 19.

Monday, August 19

  • Please be advised that due to unforeseen circumstances concrete finishing at Backstage will unfortunately go past 11:00 pm tonight. Every effort will be made to complete the work as soon as possible. 
     
    We apologize for any inconvenience this may cause and thank you in advance for your kind understanding. 

Backstage Concrete Pour UPDATE – June 24

This is an update for the construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  June 24, 2013

Please click here for general information on concrete pours.

Updated June 24.

Monday, June 24

  • Please be advised that because of this afternoon’s rain, concrete finishing at Backstage will unfortunately go past 10:00 pm tonight. Every effort will be made to complete the work as soon as possible. 
     
    We apologize for any inconvenience this may cause and thank you in advance for your kind understanding. 
%d bloggers like this: