Backstage Construction Schedule – September 10 – 14

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for September 10 – 14, 2012

Posted September 7, 2012

Monday, September 10 

  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 14 loads each, for a total of fifty-six (56) loads. *
  • Subcontractor, Deep Foundation will be installing rock anchors.

Tuesday, September 11

  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 14 loads each, for a total of fifty-six (56) loads. *
  • Subcontractor, Deep Foundation will be installing rock anchors.

Wednesday, September 12

  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 14 loads each, for a total of fifty-six (56) loads. *
  • Subcontractor, Deep Foundation will be will be installing rock anchors.

Thursday, September 13

  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 14 loads each, for a total of fifty-six (56) loads. *
  • Subcontractor, Deep Foundation will be installing rock anchors.

Friday, September 14

  • Subcontractor, GFL Excavating will be removing material from the site: four (4) dump trucks will take 14 loads each, for a total of fifty-six (56) loads. *
  • Subcontractor, Deep Foundation will be installing rock anchors.

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction September 8-14

Backstage Construction Schedule – September 4 – 7

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for September 4 – 7, 2012

Posted August 31, 2012

Monday, September 3 – Labour Day – Holiday 

Tuesday, September 4

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
  • Subcontractor, Deep Foundation will be installing rock anchors.

Wednesday, September 5

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
  • Subcontractor, Deep Foundation will be will be installing rock anchors.

Thursday, September 6

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
  • Subcontractor, Deep Foundation will be installing rock anchors.

Friday, September 7

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
  • Subcontractor, Deep Foundation will be installing rock anchors.

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: Revised L Tower – Backstage Construction Sept 4-7

Backstage Construction Schedule – August 27 – 31

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for August 27 – 31, 2012

Posted August 24, 2012

Monday, August 27

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Tuesday, August 28

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Wednesday, August 29

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
  • Subcontractor, Deep Foundation will be bringing in a rock anchor drill and beginning to install the last row of tie backs.
    • Please Note: there may be disrutions to pedestrian and vehicualr traffic during the delivery and unloading of the drill.

Thursday, August 30

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
  • Subcontractor, Deep Foundation will be installing the last row of tie backs.

Friday, August 31

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *
  • Subcontractor, Deep Foundation will be installing the last row of tie backs.

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: Revised L Tower & Backstage Construction August 28-31

Backstage Construction Schedule – August 20 – August 24

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for August 20 – August 24, 2012

Posted August 17, 2012

Monday, August 20

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Tuesday, August 21

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Wednesday, August 22

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Thursday, August 23

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Friday, August 24

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction August 18 – 24

Backstage Construction Schedule – August 13 – August 17

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for August 11 – August 17, 2012

Updated August 13, 2012

PLEASE NOTE:

  • The Esplanade reopened on August 13th to Eastbound vehicles between Yonge Street and Scott Street and pedestrians Eastbound and Westbound between Yonge Street and Scott Street.

Monday, August 13

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Tuesday, August 14

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Wednesday, August 15

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Thursday, August 16

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

Friday, August 17

  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 14 loads each, for a total of eighty-four (84) loads. *

NOTES: 

* Dump truck frequencies are dependent on road and traffic conditions and the amount excavation materials at any given time on the site.

Construction activities are dependent on whether.

Paid Duty Police Officer is on-site   daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Please click here for a downloadable construction summary: L Tower & Backstage Construction August 11 -17