Backstage Construction Schedule – April 30 – May 4

This is the current construction schedule for 1 The Esplanade – L Tower parking and
Backstage condominium for April 30 – May 4, 2012

Posted April 27/12

Monday, April 30

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Tuesday, May 1

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Wednesday, May 2

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Thursday, May 3

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site.
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

Friday, May 4

  • Subcontractor, Deep Foundation, will be drilling piles and caissons.
    • There will be five loads of concrete delivered to the site
  • Subcontractor, GFL Excavating will be removing material from the site: six (6) dump trucks will take 5 loads each, for a total of 30 loads.

* * *

NOTES:

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 30 – May 4 summary highlights: L Tower & Backstage Construction April 30-May 4

Backstage Construction Schedule – April 9 – 13

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for April 9 – 13, 2012

Updated April 10, 2012

NOTE: Subcontractor, Deep Foundation will be delivering a large drill rig to the site at 1 The Esplanade in order to complete the piles and caisson work this week. The delivery date is not confirmed at the time of posting. Please check back for updated information.

Monday, April 9

  • Subcontractor, Deep Foundation, will be installing a second row of tie backs.
  • Subcontractor, GFL Excavating will be removing material from the site: 4 dump trucks will take 5 loads each, for a total of 20 loads.

Tuesday, April 10

  • Subcontractor, Deep Foundation, will be installing a second row of tie backs.
  • Subcontractor, GFL Excavating will be removing material from the site: 4 dump trucks will take 5 loads each, for a total of 20 loads.

Wednesday, April 11

  • Subcontractor, Deep Foundation, will be delivering a drill rig to the site at 1 The Esplanade after 9 am, under police escort.
    • There will be short-term disruptions to vehicular and pedestrian traffic. The construction management team apologizes for any short-term inconvenience this may cause.
  • Subcontractor, Deep Foundation, will be installing a second row of tie backs.
  • Subcontractor, GFL Excavating will be removing material from the site: 4 dump trucks will take 5 loads each, for a total of 20 loads.

Thursday, April 12

  • Subcontractor, Deep Foundation, will be installing a second row of tie backs.
  • Subcontractor, GFL Excavating will be removing material from the site: 4 dump trucks will take 5 loads each, for a total of 20 loads.

Friday,  April 13

  • Subcontractor, Deep Foundation, will be installing a second row of tie backs.
  • Subcontractor, GFL Excavating will be removing material from the site: 4 dump trucks will take 5 loads each, for a total of 20 loads.

* * *

NOTES:

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 9 – 13 summary update: 1+8 The Esplanade – Construction Notice-April-9-13

Backstage Construction Schedule – March 26 – 30

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for March 26 – 30, 2012

Posted March 23, 2012

NOTE: The job site at 1 The Esplanade is in transition from GFL Excavating to Deep Foundation for the completion of pile and caisson work and starting at the second row tie back. There will be a drill rig and tie back drill delivered to the site but the delivery date are not confirmed at this time. Please check back for updates.

Monday, March 26

  • Sub-contractor, GFL Excavating, preparing caisson walls for Deep Foundation tie back installation.

Tuesday, March 20

  • Sub-contractor, GFL Excavating, preparing caisson walls for Deep Foundation tie back installation.

Wednesday, March 21

  • Sub-contractor, GFL Excavating, preparing caisson walls for Deep Foundation tie back installation.

Thursday, March 22

  • Sub-contractor, GFL Excavating, preparing caisson walls for Deep Foundation tie back installation.

Friday, March 23

  • Sub-contractor, GFL Excavating, preparing caisson walls for Deep Foundation tie back installation.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage March 26 – 31 summary update: L Tower & Backstage Construction March 26-31

Backstage – 1 The Esplanade – Construction Schedule Feb 21 – 24

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for February 20 – 24, 2012

Posted February 17, 2012

Monday, February 20 – Family Day Holiday

Tuesday, February 21

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Five (5) loads of concrete.

Wednesday, February 22

  • Sub-contractor, Deep Foundation disassembling drill.
  • Sub-contractor, GFL Excavating, and will have four (4) dump trucks removing material from the site, doing five (5) rounds each.

Thursday, February 23

  • Sub-contractor, Deep Foundation floating out the drill rig under police escort. Time to be posted.
  • Sub-contractor, GFL Excavating, and will have six (6) dump trucks removing material from the site, doing five (5) rounds each.

Friday, February 24

  • Sub-contractor, GFL Excavating, and will have six (6) dump trucks removing material from the site, doing five (5) rounds each.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Backstage – 1 The Esplanade – UPDATE for February 1

UPDATE January 31, 2012

Wednesday, February 1

  • UPDATE – Sub-contractor GFL Excavating will have three (3) dump trucks removing material from the site at 1 The Esplanade. There will be three (3) truck doing 5 rounds of removal each.
  • For a full listing of construction activity for the week at 1 The Esplanadeplease click here.

Backstage – 1 The Esplanade – Construction Schedule Jan 30 – Feb 3

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for January 30 – February 3, 2012

UPDATED January 31, 2012

Monday, January 30

  • Sub-contractor, Deep Foundation will be removing one of the drill rigs from the site, beginning at 7:00 am.
  • At approximately 10:00 am, a semi-trailer with the float for the drill rig will arrive to take it off-site. There will be short-term disruptions to pedestrian and vehicular traffic.
  • The remaining drill rig on site will continue drilling caissons and piles.
  • Five (5) loads of concrete.

Tuesday, January 31

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Five (5) loads of concrete.

Wednesday, February 1

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Five (5) loads of concrete.
  • UPDATE – Sub-contractor GFL Excavating will have three (3) dump trucks removing material from the site at 1 The Esplanade. There will be three (3) truck doing 5 rounds of removal each.

Thursday, February 2

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Five (5) loads of concrete.

Friday, February 3

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Five (5) loads of concrete.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

1 The Esplanade – Construction Schedule Jan 23 – 27, 2012

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for January 23 – 27, 2012

Posted January 20, 2012

Monday, January 23

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Tuesday, January 24

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Wednesday, January 25

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Thursday, January 26

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Friday, January 27

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

1 The Esplanade – Construction Schedule Jan 16 – 20, 2012

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for January 16 – 20, 2012

Posted January 13, 2012

Monday, January 16

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Tuesday, January 17

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Wednesday, January 18

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Thursday, January 19

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Friday, January 20

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Drilling and “breaking” for Backstage

These pictures show site work today–1/9/12–at 1 The Esplanade, preparing the way for the Backstage Condominium from Castlepoint, Cityzen and Fernbrook Homes. The site will also house the underground parking for the adjacent L Tower. The work this week is focused on drilling caissons and “breaking” parts of the railway bridge structure that will be replaced by the Backstage podium. During construction work there are also some temporary holds on eastbound traffic but with every effort made to minimize delays.

Between Backstage and L Tower, temporarily holding traffic on The Esplanade, 1/9/12

"Breaking" a section of railway bridge with a pneumatic hammer, 1 The Esplanade, 1/9/12

Drilling at the Backstage construction site, 1 The Esplanade, 1/9/12

Backstage construction site looking west, 1 The Esplanade, 1/9/12

A "found" metal "flower" at the Backstage construction site, 1 The Esplanade, 1/9/12

Backstage construction site, looking east, 1 The Esplanade, 1/9/12

1 The Esplanade – Construction Schedule Jan 9 – 13, 2012

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for January 9 – 13, 2012

Posted January 6, 2012

Monday, January 9

  • Steel pile delivery at 7:00 am.
  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete into the site.
  • Sub-contractor, GFL delivering an excavator.

Tuesday, January 10

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete into the site.
  • Sub-contractor, GFL breaking the bridge retaining wall.

Wednesday, January 11

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete into the site.
  • Sub-contractor, GFL breaking the bridge retaining wall.

Thursday, January 12

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete into the site.
  • Sub-contractor, GFL breaking the bridge retaining wall.

Friday, January 13

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete into the site.
  • Sub-contractor, GFL breaking the bridge retaining wall.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

%d bloggers like this: