Backstage Construction Schedule – April 2 – 6

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for April 2 – 6, 2012

Posted March 30, 2012

Monday, April 2

  • Sub-contractor, Deep Foundation, will be floating in the tie back machine in the morning.
  • NOTE: This will unfortunately cause short-term delays for vehicular and pedestrian traffic.

Tuesday, April 3

  • Sub-contractor, Deep Foundation, will be installing tie backs.

Wednesday, April 4

  • Sub-contractor, Deep Foundation, will be installing tie backs.
  • Sub-contractor, GFL Excavating, will be removing material from the site: 4 trucks doing 5 loads each.

Thursday, April 5

  • Sub-contractor, Deep Foundation, will be installing tie backs.
  • Sub-contractor, GFL Excavating, will be removing material from the site: 4 trucks doing 5 loads each.

Good Friday – Holiday – April 6

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Thursday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage April 2 – 6 summary update: L Tower & Backstage Construction April 2 – 6

Backstage Construction Schedule – March 26 – 30

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for March 26 – 30, 2012

Posted March 23, 2012

NOTE: The job site at 1 The Esplanade is in transition from GFL Excavating to Deep Foundation for the completion of pile and caisson work and starting at the second row tie back. There will be a drill rig and tie back drill delivered to the site but the delivery date are not confirmed at this time. Please check back for updates.

Monday, March 26

  • Sub-contractor, GFL Excavating, preparing caisson walls for Deep Foundation tie back installation.

Tuesday, March 20

  • Sub-contractor, GFL Excavating, preparing caisson walls for Deep Foundation tie back installation.

Wednesday, March 21

  • Sub-contractor, GFL Excavating, preparing caisson walls for Deep Foundation tie back installation.

Thursday, March 22

  • Sub-contractor, GFL Excavating, preparing caisson walls for Deep Foundation tie back installation.

Friday, March 23

  • Sub-contractor, GFL Excavating, preparing caisson walls for Deep Foundation tie back installation.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on the link for a printable PDF of the L Tower and Backstage March 26 – 31 summary update: L Tower & Backstage Construction March 26-31

Backstage Construction Site Photos March 16/12

Backstage Construction site March 16, 2012 looking west to Yonge Street Railway Bridge

Excavating bulk - 1 The Esplanade - March 16, 2012

Excavating 1 The Esplanade - March 16, 2012

Loading the dirt into the dump truck - 1 load of 50 per day - 1 The Esplanade March 16, 2012

Backstage – Construction Schedule – March 5 – 9

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for March 5 – 9, 2012

Posted March 2, 2012

Monday, March 5

  • Sub-contractor, GFL Excavating, doing bulk excavating, with five (5) dump trucks removing material from the site, doing five (5) rounds each.

Tuesday, March 6

  • Sub-contractor, GFL Excavating, doing bulk excavating, with five (5) dump trucks removing material from the site, doing five (5) rounds each.

Wednesday, March 7

  • Sub-contractor, GFL Excavating, doing bulk excavating, with five (5) dump trucks removing material from the site, doing five (5) rounds each.

Thursday, March 8

  • Sub-contractor, GFL Excavating, doing bulk excavating, with five (5) dump trucks removing material from the site, doing five (5) rounds each.

Friday, March 9

  • Sub-contractor, GFL Excavating, doing bulk excavating, with five (5) dump trucks removing material from the site, doing five (5) rounds each.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Click on this link for a printable PDF summary schedule of the L Tower and Backstage for March 3 – 10 inclusive: 1+8 The Esplanade – Construction Notice-March-3-10

Backstage – Construction Schedule Feb 27 – Mar 2

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for February 27 – March 2, 2012

Posted February 24, 2012

Monday, February 27

  • Sub-contractor, GFL Excavating, doing bulk excavating, with fifteen (15) dump trucks removing material from the site, doing five (5) rounds each.

Tuesday, February 28

  • Sub-contractor, GFL Excavating, doing bulk excavating, with fifteen (15) dump trucks removing material from the site, doing five (5) rounds each.

Wednesday, February 29

  • Sub-contractor, GFL Excavating, doing bulk excavating, with fifteen (15) dump trucks removing material from the site, doing five (5) rounds each.

Thursday, March 1

  • Sub-contractor, GFL Excavating, doing bulk excavating, with fifteen (15) dump trucks removing material from the site, doing five (5) rounds each.

Friday, March 2

  • Sub-contractor, GFL Excavating, doing bulk excavating, with fifteen (15) dump trucks removing material from the site, doing five (5) rounds each.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

Schedule for 1 The Esplanade October 31 – November 4

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for the week of October 31 – November 4, 2011

Posted October 29, 2011

For example images of this work please click here.

 

Monday, October 31

  • Sub-contractor GFL will be doing bulk excavating. There will be 15 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.

    • The trucks will enter from eastbound from Yonge Street, travel just west of the Esplanade gate toward Scott Street, then reverse  into the site to pick up the excavated bulk. The trucks will then pull out and exit east along The Esplanade.
    • There will be short-term impacts to vehicular and pedestrian traffic while the trucks are entering and departing the site.

Tuesday, November 1

  • Sub-contractor GFL will be doing bulk excavating. There will be 15 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.
    • The trucks will enter from eastbound from Yonge Street, travel just west of the Esplanade gate toward Scott Street, then reverse  into the site to pick up the excavated bulk. The trucks will then pull out and exit east along The Esplanade.
    • There will be short-term impacts to vehicular and pedestrian traffic while the trucks are entering and departing the site.

Wednesday, November 2

  • Sub-contractor GFL will be doing bulk excavating. There will be 15 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.
    • The trucks will enter from eastbound from Yonge Street, travel just west of the Esplanade gate toward Scott Street, then reverse into the site to pick up the excavated bulk. The trucks will then pull out and exit east along The Esplanade.
    • There will be short-term impacts to vehicular and pedestrian traffic while the trucks are entering and departing the site.

Thursday, November 3

  • Sub-contractor GFL will be doing bulk excavating. There will be 15 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.
    • The trucks will enter from eastbound from Yonge Street, travel just west of the Esplanade gate toward Scott Street, then reverse into the site to pick up the excavated bulk. The trucks will then pull out and exit east along The Esplanade.
    • There will be short-term impacts to vehicular and pedestrian traffic while the trucks are entering and departing the site.

Friday, November 4

  • Sub-contractor GFL will be doing bulk excavating. There will be 15 trucks each doing 5 rounds of hauling, entering and exiting at the 1 The Esplanade gate, just west of Scott Street.
    • The trucks will enter from eastbound from Yonge Street, travel just west of the Esplanade gate toward Scott Street, then reverse into the site to pick up the excavated bulk. The trucks will then pull out and exit east along The Esplanade.
    • There will be short-term impacts to vehicular and pedestrian traffic while the trucks are entering and departing the site.
NOTES:
  • A Paid Duty Police Officer is on-site daily from 7:00 am to 4:00 pm daily to assist with traffic control.