Backstage – Bridge Demolition March 17

On Saturday March 17, a machine for bridge demolition will arrive at 9:00 am on the Backstage condominium construction site at 1 The Esplanade.

The remaining portion of the eastern bridge wall structure will be demolished.  This is necessary to permit the full site excavation for the L Tower underground parking and the construction of the Backstage Condominium.

1 The Esplanade - Portion of Bridge Wall to be demolished on March 17

1 The Esplanade – Construction Schedule Jan 16 – 20, 2012

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for January 16 – 20, 2012

Posted January 13, 2012

Monday, January 16

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Tuesday, January 17

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Wednesday, January 18

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Thursday, January 19

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

Friday, January 20

  • Deep Foundation drilling caissons and piles: Seven (7) loads of concrete.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.

1 The Esplanade – Construction Schedule Jan 9 – 13, 2012

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for January 9 – 13, 2012

Posted January 6, 2012

Monday, January 9

  • Steel pile delivery at 7:00 am.
  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete into the site.
  • Sub-contractor, GFL delivering an excavator.

Tuesday, January 10

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete into the site.
  • Sub-contractor, GFL breaking the bridge retaining wall.

Wednesday, January 11

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete into the site.
  • Sub-contractor, GFL breaking the bridge retaining wall.

Thursday, January 12

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete into the site.
  • Sub-contractor, GFL breaking the bridge retaining wall.

Friday, January 13

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete into the site.
  • Sub-contractor, GFL breaking the bridge retaining wall.

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.