Backstage Construction Schedule – August 30 – September 5

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for August 30 – September 5, 2014.             Please click here for general information on concrete pours

 

The crane in action at Backstage condominium, August 28, 2014

The crane in action at Backstage condominium, August 28, 2014

Saturday, August 30

  • A Italform crew working on the Protective Platform on the south side for the building from 9:00 am – 3:00 pm. 
  • A Dominus Construction crew doing housekeeping on-site from from 9:00 am – 2:00 pm. 

Monday, September 1 – Labour Day – SITE CLSOED FOR THE HOLIDAY

Tuesday, September 2

  • Rebar delivery from 7:00 am.
  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Wednesday, September 3

  • 16th  Floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 10:30 am.
  • An after-slab concrete pour for 9th floor walls and columns, 45 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

Thursday, September 4

  • 16th Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 1o:30 am.
  • An after-slab concrete pour for 9th floor walls and columns, 45 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

Friday, September 5

  • Rebar delivery from 7:00 am.
  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

 NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule – August 25 – 29

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for August 25 – 29, 2014. UPDATED August 27

Please click here for general information on concrete pours. –

 

Backstage Condominium

Backstage Condominium

Monday, August 25

  • A  wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Tuesday, August 26

  • Rebar delivery from 7:00 am.
  • 15th  Floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 1o:30 am.
  • An after-slab concrete pour for 9th floor walls and columns, 45 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

Wednesday, August 27 – UPDATED

  • 15th Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 1o:30 am.
  • An after-slab concrete pour for 9th floor walls and columns, 45 metres of concrete, to begin following the main slab pour.
  • NEW: Following the concrete slab pour, subcontractor Italform will be raising the large crane 4 storeys today, between 3:30 pm and 8:00 pm. 
  • Concrete Finishing until to 10:30 pm.

Thursday, August 28

  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Friday, August 29

  • Rebar delivery from 7:00 am.
  • 15th  Floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 1o:30 am.
  • An after-slab concrete pour for 9th floor walls and columns, 45 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:30 pm.

 NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule – August 16 – 22

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for August 16 – 22, 2014.

Please click here for general information on concrete pours.

 

Backstage August 15, 2014

Backstage August 15, 2014

Saturday, August 16

  • A 12-person forming crew from subcontractor Italform, will be on site working from 9:00 am.

Monday, August 18

  • A  wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Tuesday, August 19

  • Rebar delivery from 7:00 am.
  • 14th  Floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 1o:00 am.
  • An after-slab concrete pour for 9th floor walls and columns, 45 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

Wednesday, August 20

  • 14th Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 1o:00 am.
  • An after-slab concrete pour for 9th floor walls and columns, 45 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

Thursday, August 21 

  • A wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Friday, August 22

  • Rebar delivery from 7:00 am.
  • 14th  Floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 1o:00 am.
  • An after-slab concrete pour for 9th floor walls and columns, 45 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

 NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule – August 9 – 15

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for August 9 – 15, 2014. Updated August 13.

Please click here for general information on concrete pours.

Concrete pour at Backstage Condominium, August 7, 2014

Concrete pour at Backstage Condominium, August 7, 2014

Saturday, August 9

  • 12th Floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 9:30 am.
  • Concrete Finishing until to 10:00 pm.

Monday, August 11

  • A  12th and 13th floor wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 1:00 pm.

Tuesday, August 12

  • Rebar delivery from 7:00 am.
  • 13th  Floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 1o:00 am.
  • An after-slab concrete pour for 9th floor walls and columns, 45 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

Wednesday, August 13

  • 13th Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 1o:00 am.
  • An after-slab concrete pour for 9th floor walls and columns, 45 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

Thursday, August 14 – UPDATED

  • A 13th floor wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 1:00 pm.
  • Toro Aluminum will be delivering a tractor trailer load of windows at 3:00 pm. The tractor trailer will be occupying the south curb lane of The Esplanade during unloading.
  • Eastbound traffic from Yonge Street will be impacted temporarily. Pedestrians will be able to have access through the site during unloading. We apologize any inconvenience this may cause.

Friday, August 15

  • Rebar delivery from 7:00 am.
  • 13th  Floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 1o:00 am.
  • An after-slab concrete pour for 9th floor walls and columns, 45 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

 

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Backstage Construction Schedule – August 2 – 9

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for August 2 – 8, 2014.

Backstage Condo, August 1 2014

Backstage Condo, August 1 2014

Please click here for general information on concrete pours.

Saturday, August 2

  • A 5-man crew form Italform removing forming from the west side of the building, from  9:00 am. 
  • A 2-man crew from Dominus removing the concrete curd on the 5th floor, from 9:00 am.

Monday, August 4 – Site Closed – Civic Holiday

Tuesday, August 5

  • A  11th and 12th floor wall and column concrete pour, by subcontractor Italform (45 metres of concrete), scheduled to run from 12:30 pm.

Wednesday, August 6

  • 12th Floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 1o:00 am.
  • An after-slab concrete pour for 9th floor walls and columns, 35 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

Thursday, August 7

  • Rebar delivery from 7:00 am.
  • 11th  Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 1o:00 am.
  • An after-slab concrete pour for 9th floor walls and columns, 35 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

 Friday, August 8

  • Rebar delivery from 7:00 am.
  • A 12th and 13th floor wall and column concrete pour, by subcontractor Italform (35 metres of concrete), scheduled to run from 12:30 pm.

Saturday, August 9 – updated

  • 12th Floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 9:30 am.
  • Concrete Finishing until to 10:00 pm.

NOTES:

  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
  • Concrete pour schedules and times are subject to weather conditions.
  • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
  • Concrete trucks must keep their engines running during the pouring process.

Backstage reaches 10th storey — Construction Schedule – July 26 – August 1

Backstage has reached it’s 10th floor wall and concrete pouring will commence for the  11th floor slab on July 29. 

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for July 26 – August 1, 2014.

 

Backstage condominium: concrete truck pouring concrete.

Backstage condominium: concrete truck unloading.

Please click here for general information on concrete pours.

Saturday, July 26

  • A forming crew working on 10th floor wall and 11th floor slab from 9:00 am. 
  • Dominus crew doing construction housekeeping on-site.

Monday, July 28

  • A  10th floor wall and column concrete pour, by subcontractor Italform (35 metres of concrete), scheduled to run from 12:30 pm.

 Tuesday, July 29

  • Rebar delivery from 7:00 am.
  •  11th Floor slab concrete pour #1, by subcontractor Italform, scheduled to begin at 1o:00 am.
  • An after-slab concrete pour for 9th floor walls and columns, 35 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

Wednesday, July 30

  • 11th  Floor slab concrete pour #2, by subcontractor Italform, scheduled to begin at 1o:00 am.
  • An after-slab concrete pour for 9th floor walls and columns, 35 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

Thursday, July 31

  • A 11th  floor wall and column concrete pour, by subcontractor Italform (35 metres of concrete), scheduled to run from 1:00 pm.

 Friday, August 1

  • Rebar delivery from 7:00 am.
  • 11th Floor slab concrete pour #3, by subcontractor Italform, scheduled to begin at 1o:00 am.
  • An after-slab concrete pour for 10th floor walls and columns, 35 metres of concrete, to begin following the main slab pour.
  • Concrete Finishing until to 10:00 pm.

NOTES:

      • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.
      • Concrete pour schedules and times are subject to weather conditions.
      • There may be some short-term impacts on traffic flow as concrete trucks are moved into position.
      • Concrete trucks must keep their engines running during the pouring process.

1 The Esplanade Construction Schedule for October 10 – 14

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condo for the week of October 10 – 14, 2011

Posted October 7, 2011

1 The Esplanade – L Tower parking and Backstage condo.

Monday, October 10

Happy Thanksgiving!

Tuesday, October 11

Sub-contractor Deep Foundation will be removing the crane at 1 the Esplanade. The float will be coming between 10:00 am and 1:00 pm under police escort down The Esplande.

There will be significant impact on pedestrian and vehicular traffic along The Esplanade.

Please Note: The bulk excavating is schedule to start this week. Therefore there will be high impact on traffic at Scott Street and The Esplanade due to a large number of dump trucks coming to and leaving the site.

At this time there is no firm start date. This site will be updated as soon as this information becomes available.