Backstage Construction Schedule – January 21 – 25

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  January 21 – 25, 2013

Posted January 18, 2013

Monday, January 21 – Crane installation – Vehicular Road Closure

  • Italforming will be erecting tower crane today: The Esplanade will closed to vehicular traffic per hoisting permit 58988001 as approved by City of Toronto.
  • Pedestrian access through the site will remain open.
  • Please note: The will be significant construction traffic to the site: one 300 ton mobile crane and two support trucks and nine semi-trailer trucks bring in the tower crane and related components throughout the day.

Tuesday, January 22

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator, 5 dump trucks 14 loads each, for an estimated  total of 70 loads.

Wednesday, January 23

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator, 5 dump trucks 14 loads each, for an estimated  total of 70 loads.

Thursday, January 24

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator, 5 dump trucks 14 loads each, for an estimated  total of 70 loads.

Friday, January 25 

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • GFL Excavating will be removing material with the Long Reach excavator, 5 dump trucks 14 loads each, for an estimated  total of 70 loads.

NOTES:Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control

Please click here for a downloadable construction summary: L Tower & Backstage Construction Summary Jan 21 – 25

Backstage Construction Schedule – January 14 – 18

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  January 14 – 18, 2013

Posted January 11, 2013

Monday, January 14

  • GFL Excavating will be preparing material using the hydraulic breaker.

Tuesday, January 15

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • There will be a delivery of reinforcing steel at 7:30 am.
  • Italforming will be bringing in a boom truck in to unload reinforcing steel.

 

Wednesday, January 16

  • GFL Excavating will be preparing material using the hydraulic breaker.
  • Italforming may be beginning to pour concrete for the crane base – to be confirmed by 5:00 pm, Monday, January 14. 
  • If the concrete pour begins there will be a concrete pump placing 120 meters of concrete.

Thursday, January 17

  • GFL Excavating will be preparing material using the hydraulic breaker.

Friday, January 18 

  • GFL Excavating will be preparing material using the hydraulic breaker.

Please note:

  • There may be some short-term disruptions to vehicular and pedestrian traffic while concrete and delivery trucks are moved into position and unloaded.
  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control

Please click here for a downloadable construction summary: 

Backstage Construction Schedule – January 7 – 11

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for  January 7 – 11, 2013

Posted January 4 2013

Monday, January 7

  • GFL Excavating will be operating the Long Reach excavator removing material. There will be 6 dump trucks doing 14 loads each, for an expected total of 84 loads.
  • GFL Excavating will be preparing material using the hydraulic breaker.

Tuesday, January 8

  • GFL Excavating will be operating the Long Reach excavator removing material. There will be 6 dump trucks doing 14 loads each, for an expected total of 84 loads.
  • GFL Excavating will be preparing material using the hydraulic breaker.
  • Aecon Utilities will be working at Yonge and the Esplanade installing conduits for temporary high voltage service.
  • City of Toronto contractor — OJCR Construction — is expected to be on-site to test water-main and sanitary sewers. No disruptions to traffic are anticipated.

Wednesday, January 9

  • GFL Excavating will be operating the Long Reach excavator removing material. There will be 6 dump trucks doing 14 loads each, for an expected total of 84 loads.
  • GFL Excavating will be preparing material using the hydraulic breaker.
  • Aecon Utilities will be working at Yonge and the Esplanade installing conduits for temporary high voltage service.

Thursday, January 10

  • GFL Excavating will be operating the Long Reach excavator removing material. There will be 6 dump trucks doing 14 loads each, for an expected total of 84 loads.
  • GFL Excavating will be preparing material using the hydraulic breaker.
  • Aecon Utilities will be working at Yonge and the Esplanade installing conduits for temporary high voltage service.

Friday, January 11 

  • GFL Excavating will be operating the Long Reach excavator removing material. There will be 6 dump trucks doing 14 loads each, for an expected total of 84 loads.
  • GFL Excavating will be preparing material using the hydraulic breaker.
  • Aecon Utilities will be working at Yonge and the Esplanade installing conduits for temporary high voltage service.

Please note:

  • There may be some short-term disruptions to vehicular and pedestrian traffic while dump trucks are moved into position and loaded.
  • Aecon Utilities work may also cause short-term disruptions to  to vehicular and pedestrian traffic.
  • Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control

Please click here for a downloadable construction summary: L Tower & Backstage Construction Jan 7-11

Backstage Construction Schedule – December 31 – January 4

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for December 31, 2012 – January 4, 2013

Updated January 3 2013

Monday, December 31

  • No construction activity scheduled.

Tuesday, January 1

  •  No construction activity scheduled.

Wednesday, January 2

  • No construction activity scheduled.

Thursday, January 3

  • GFL Excavating will be preparing material using the hydraulic breaker.

Friday, January 4 – UPDATED

  • GFL Excavating will be operating the Long Reach excavator removing material. There will be 5 dump trucks doing 14 loads each, for an expected total of 70 loads.

Please note:

There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control

Please click here for a downloadable construction summary: L Tower & Backstage Construction December 31 – January 4

Recap on Dec 5 Long Reach Back-hoe delivery

UPDATE: The Long Reach Back-hoe that was scheduled to arrive Wednesday, December 5, under police escort between 6:20 am and 7:00 am. It actually arrived at 5:30 am as the City of Toronto permit stipulated that the semi-trailer float (truck) had to be out of the downtown core prior to 6:00 am. Unfortunately we did not receive accurate information on the timing of the delivery.

On December 4 we were advised by subcontractor GFL Excavating that the back-hoe was coming early in the morning, instead of the originally and preferred plan to deliver it at midday. GFL could not get a permit for midday because City of Toronto staff considered the impact on daytime traffic would be too onerous. The permit was issued for 5 am to 6 am delivery and GFL was instructed by the City and the Police to have their large delivery truck off the site an out of the downtown by 6:00 am.

In this case the regulations for large deliveries trumped the regulations for construction noise; the regulating bodies determined that the traffic regulations trumped the standard construction noise regulations.  

Please click here for a revised Backstage – 1 The Esplanade construction schedule.

 
Please click here for a revised Backstage – 1 The Esplanade construction schedule.

Backstage Construction Schedule – November 26 – 30

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for November 26 – 30, 2012

Updated November 29

We have been advised that City of Toronto’s subcontractor — OJCR Construction — will begin sanitary sewer and water-main work on The Esplanade on  Wednesday, November 28. We have been advised that:

  1. Pedestrian traffic will remain open. 
  2. Eastbound Vehicular Traffic will be closed from 7:00 am to 7:00 pm      

We will update this information when we can. Please check back here for updates

Or please contact 

Joseph Sinopoli
Toronto Water
416-338-6526 Office

Thursday, November 29 – WORK CANCELLED 

  • CANCELLED A large backhoe (a “long reach”) will be delivered under police escort to the site at midday. There will be temporary disruptions to traffic on Front Street East, Scott Street and The Esplanade. 

Friday, November 30

  • CANCELLED Set-up of the long-reach on site

NOTE: The “Long Reach” Backhoe  will now arrive on Saturday, December 1. Please click here for details. 

Please note:

There may be some short-term disruptions to vehicular traffic while delivery trucks are unloaded.

Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control

Please click here for a downloadable construction summary: L Tower & Backstage Construction November 26 – 30

Backstage – 1 The Esplanade – Construction Schedule Feb 6 – 10

This is the current construction schedule for 1 The Esplanade – L Tower parking and Backstage condominium for February 6 – 10, 2012

Updated February 8, 2012

Monday, February 6

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.
  • Sub-contractor, GFL will be delivering a backhoe.
  • Sub-contractor, GFL and will have six (6) dump trucks removing material from the site, doing five (5) rounds each.

Tuesday, February 7

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.
  • Sub-contractor, GFL and will have six (6) dump trucks removing material from the site, doing five (5) rounds each.

Wednesday, February 8

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.

Thursday, February 9

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.
  • UPDATED: Sub-contractor, GFL is scheduled to have 4 dump trucks doing 5 rounds each, removing material from the site. 

Friday, February 10

  • Sub-contractor, Deep Foundation drilling caissons and piles.
  • Seven (7) loads of concrete.
  • UPDATED: Sub-contractor, GFL is scheduled to have 4 dump trucks doing 5 rounds each, removing material from the site. 

* * *

NOTES:

A Paid Duty Police Officer is on-site daily Monday to Friday, from 7:00 am to 4:00 pm daily to assist with traffic control.