Backstage Construction Update – February 27 – March 4, 2016
February 26, 2016 Leave a comment
This is the construction schedule for 1 The Esplanade, Backstage condominium – for February 27 – March 4, 2016
Suites up to the 19th floor are ready for the occupancy as move-ins to Backstage continue through the weekend and the coming week. Exterior work, to install the podium cladding and balcony glazing, that was delayed by inclement weather continues. Occasional deliveries will occur as needed with minimal impact on the street or traffic flows. The 3rd and 4th floor parking levels will have their lines painted prior to opening to new residents. Work also continues on the interior of the building the remaining unfinished suites for occupancy.
Please check back at ltowerconstructioninfo.com for updates.
Please click on the link to download a printable PDF Summary Construction Schedule for February 27 – March 4: Backstage Construction Summary-Feb 27-Mar 4-2016
Saturday, February 27
- Move-ins continue.
- Interior suite work.
- Housekeeping work on site.
Sunday, February 28
- Possible move-ins.
Monday, February 22
- Move-ins continue.
- Interior suite work: drywall and final finishing.
- Podium cladding installation and window installation on the southeast elevation.
Tuesday, March 1
- Kitchen cabinet delivery.
- Move-ins continue.
- Interior suite work: drywall and final finishing.
- Podium cladding installation and window installation on the southeast elevation.
- Third and fourth floor garage floors painted in preparation for use by new residents.
Wednesday, March 2
- Move-ins continue.
- Interior suite work: drywall and final finishing.
- Podium cladding installation and window installation on the southeast elevation.
- Third and fourth floor garage floors painted in preparation for use by new residents.
Thursday, March 3
- Move-ins continue.
- Interior suite work: drywall and final finishing.
- Podium cladding installation and window installation on the southeast elevation.
Friday, March 4
- Move-ins continue.
- Interior suite work: drywall and final finishing.
- Podium cladding installation and window installation on the southeast elevation.