Backstage Construction Update – December 18, 2017 update

This is a construction update for Backstage Condominium, 1 The Esplanade, December 18, 2017 

Our best wishes for the Holiday Season.

This is our last full post for 2017. We expect to provide a concluding update just prior to the New Year. 

The Esplanade on a cold December day, with sidewalk work halted due to weather.



Exterior Work – At Grade

Work on the sidewalk is nearing completion along the south side of The Esplanade but recent cold weather has slowed its progress. This week crews, with the expected milder temperatures, work crews will resume work. It is hoped that the sidewalk pavers can be completed to The Esplanade as soon as possible. Work on the front entranceway to Backstage may take longer, given the uncertainties of the weather.

Weather permitting, work will aim to finish the sidewalk to Yonge Street this week.

The completed concrete section of the sidewalk at Backstage.


Interior Work – Future Path & Public Exhibit Space

Work on the interior of the future PATH connection and Public Exhibit Space has made signiifcant progress in the first half of this month. Insulation has been installed. Drywall work is well advanced in the PATH and underway in the future Public Exhibit Space. The stairway to the ground floor public lobby area has been installed. Concrete will be poured into the steps in the coming weeks. Lighting fixtures will also begin to be installed in the next few weeks. An elevator has already been installed that will serve the PATH and Public Exhibit Space, which is expected to open in 2018. 

The interior section of the future PATH as insulation and drywall work comes closer to completion.

The interior of the future PATH showing the south wall with completed insulation.

Stepping up to the future Public Exhibit Space and PATH.


We will back just before the New Year with a wrap-up posting. Have a safe and happy Holiday Season.




 

 

 

Backstage Construction Update – December 2017 update

This is a construction update for Backstage Condominium, 1 The Esplanade, December, 2017 

Work on the exterior of Backstage is very near complete, with the remaining focus being the finishing of the sidewalk along The Esplanade. 


The completed outdoor amenity space at Backstage, looking west.

Exterior Work – Podium Deck

Landscaping and plantings for the outdoor amenity space on the podium deck are complete. Only barbecue fixtures and railing for the outdoor lap pool remain to be installed. 

The landscaped outdoor amenity space looking east.

The outdoor amenity space looking northwest across to the pool to L Tower.


Exterior Work – At Grade

Work on the sidewalk is nearing completion. Trees have been installed along the sidewalk. Granite pavers are being installed, mirroring the north side of The Esplanade along the frontage of  the L Tower. Asphalt has been laid down to the curb edge. Noting that the whole roadway between Yonge and Scott is planned to be resurfaced next year after the winter. 

Granite paving stones being installed along The Esplanade frontage of Backstage.

Asphalt has been filled in to the curb edge.

The concrete and asphalt work is done at the entrance to the TPA Green P lot.

Interior Work – Future Path & Public Exhibit Space

Work on the interior of the future PATH connection and Public Exhibit Space continues to make steady progress. Insulation has been installed. Work on the ceilings is underway and drywall work is about to begin on the interior walls. The staircase that will connect the main floor of the public lobby to the PATH and Public Exhibit Space has been installed and finishing work on it will continue this month. An elevator has been installed that will also serve the PATH. 

Work on the interior PATH is moving forward at a steady pace.

Staircase installed that leads from the public and retail entrance to the interior PATH.


We will be continue to provide construction updates while exterior work remains to be completed. Please check back here at ltowerconstructioninfo.com for regular updates.




And we will leave this month’s update with another view of the outdoor amenity space:

The curving path between the green lawn and tree plantings on the outdoor amenity space.

 

 

%d bloggers like this: