Work on the outdoor amenity space and pool in progress at Backstage

Exterior Work

Work on the podium is being ramped up now that the nice weather is finally here. The porcelain tile is being installed on the east ‘fins’ of the tower. The tiling of outdoor swimming pool has begun and will continue through the coming week or more, weather permitting. Work is starting on some of the block work on the south end of the podium which will be supporting the concrete deck along the backside of the pool.

Tiling begins on the outdoor pool at Backstage

Construction management is continuing to work with their landscape contractor to plan and schedule the finishes for the podium deck. They are still working with the City of Toronto to finalize the landscape permit before proceeding on finishing the sidewalk and exterior at street level.

Work continues on installing the porcelain tiling on the east face of the tower at Backstage


 

Installing the whirlpool, just inside from the outdoor amenity space and pool at Backstage

Interior Work 

Delivery of the pre-finished whirlpool has been made and it is being installed this week, with finishing continuing through the next week. The first order of mirrors have been installed in the fitness/yoga areas, with the more coming soon. Furniture for the amenity areas will arrive the first week of May.

Finishing touches on the indoor amenity spaces at Backstage include the installation of mirrors in the Gym and Yoga Room


We will be continue to provide construction updates while work remains to be completed through the remainder of the spring. Please check back here at ltowerconstructioninfo.com for regular updates.




And we will leave this month’s update with this – the view from the 36th floor: 

Looking down over Union Station from the 36th floor at Backstage

 