Backstage Construction Update – December 19, 2016 – January 3, 2017
December 19, 2016 Leave a comment
This is a construction update for Backstage Condominium, 1 The Esplanade, December 19, 2016 – January 3, 2017
HAPPY HOLIDAYS

Railings for the podium deck, which are set to begin being installed the week of December 19, weather permitting.
Monday, December 19
- Exterior work as weather permits: porcelain tile installation east tower, railing installation on the podium deck, finishing work on the podium.
- Interior work: finishing work in amenity areas and podium level hallways.
Tuesday, December 20
- Exterior work as weather permits: porcelain tile installation east tower, railing installation on the podium deck, and finishing work on the podium.
- Interior work: finishing work in amenity areas and podium level hallways.

Progress continues, weather permitting, on installing porcelain tiles on the east face of the tower.
Wednesday, December 21
- Exterior work as weather permits: porcelain tile installation east tower, railing installation on the podium deck, and finishing work on the podium.
- Interior work: finishing work in amenity areas and podium level hallways.
Thursday, December 22
- Exterior work as weather permits: porcelain tile installation east tower, railing installation on the podium deck, and finishing work on the podium.
- Interior work: finishing work in amenity areas and podium level hallways.
Friday, December 23
- Exterior work as weather permits: porcelain tile installation east tower, railing installation on the podium deck, and finishing work on the podium.
- Interior work: finishing work in amenity areas and podium level hallways.

Heaters installed to keep the outdoor pool concrete at a constant temperature which is required to insure waterproofing adheres to the surface.
Happy Holidays – Site Closed December 24 – January 2
There will no scheduled construction work from December 24 through January 2.
Happy New Year
Construction work will resume at Backstage on January 3, 2017.
NOTE: Signalized intersection at The Esplanade & Yonge
City of Toronto contractors have been working to install the footings and electrical conduit for the traffic signal that will be installed at Yonge and The Esplanade. As well, the former concrete median has been demolished. When this work is complete there will be a signalized pedestrian crossing to the GO Bus Station and the west side of Yonge Street. This was identified as key deliverable in the original development consultations for the L Tower and Backstage.
Work on the sidewalk on the south side of the The Esplanade, in front of Backstage, will proceed in the New Year, once the City has completed necessary work for the traffic signal and when weather permits.

Median removed by City of Toronto contractors, in preparation for the signalized pedestrian crossing at Yonge and The Esplanade