Backstage Construction Update – December 5 – 11, 2016
December 5, 2016 Leave a comment
This is a construction update for Backstage Condominium, 1 The Esplanade, December 5 – 11, 2016
Work on the podium deck has focussed on parging and waterproofing on the surface of the outdoor pool under the protective cover of the tenting. The installation of porcelain tiles on the tower’s east face continues.
Interior finishing work in the amenity spaces continues this week with a focus on installing stone cladding on the fireplaces, completing wall panelling, and installing flooring. In the lower corridors carpet installation is close to being completed in the corridors on floors 2, 3, 4, 5 and 7.
Please check back here at ltowerconstructioninfo.com for regular updates.
Monday, December 5
- Porcelain tile installation on the east tower.
- Balcony railing installation continues on the west tower.
- Podium deck work on the outdoor pool under the tent.
- Finishing work in amenity areas.
Tuesday, December 6
- Porcelain tile installation on the east tower.
- Balcony railing installation continues on the west tower.
- Podium deck work on the outdoor pool under the tent.
- Finishing work in amenity areas.
Wednesday, December 7
- Porcelain tile installation on the east tower.
- Balcony railing installation continues on the west tower.
- Podium deck work on the outdoor pool under the tent.
- Finishing work in amenity areas.
Thursday, December 8
- Porcelain tile installation on the east tower.
- Balcony railing installation continues on the west tower.
- Podium deck work on the outdoor pool under the tent.
- Finishing work in amenity areas.
Friday, December 9
- Porcelain tile installation on the east tower.
- Balcony railing installation continues on the west tower.
- Podium deck work on the outdoor pool under the tent.
- Finishing work in amenity areas.
Saturday, December 10
- No scheduled work though move-ins are possible.
Sunday, December 11
- No work on site though move-ins are possible.