Backstage Construction Update – December 19, 2016 – January 3, 2017
December 19, 2016 Leave a comment
This is a construction update for Backstage Condominium, 1 The Esplanade, December 19, 2016 – January 3, 2017
HAPPY HOLIDAYS

Railings for the podium deck, which are set to begin being installed the week of December 19, weather permitting.
Monday, December 19
- Exterior work as weather permits: porcelain tile installation east tower, railing installation on the podium deck, finishing work on the podium.
- Interior work: finishing work in amenity areas and podium level hallways.
Tuesday, December 20
- Exterior work as weather permits: porcelain tile installation east tower, railing installation on the podium deck, and finishing work on the podium.
- Interior work: finishing work in amenity areas and podium level hallways.

Progress continues, weather permitting, on installing porcelain tiles on the east face of the tower.
Wednesday, December 21
- Exterior work as weather permits: porcelain tile installation east tower, railing installation on the podium deck, and finishing work on the podium.
- Interior work: finishing work in amenity areas and podium level hallways.
Thursday, December 22
- Exterior work as weather permits: porcelain tile installation east tower, railing installation on the podium deck, and finishing work on the podium.
- Interior work: finishing work in amenity areas and podium level hallways.
Friday, December 23
- Exterior work as weather permits: porcelain tile installation east tower, railing installation on the podium deck, and finishing work on the podium.
- Interior work: finishing work in amenity areas and podium level hallways.

Heaters installed to keep the outdoor pool concrete at a constant temperature which is required to insure waterproofing adheres to the surface.
Happy Holidays – Site Closed December 24 – January 2
There will no scheduled construction work from December 24 through January 2.
Happy New Year
Construction work will resume at Backstage on January 3, 2017.
NOTE: Signalized intersection at The Esplanade & Yonge
City of Toronto contractors have been working to install the footings and electrical conduit for the traffic signal that will be installed at Yonge and The Esplanade. As well, the former concrete median has been demolished. When this work is complete there will be a signalized pedestrian crossing to the GO Bus Station and the west side of Yonge Street. This was identified as key deliverable in the original development consultations for the L Tower and Backstage.
Work on the sidewalk on the south side of the The Esplanade, in front of Backstage, will proceed in the New Year, once the City has completed necessary work for the traffic signal and when weather permits.

Median removed by City of Toronto contractors, in preparation for the signalized pedestrian crossing at Yonge and The Esplanade
Backstage Construction Update – December 12 – 18, 2016
December 12, 2016 Leave a comment
This is a construction update for Backstage Condominium, 1 The Esplanade, December 12 – 18, 2016
Monday, December 12
- Exterior work as weather permits on the tower and podium deck.
- Finishing work in amenity areas and podium level hallways.
Tuesday, December 13
- Exterior work as weather permits on the tower and podium deck.
- Finishing work in amenity areas and podium level hallways.
Wednesday, December 14
- Exterior work as weather permits on the tower and podium deck.
- Finishing work in amenity areas and podium level hallways.
Thursday, December 15
- Exterior work as weather permits on the tower and podium deck.
- Finishing work in amenity areas and podium level hallways.
Friday, December 16
- Exterior work as weather permits on the tower and podium deck.
- Finishing work in amenity areas and podium level hallways.
Saturday, December 17
- No scheduled work.
Sunday, December 18
- No work onsite.
Sony Centre Plaza Public Art – Dream Ballet Triptych revealed
December 12, 2016 Leave a comment
L Tower 8 The Esplanade – Sony Centre Plaza Update – December update.
On December 8th the major new public art installation in the Sony Centre Plaza was revealed: Triptych Dream Ballet by Toronto artist Harley Valentine is now fully revealed. Dream Ballet is the centrepiece of the Claude Cormier + Associés designed plaza. As with the adjacent redesigned Bercy Park (also by Claude Cormier), some finishing and landscaping work remains to be complete before the Plaza is “finished” but the artwork is easily viewable by all as the new gateway to the St. Lawrence Market neighbourhood and Old Town Toronto.
The reveal event on December 8th featured remarks from Alfredo Romano, President of Castlepoint Numa, artist Harley Valentine, and Rex Harrington, former Principal Dancer of the National Ballet who performed for many years at the Sony Centre. Attendees included Suzanne Kavanagh, President of the St. Lawrence Neighbourhood Association, and Al Smith, Executive Director, of the St. Lawrence Market Neighbourhood BIA.

Alfredo Romano, President of Castlepoint Numa, speaking at the Dream Ballet Triptych “reveal” on December 8.
The Esplanade and Yonge
City contractors are at work on installing footings for new traffic lights and street lights at the corner of Yonge and The Esplanade. They are also taking the concrete median apart that divides Yonge Street. This work is preparation for the new controlled pedestrian crossing at The Esplanade, which was one of the public realm deliverables of the L Tower redevelopment.
Check back here at ltowerconstructioninfo.com for updates.
Backstage Construction Update – December 5 – 11, 2016
December 5, 2016 Leave a comment
This is a construction update for Backstage Condominium, 1 The Esplanade, December 5 – 11, 2016
Work on the podium deck has focussed on parging and waterproofing on the surface of the outdoor pool under the protective cover of the tenting. The installation of porcelain tiles on the tower’s east face continues.
Interior finishing work in the amenity spaces continues this week with a focus on installing stone cladding on the fireplaces, completing wall panelling, and installing flooring. In the lower corridors carpet installation is close to being completed in the corridors on floors 2, 3, 4, 5 and 7.
Please check back here at ltowerconstructioninfo.com for regular updates.
Monday, December 5
- Porcelain tile installation on the east tower.
- Balcony railing installation continues on the west tower.
- Podium deck work on the outdoor pool under the tent.
- Finishing work in amenity areas.
Tuesday, December 6
- Porcelain tile installation on the east tower.
- Balcony railing installation continues on the west tower.
- Podium deck work on the outdoor pool under the tent.
- Finishing work in amenity areas.
Wednesday, December 7
- Porcelain tile installation on the east tower.
- Balcony railing installation continues on the west tower.
- Podium deck work on the outdoor pool under the tent.
- Finishing work in amenity areas.
Thursday, December 8
- Porcelain tile installation on the east tower.
- Balcony railing installation continues on the west tower.
- Podium deck work on the outdoor pool under the tent.
- Finishing work in amenity areas.
Friday, December 9
- Porcelain tile installation on the east tower.
- Balcony railing installation continues on the west tower.
- Podium deck work on the outdoor pool under the tent.
- Finishing work in amenity areas.
Saturday, December 10
- No scheduled work though move-ins are possible.
Sunday, December 11
- No work on site though move-ins are possible.