Backstage Construction Update – November 28 – December 4, 2016

This is a construction update for Backstage Condominium, 1 The Esplanade, November 28 – December 4, 2016

Work on the podium deck and east tower porcelain tile continues this week.

Work on the podium deck and east tower porcelain tile continues this week.


Work on the podium deck has focussed on completing parging or the application of a thin coat of a cementitious mortar to the pool’s concrete to refine the surface in preparation for waterproofing, which will commence this week. Work also continues on installing the porcelain tiles on the tower’s east face.

Work continues in the indoor amenity areas. Fireplaces are ready to be measured for stone cladding this week. While flooring in the 5th floor party room scheduled to begin in the next week. Steam units for steam rooms are installed and have been enclosed, and ready for tiling this week.
In the lower corridors carpeting is being installed in the corridors on floors 2, 3, 4, 5 and 7. Wallpaper and painting has been completed.
Another round of inspections on unoccupied units has been completed. This week should see more of the remaining unoccupied suites released for occupancy.

Please check back here at ltowerconstructioninfo.com for regular updates.


The pool is being prepared for waterproofing under the protection of the tenting.

The pool is being prepared for waterproofing under the protection of the tenting.


Monday, November 28

  • Porcelain tile installation at the top of the east tower.
  • Balcony railing installation continues on the west tower.
  • Podium deck work on the outdoor pool under the tent.
  • Finishing work in amenity areas.

Tuesday, November 29

  • Porcelain tile installation at the top of the east tower.
  • Balcony railing installation continues on the west tower.
  • Podium deck work on the outdoor pool under the tent.
  • Finishing work in amenity areas.

Wednesday, November 30

  • Porcelain tile installation at the top of the east tower.
  • Balcony railing installation continues on the west tower.
  • Podium deck work on the outdoor pool under the tent.
  • Finishing work in amenity areas.

Thursday, December 1

  • Porcelain tile installation at the top of the east tower.
  • Balcony railing installation continues on the west tower.
  • Podium deck work on the outdoor pool under the tent.
  • Finishing work in amenity areas.

Friday, December 2

  • Porcelain tile installation at the top of the east tower.
  • Balcony railing installation continues on the west tower.
  • Podium deck work on the outdoor pool under the tent.
  • Finishing work in amenity areas.

Hallways on the lower floors are being completed.

Hallways on the lower floors are being completed.


Saturday, December 3

  • No scheduled work though move-ins are possible.

Sunday, December 4

  • No work on site though move-ins are possible.

Amenity room panelling installed

Amenity room panelling installed


 

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: